INDOT contract R-43234-A bid tabulation
SMALL STRUCTURE REPLACEMENT. Let by Indiana DOT on February 12, 2025, Orange, Vincennes. 8 bids received; low bid $540,364 by Crider & Crider Inc.
- Owner
- Indiana DOT
- Letting
- 12 FEB 2025
- Pay items
- 62
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Crider & Crider Inc | $540,364 | Low |
| 2 | E & B Paving LLC | $567,633 | +5.0% |
| 3 | Lutgring Brothers Inc | $586,000 | +8.0% |
| 4 | Milestone Contractors LP | $621,150 | +15% |
| 5 | CLR Inc | $631,819 | +17% |
| 6 | Force Construction Co Inc | $695,242 | +29% |
| 7 | C & R Construction and Consulting LLC | $749,019 | +39% |
| 8 | Hall Contracting of Kentucky Inc | $853,772 | +58% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Crider & Crider Inc | 2. E & B Paving LLC | 3. Lutgring Brothers Inc | 4. Milestone Contractors LP | 5. CLR Inc | 6. Force Construction Co Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $17,850 | $14,000 | $14,000 | $11,000 | $35,438 | $6,619.00 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $24,229 | $27,500 | $28,227 | $30,000 | $28,500 | $34,000 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $31,790 | $17,000 | $17,000 | $18,000 | $18,508 | $24,580 |
| 0011 | Present structure, remove, structure no. 11 (202-51330) | LS | 1 | $19,336 | $37,000 | $15,000 | $30,000 | $38,356 | $29,760 |
| 0012 | Excavation, common (203-02000) | CYS | 175 | $170.00 | $125.00 | $96.00 | $65.00 | $42.00 | $155.00 |
| 0013 | Excavation, rock (203-02010) | CYS | 104 | $124.00 | $75.00 | $133.00 | $110.00 | $140.00 | $141.00 |
| 0014 | Borrow (203-02070) | CYS | 1,935 | $29.75 | $25.00 | $43.00 | $50.00 | $24.00 | $43.00 |
| 0015 | Embankment foundation soils treatment (203-07042) | SYS | 388 | $50.50 | $60.00 | $52.00 | $50.00 | $45.00 | $54.00 |
| 0016 | Pump around (205-11626) | EACH | 1 | $17,000 | $8,000.00 | $16,000 | $18,000 | $28,000 | $7,842.00 |
| 0017 | Stormwater management budget (205-12108) | DOL | 15,815 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0018 | Stormwater management implementation (205-12616) | LS | 1 | $6,521.00 | $23,000 | $11,000 | $7,200.00 | $1,500.00 | $6,892.00 |
| 0019 | Subgrade treatment, type II (207-08264) | SYS | 81 | $24.00 | $89.00 | $47.00 | $35.00 | $22.00 | $33.00 |
| 0020 | Subgrade treatment, type IC (207-09935) | SYS | 84 | $43.00 | $70.00 | $46.00 | $35.00 | $70.00 | $64.00 |
| 0021 | Structure backfill, type 2 (211-09265) | CYS | 314 | $54.00 | $35.00 | $88.00 | $100.00 | $41.00 | $70.00 |
| 0022 | Flowable backfill, non- removable (213-09269) | CYS | 2 | $550.00 | $800.00 | $500.00 | $800.00 | $550.00 | $796.00 |
| 0023 | Geotextile for pavement, type 2B (214-12239) | SYS | 89 | $7.00 | $12.00 | $12.00 | $7.00 | $18.00 | $14.00 |
| 0024 | Compacted aggregate, no. 2 (301-12231) | CYS | 1 | $320.00 | $550.00 | $900.00 | $800.00 | $200.00 | $479.00 |
| 0025 | Compacted aggregate, no. 8 (301-12233) | CYS | 104 | $86.00 | $82.00 | $118.00 | $125.00 | $76.00 | $60.00 |
| 0026 | Compacted aggregate, no. 53 (303-01180) | TON | 106 | $47.00 | $60.00 | $62.00 | $45.00 | $66.00 | $63.00 |
| 0027 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 766 | $4.00 | $8.50 | $11.00 | $8.00 | $7.75 | $8.70 |
| 0028 | Milling, transition (306-08043) | SYS | 297 | $16.00 | $8.50 | $4.00 | $15.00 | $8.50 | $11.00 |
| 0029 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 94 | $283.00 | $226.00 | $235.00 | $180.00 | $240.00 | $247.00 |
| 0030 | QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041) | TON | 11 | $295.00 | $740.00 | $245.00 | $300.00 | $300.00 | $257.00 |
| 0031 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 33 | $295.00 | $344.00 | $245.00 | $300.00 | $305.00 | $257.00 |
| 0032 | Joint adhesive, surface (401-10258) | LFT | 385 | $2.00 | $1.00 | $1.50 | $1.00 | $1.50 | $1.60 |
| 0033 | Joint adhesive, intermediate (401-10259) | LFT | 25 | $2.00 | $0.88 | $1.50 | $2.00 | $1.85 | $1.60 |
| 0034 | Liquid asphalt sealant (401-11785) | LFT | 385 | $1.00 | $2.45 | $0.75 | $2.00 | $0.75 | $0.80 |
| 0035 | Asphalt for tack coat (406-05520) | TON | 1 | $872.00 | $1.00 | $725.00 | $700.00 | $725.00 | $762.00 |
| 0036 | Cracks in asphalt pavement, fill (408-12028) | TON | 0.10 | $5,500.00 | $22,828 | $4,800.00 | $4,200.00 | $4,800.00 | $5,043.00 |
| 0037 | HMA for approaches, type B (610-07487) | TON | 14 | $355.00 | $402.00 | $295.00 | $185.00 | $295.00 | $310.00 |
| 0038 | Mailbox assembly, reset, single (611-08232) | EACH | 2 | $902.00 | $750.00 | $900.00 | $750.00 | $700.00 | $788.00 |
| 0039 | Riprap, class 1 (616-05688) | TON | 87 | $54.00 | $100.00 | $125.00 | $95.00 | $86.00 | $54.00 |
| 0040 | Geotextile for riprap, type 1A (616-12246) | SYS | 121 | $4.00 | $4.00 | $12.00 | $2.25 | $12.00 | $9.80 |
| 0041 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $1,262.00 | $1,050.00 | $1,050.00 | $200.00 | $225.00 | $1,103.00 |
| 0042 | Mulched seeding, type U (621-06560) | SYS | 2,445 | $3.00 | $2.10 | $2.10 | $6.00 | $3.50 | $2.20 |
| 0043 | Sodding (621-06574) | SYS | 772 | $11.00 | $9.42 | $10.00 | $20.00 | $14.00 | $9.90 |
| 0044 | Computer system equipment (628-11976) | EACH | 1 | $1,803.00 | $700.00 | $1,500.00 | $2,150.00 | $100.00 | $841.00 |
| 0045 | Field office, type D (628-12683) | MOS | 12 | $2,500.00 | $3,000.00 | $2,500.00 | $3,500.00 | $950.00 | $3,782.00 |
| 0046 | Concrete, C , for sinkhole treatment (702-93722) | CYS | 1 | $1,100.00 | $1,800.00 | $900.00 | $1,850.00 | $1,000.00 | $1,405.00 |
| 0047 | Waterproofing membrane type 2 (714-000086) | SFT | 2,400 | $3.75 | $1.90 | $4.00 | $2.00 | $2.00 | $1.90 |
| 0048 | Structure, reinforced concrete, box sections, 10 FT X 6 FT (714-11183) | LFT | 60 | $1,599.00 | $1,750.00 | $2,000.00 | $2,100.00 | $3,307.00 | $2,027.00 |
| 0049 | Road closure sign assembly (801-04308) | EACH | 13 | $180.00 | $277.00 | $277.00 | $280.00 | $198.00 | $291.00 |
| 0050 | Detour route marker assembly (801-06625) | EACH | 34 | $90.00 | $152.00 | $152.00 | $155.00 | $85.00 | $160.00 |
| 0051 | Construction sign, type A (801-06640) | EACH | 17 | $210.00 | $223.00 | $223.00 | $225.00 | $170.00 | $234.00 |
| 0052 | Maintaining traffic (801-06775) | LS | 1 | $6,416.00 | $24,562 | $13,000 | $6,033.25 | $25,755 | $104,000 |
| 0053 | Barricade, type III-B (801-07119) | LFT | 140 | $17.00 | $16.35 | $16.35 | $17.00 | $17.00 | $17.00 |
| 0054 | Reference post (802-04893) | EACH | 2 | $571.00 | $475.00 | $475.00 | $500.00 | $535.00 | $499.00 |
| 0055 | Sign post, square, type 1, reinforced anchor base (802-05701) | LFT | 22 | $60.00 | $50.00 | $50.00 | $50.00 | $33.00 | $53.00 |
| 0056 | Sign, sheet, and supports, remove (802-07059) | EACH | 3 | $631.00 | $525.00 | $525.00 | $550.00 | $290.00 | $552.00 |
| 0057 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 8 | $90.00 | $75.00 | $75.00 | $78.00 | $30.00 | $79.00 |
| 0058 | Sign, ground mounted, reset (802-91122) | EACH | 1 | $2,525.00 | $2,100.00 | $2,100.00 | $2,100.00 | $115.00 | $2,206.00 |
| 0059 | Line, thermoplastic, solid, white, 6 in. (808-75043) | LFT | 770 | $4.00 | $2.21 | $2.21 | $2.25 | $3.50 | $2.30 |
| 0060 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 6 | $48.00 | $63.60 | $75.00 | $30.00 | $85.00 | $31.00 |
| 0061 | Snowplowable raised pavement marker (808-75998) | EACH | 6 | $180.00 | $89.00 | $89.00 | $90.00 | $170.00 | $94.00 |
| 0062 | Line, thermoplastic, broken, yellow, 6 in. (808-96078) | LFT | 385 | $4.00 | $3.01 | $3.01 | $3.00 | $3.40 | $3.20 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of February 12, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.