INDOT contract R-41079-A bid tabulation
NEW INTERCHANGE, BRIDGE AND SIDEWALK CONSTRUCTION. Let by Indiana DOT on May 14, 2025, Allen, Fort Wayne. 6 bids received; low bid $50,912,302 by Milestone Contractors LP.
- Owner
- Indiana DOT
- Letting
- 14 MAY 2025
- Pay items
- 333
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Milestone Contractors LP | $50,912,302 | Low |
| 2 | R L McCoy Inc/Fox Contractors Corp J/V | $52,163,251 | +2.0% |
| 3 | Crider & Crider Inc | $54,792,654 | +8.0% |
| 4 | E & B Paving LLC | $54,808,000 | +8.0% |
| 5 | Phend & Brown Inc | $55,490,236 | +9.0% |
| 6 | Gradex Inc | $57,373,716 | +13% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Milestone Contractors LP | 2. R L McCoy Inc/Fox Contractors Corp J/V | 3. Crider & Crider Inc | 4. E & B Paving LLC | 5. Phend & Brown Inc | 6. Gradex Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $400,000 | $500,000 | $305,000 | $528,120 | $340,000 | $6,304,280 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, PCCP (109-08441) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, pavement traffic markings (109-09377) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0011 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0012 | Mobilization and demobilization (110-01001) | LS | 1 | $2,548,262 | $2,608,000 | $2,670,000 | $2,740,400 | $2,733,200 | $2,868,686 |
| 0013 | Partnering overhead (113-01614) | LS | 1 | $10,000 | $44,000 | $50,000 | $40,000 | $40,000 | $25,000 |
| 0014 | Clearing right-of-way (201-52370) | LS | 1 | $1,019,305 | $1,043,000 | $1,080,000 | $1,096,160 | $905,616 | $1,147,474 |
| 0015 | Pavement removal (202-02240) | SYS | 814 | $52.00 | $65.00 | $35.80 | $106.00 | $31.00 | $31.64 |
| 0016 | Pipe abandon and grout fill (202-02637) | LFT | 1,258 | $108.50 | $43.00 | $106.00 | $108.50 | $108.50 | $90.42 |
| 0017 | Catch basin, remove (202-02928) | EACH | 1 | $835.00 | $770.00 | $818.00 | $835.00 | $835.00 | $303.66 |
| 0018 | Present structure, remove portions, structure no. 2 (202-51328) | LS | 1 | $9,863.00 | $200,000 | $10,000 | $50,000 | $323,500 | $10,000 |
| 0019 | Present structure, remove portions, structure no. 3 (202-51328) | LS | 1 | $9,863.00 | $200,000 | $10,000 | $50,000 | $323,500 | $10,000 |
| 0020 | Inlet, remove (202-91385) | EACH | 12 | $835.00 | $770.00 | $818.00 | $835.00 | $835.00 | $337.87 |
| 0021 | Pipe, remove (202-96133) | LFT | 2,724 | $45.00 | $17.50 | $45.00 | $45.00 | $45.00 | $10.70 |
| 0022 | Excavation, common (203-02000) | CYS | 411,766 | $10.00 | $9.00 | $8.65 | $8.75 | $8.80 | $10.97 |
| 0023 | Borrow (203-02070) | CYS | 219,634 | $15.00 | $9.75 | $15.00 | $15.00 | $16.25 | $0.01 |
| 0024 | Pump around (205-11626) | EACH | 2 | $49,221 | $38,300 | $50,000 | $25,000 | $25,000 | $18,155 |
| 0025 | Stormwater management budget (205-12108) | DOL | 1,044,895 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0026 | Stormwater management implementation (205-12616) | LS | 1 | $14,782 | $171,000 | $546,787 | $553,336 | $541,000 | $369,365 |
| 0027 | SWQCP preparation (205-12618) | LS | 1 | $7,462.00 | $18,700 | $7,933.50 | $3,900.00 | $25,000 | $4,900.00 |
| 0028 | Excavation, foundation, unclassified (206-51230) | CYS | 397 | $133.00 | $70.00 | $140.00 | $100.00 | $53.00 | $140.00 |
| 0029 | Subgrade treatment, type II (207-08264) | SYS | 7,990 | $11.50 | $18.25 | $11.30 | $10.00 | $11.50 | $12.51 |
| 0030 | Subgrade treatment, type III (207-08266) | SYS | 10,262 | $3.00 | $5.50 | $2.80 | $2.00 | $3.00 | $0.74 |
| 0031 | Subgrade treatment, type IC (207-09935) | SYS | 5,579 | $32.00 | $50.00 | $24.90 | $28.50 | $29.53 | $27.35 |
| 0032 | Subgrade treatment, type ibc (207-12635) | SYS | 135,874 | $11.90 | $15.00 | $14.30 | $13.50 | $12.05 | $12.26 |
| 0033 | B borrow (211-02050) | CYS | 3,857 | $50.00 | $55.00 | $45.80 | $47.00 | $48.25 | $38.58 |
| 0034 | Aggregate for end bent backfill (211-06467) | CYS | 187 | $134.00 | $165.00 | $140.00 | $250.00 | $190.00 | $187.00 |
| 0035 | Structure backfill, type 1 (211-09264) | CYS | 5,643 | $46.00 | $61.00 | $45.00 | $46.00 | $46.00 | $35.65 |
| 0036 | Structure backfill, type 2 (211-09265) | CYS | 2,179 | $147.00 | $62.50 | $77.30 | $79.00 | $93.36 | $32.90 |
| 0037 | Flowable backfill, non- removable (213-09269) | CYS | 778 | $236.00 | $330.00 | $216.50 | $233.00 | $234.01 | $160.00 |
| 0038 | Geogrid, type IB (214-11796) | SYS | 2,237 | $3.50 | $3.40 | $3.40 | $3.00 | $3.57 | $2.66 |
| 0039 | Geotextile for pavement, type 2A (214-12238) | SYS | 122,506 | $5.00 | $4.80 | $3.40 | $4.00 | $3.50 | $2.64 |
| 0040 | Geotextile for pavement, type 2B (214-12239) | SYS | 1,549 | $5.00 | $5.00 | $3.50 | $7.50 | $3.50 | $3.03 |
| 0041 | Chemical modification, soils, cement (215-12637) | SYS | 26,261 | $14.90 | $14.50 | $13.30 | $13.35 | $13.35 | $12.26 |
| 0042 | Compacted aggregate, no. 2 (301-12231) | CYS | 92 | $107.00 | $75.00 | $82.30 | $84.00 | $300.00 | $106.11 |
| 0043 | Compacted aggregate, no. 53 (301-12234) | CYS | 21,811 | $59.00 | $71.00 | $64.10 | $60.00 | $75.00 | $39.43 |
| 0044 | Subbase for PCCP (302-06464) | CYS | 217 | $177.00 | $170.00 | $121.00 | $150.00 | $130.00 | $62.15 |
| 0045 | Dense graded subbase (302-07455) | CYS | 228 | $78.00 | $70.00 | $83.60 | $60.00 | $85.50 | $83.06 |
| 0046 | Compacted aggregate, no. 53 (303-01180) | TON | 10,973 | $31.00 | $40.00 | $32.20 | $45.00 | $33.18 | $28.71 |
| 0047 | Widening with HMA, type C (304-07494) | TON | 2,478 | $85.00 | $384.00 | $118.00 | $341.34 | $104.00 | $330.32 |
| 0048 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 1,149 | $10.00 | $11.50 | $11.50 | $1.00 | $11.50 | $2.20 |
| 0049 | Milling, transition (306-08043) | SYS | 1,562 | $5.00 | $10.50 | $10.50 | $1.00 | $10.50 | $2.20 |
| 0050 | QC/QA-HMA, 2, 58S, surface, 9.5 MM (401-000001) | TON | 1,241 | $0.01 | $0.01 | $0.01 | $0.01 | $58.00 | $0.01 |
| 0051 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 2,421 | $142.00 | $132.00 | $142.00 | $132.00 | $128.00 | $132.00 |
| 0052 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 448 | $100.00 | $106.00 | $100.00 | $106.00 | $128.00 | $106.00 |
| 0053 | QC/QA-HMA, 3, 58E, surface, 9.5 MM (401-000008) | TON | 2,777 | $112.00 | $106.00 | $112.00 | $106.00 | $121.00 | $106.00 |
| 0054 | QC/QA-HMA, 4, 58E, surface, 9.5 MM (401-000009) | TON | 174 | $175.00 | $188.00 | $175.00 | $188.00 | $134.00 | $188.00 |
| 0055 | QC/QA-HMA, 2, 58S, intermediate, 19.0 MM (401-000037) | TON | 2,098 | $0.01 | $0.01 | $0.01 | $0.01 | $45.00 | $0.01 |
| 0056 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 2,974 | $105.00 | $132.00 | $105.00 | $132.00 | $104.00 | $132.00 |
| 0057 | QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041) | TON | 731 | $106.00 | $90.00 | $106.00 | $90.00 | $100.00 | $90.00 |
| 0058 | QC/QA-HMA, 3, 58E, intermediate, 19.0 MM (401-000044) | TON | 4,188 | $92.00 | $78.00 | $92.00 | $91.00 | $100.00 | $78.00 |
| 0059 | QC/QA-HMA, 3, 58S, base, 19.0 MM (401-000053) | TON | 24,454 | $90.00 | $78.00 | $90.00 | $88.00 | $93.50 | $78.00 |
| 0060 | QC/QA-HMA, 4, 58E, intermediate, OG, 19.0 MM (401-000067) | TON | 13,384 | $95.00 | $92.00 | $95.00 | $92.00 | $100.00 | $92.00 |
| 0061 | Joint adhesive, surface (401-10258) | LFT | 61,822 | $0.30 | $0.05 | $0.30 | $0.05 | $0.50 | $0.05 |
| 0062 | Joint adhesive, intermediate (401-10259) | LFT | 60,262 | $0.40 | $0.05 | $0.40 | $0.05 | $0.70 | $0.05 |
| 0063 | Inertial profiler, HMA (401-12169) | LS | 1 | $15,000 | $5,000.00 | $15,000 | $5,000.00 | $7,500.00 | $5,000.00 |
| 0064 | HMA spray paver emulsion (401-12664) | TON | 32 | $1,150.00 | $2,130.00 | $1,150.00 | $2,130.00 | $900.00 | $2,130.00 |
| 0065 | Asphalt for tack coat (406-05520) | TON | 98.80 | $800.00 | $440.00 | $800.00 | $440.00 | $800.00 | $440.00 |
| 0066 | QC/QA-PCCP, 10 in. (501-06321) | SYS | 26,826 | $91.75 | $105.00 | $91.75 | $105.00 | $86.00 | $105.00 |
| 0067 | QC/QA-PCCP, 9 in. (501-09107) | SYS | 21,270 | $81.50 | $65.00 | $81.50 | $65.00 | $77.00 | $65.00 |
| 0068 | Inertial profiler, PCCP (501-12171) | LS | 1 | $10,000 | $5,000.00 | $10,000 | $5,000.00 | $7,500.00 | $5,000.00 |
| 0069 | PCCP, 9 in. (502-06457) | SYS | 2,744 | $91.25 | $102.00 | $91.25 | $102.00 | $130.00 | $102.00 |
| 0070 | Retrofitted tie bars (503-03489) | EACH | 156 | $30.00 | $32.00 | $45.00 | $25.00 | $55.00 | $45.00 |
| 0071 | D-1 contraction joint (503-05240) | LFT | 29,225 | $18.50 | $9.20 | $18.50 | $9.00 | $21.00 | $9.00 |
| 0072 | Jointed reinforced concrete pavement, 12 in. (503-12476) | SYS | 694 | $175.00 | $260.00 | $175.00 | $175.00 | $215.00 | $175.00 |
| 0073 | Terminal joint, type HMA (503-12477) | LFT | 238 | $275.00 | $420.00 | $380.00 | $250.00 | $450.00 | $275.00 |
| 0074 | Terminal joint, type PCCP (503-12478) | LFT | 156 | $300.00 | $460.00 | $325.00 | $250.00 | $350.00 | $325.00 |
| 0075 | Expansion joint with load transfer (503-12479) | LFT | 156 | $35.00 | $54.00 | $40.00 | $25.00 | $52.00 | $40.00 |
| 0076 | Guardrail, remove (601-02241) | LFT | 19,576 | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 | $1.50 |
| 0077 | Impact attenuator, ED-W1, TL-3 (601-06233) | EACH | 4 | $13,000 | $13,000 | $13,000 | $13,000 | $13,000 | $7,795.00 |
| 0078 | Guardrail, W-beam, cable terminal anchor (601-06855) | EACH | 6 | $1,250.00 | $1,250.00 | $1,250.00 | $1,250.00 | $1,250.00 | $1,050.00 |
| 0079 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 10,106.25 | $18.50 | $18.50 | $18.50 | $18.50 | $18.50 | $17.60 |
| 0080 | Guardrail, MGS W-beam, double faced, 6 FT 3 in. spacing (601-12284) | LFT | 400 | $28.00 | $28.00 | $28.00 | $28.00 | $28.00 | $27.00 |
| 0081 | Guardrail height transition, MGS (601-12289) | EACH | 13 | $800.00 | $800.00 | $800.00 | $800.00 | $800.00 | $750.00 |
| 0082 | Guardrail transition, MGS with curb (601-12291) | EACH | 6 | $2,700.00 | $2,700.00 | $2,700.00 | $2,700.00 | $2,700.00 | $3,100.00 |
| 0083 | Guardrail transition, MGS without curb (601-12292) | EACH | 10 | $2,600.00 | $2,600.00 | $2,600.00 | $2,600.00 | $2,600.00 | $3,000.00 |
| 0084 | Guardrail end treatment, type OS (601-94689) | EACH | 13 | $2,750.00 | $2,750.00 | $2,750.00 | $2,750.00 | $2,750.00 | $2,800.00 |
| 0085 | Guardrail end treatment, type MS (601-94690) | EACH | 2 | $5,400.00 | $5,400.00 | $5,400.00 | $5,400.00 | $5,400.00 | $5,000.00 |
| 0086 | Barrier delineator (602-06729) | EACH | 64 | $25.00 | $26.00 | $25.00 | $25.00 | $35.00 | $25.00 |
| 0087 | Fence, chain link, 96 in. (603-01932) | LFT | 297 | $27.00 | $27.00 | $27.00 | $27.00 | $27.00 | $55.50 |
| 0088 | Fence, chain link, reset (603-06065) | LFT | 415 | $14.00 | $14.00 | $14.00 | $14.00 | $14.00 | $52.00 |
| 0089 | Fence, pedestrian (603-93373) | LFT | 2,126 | $470.00 | $470.00 | $470.00 | $470.00 | $470.00 | $562.25 |
| 0090 | Temporary fence (603-97461) | LFT | 920 | $12.00 | $12.00 | $12.00 | $12.00 | $12.00 | $17.00 |
| 0091 | HMA for sidewalk (604-05528) | TON | 883 | $90.00 | $115.00 | $90.00 | $115.00 | $117.00 | $115.00 |
| 0092 | Sidewalk, concrete (604-06070) | SYS | 3,954 | $92.00 | $72.00 | $92.00 | $72.00 | $85.00 | $72.00 |
| 0093 | Curb ramp, concrete (604-08086) | SYS | 449 | $182.50 | $125.00 | $182.50 | $125.00 | $260.00 | $125.00 |
| 0094 | Detectable warning surfaces (604-12083) | SYS | 52 | $403.00 | $220.00 | $403.00 | $220.00 | $270.00 | $220.00 |
| 0095 | Curb, concrete (605-06120) | LFT | 3,692 | $42.25 | $35.00 | $42.25 | $35.00 | $30.00 | $35.00 |
| 0096 | Curb, concrete, type B (605-06121) | LFT | 46 | $104.25 | $90.00 | $104.25 | $124.50 | $72.00 | $104.25 |
| 0097 | Curb and gutter, concrete (605-06140) | LFT | 14,074 | $21.25 | $29.00 | $21.25 | $29.00 | $33.00 | $29.00 |
| 0098 | Curb and gutter, concrete, type B (605-06145) | LFT | 1,334 | $45.00 | $39.00 | $44.00 | $39.00 | $30.00 | $39.00 |
| 0099 | Milled PCCP corrugations, conventional (606-11064) | LFT | 160 | $28.00 | $4.00 | $0.70 | $15.00 | $19.00 | $5.31 |
| 0100 | Milled HMA corrugations, conventional (606-12399) | LFT | 19,839 | $1.00 | $3.50 | $0.58 | $5.00 | $3.00 | $1.29 |
| 0101 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 1,052 | $175.00 | $280.00 | $165.00 | $250.00 | $226.00 | $165.00 |
| 0102 | HMA for approaches, type B (610-07487) | TON | 1,921 | $151.00 | $145.00 | $151.00 | $145.00 | $126.00 | $145.00 |
| 0103 | PCCP for approaches, 6 in. (610-08446) | SYS | 307 | $111.25 | $90.00 | $111.25 | $90.00 | $133.00 | $90.00 |
| 0104 | PCCP for approaches, 9 in. (610-09108) | SYS | 955 | $101.50 | $90.00 | $101.50 | $90.00 | $142.00 | $90.00 |
| 0105 | Mailbox assembly, single (611-06497) | EACH | 16 | $251.00 | $251.00 | $251.00 | $251.00 | $251.00 | $350.00 |
| 0106 | Right-of-way marker (615-06490) | EACH | 138 | $167.00 | $167.00 | $167.00 | $167.00 | $167.00 | $175.00 |
| 0107 | Monument, type B (615-06505) | EACH | 89 | $925.00 | $925.00 | $925.00 | $925.00 | $925.00 | $775.00 |
| 0108 | Monument, type C (615-06510) | EACH | 6 | $775.00 | $775.00 | $775.00 | $775.00 | $775.00 | $350.00 |
| 0109 | Monument, section corner (615-06527) | EACH | 12 | $580.00 | $580.00 | $580.00 | $580.00 | $580.00 | $525.00 |
| 0110 | Riprap, class 1 (616-05688) | TON | 70 | $110.00 | $107.00 | $106.00 | $110.00 | $110.00 | $103.19 |
| 0111 | Riprap, class 2 (616-05689) | TON | 27 | $110.00 | $98.00 | $115.00 | $110.00 | $110.00 | $79.10 |
| 0112 | Riprap, revetment (616-06405) | TON | 2,455 | $69.00 | $98.00 | $65.20 | $90.00 | $76.97 | $58.46 |
| 0113 | Geotextile for riprap, type 1A (616-12246) | SYS | 1,634 | $5.00 | $5.00 | $3.80 | $4.00 | $4.20 | $3.15 |
| 0114 | Geotextile for riprap, type 2A (616-12248) | SYS | 2,435 | $5.00 | $6.00 | $4.00 | $4.00 | $5.24 | $3.68 |
| 0115 | Geotextile for riprap, type 2B (616-12249) | SYS | 6 | $11.00 | $7.50 | $10.80 | $11.00 | $11.00 | $18.31 |
| 0116 | Slopewall, concrete, 4 in. (616-51367) | SYS | 1,690 | $120.00 | $150.00 | $110.00 | $115.00 | $150.00 | $110.00 |
| 0117 | Mobilization and demobilization for seeding (621-01004) | EACH | 15 | $800.00 | $575.00 | $800.00 | $800.00 | $575.00 | $800.00 |
| 0118 | Erosion control blanket (621-02770) | SYS | 21,264 | $1.30 | $1.75 | $1.30 | $1.30 | $1.75 | $1.30 |
| 0119 | Erosion control blanket , leno-woven (621-02770) | SYS | 12,078 | $2.60 | $4.98 | $2.60 | $2.60 | $4.98 | $2.60 |
| 0120 | Fertilizer , for permanent seeding (621-06545) | TON | 25 | $800.00 | $975.00 | $800.00 | $800.00 | $975.00 | $800.00 |
| 0121 | Seed mixture, type U (621-06554) | LBS | 7,943 | $4.50 | $4.78 | $4.50 | $4.50 | $4.78 | $4.50 |
| 0122 | Mulched seeding, type U (621-06560) | SYS | 5,912 | $0.50 | $0.88 | $0.50 | $0.50 | $0.88 | $0.50 |
| 0123 | Mulching material (621-06565) | TON | 35 | $510.00 | $690.00 | $510.00 | $510.00 | $690.00 | $510.00 |
| 0124 | Water (621-06567) | KGAL | 55.20 | $1.00 | $5.00 | $1.00 | $1.00 | $5.00 | $1.00 |
| 0125 | Sodding (621-06574) | SYS | 5,778 | $4.50 | $4.95 | $4.50 | $4.50 | $4.95 | $8.21 |
| 0126 | Plant, deciduous tree, single stem, 1.25 in. or under (622-05648) | EACH | 13 | $280.00 | $325.00 | $280.00 | $280.00 | $325.00 | $280.00 |
| 0127 | Plant, deciduous tree, single stem, 1.25 in. to 2 in. (622-05649) | EACH | 13 | $310.00 | $495.00 | $310.00 | $310.00 | $495.00 | $310.00 |
| 0128 | Plant, deciduous tree, single stem, over 2 in. to 2.5 in. (622-05650) | EACH | 26 | $405.00 | $575.00 | $405.00 | $405.00 | $575.00 | $405.00 |
| 0129 | Field office, type D (628-12683) | MOS | 36 | $4,500.00 | $4,000.00 | $3,725.50 | $5,000.00 | $5,785.21 | $4,215.30 |
| 0130 | Dynamic pile load test (701-06011) | EACH | 9 | $1,250.00 | $8,000.00 | $1,250.00 | $3,000.00 | $3,500.00 | $1,250.00 |
| 0131 | Pile, steel pipe, 0.375 in., diameter 14 in. (701-08122) | LFT | 1,855 | $91.00 | $98.00 | $90.00 | $130.00 | $93.00 | $90.00 |
| 0132 | Test pile, dynamic, production (701-09557) | LFT | 682 | $79.00 | $56.00 | $80.00 | $140.00 | $108.00 | $80.00 |
| 0133 | Test pile, dynamic, restrike (701-09559) | EACH | 9 | $1,250.00 | $2,500.00 | $1,250.00 | $3,000.00 | $5,000.00 | $1,250.00 |
| 0134 | Pile, steel pipe, 0.375 in., diameter 14 in. (701-09665) | LFT | 3,879 | $89.00 | $106.00 | $90.00 | $125.00 | $93.00 | $90.00 |
| 0135 | Concrete, A, substructure (702-51005) | CYS | 279.80 | $950.00 | $1,200.00 | $850.00 | $1,200.00 | $1,250.00 | $850.00 |
| 0136 | Concrete, B, footings (702-51015) | CYS | 236.90 | $500.00 | $575.00 | $425.00 | $600.00 | $750.00 | $425.00 |
| 0137 | Field drilled hole in concrete (702-51863) | EACH | 424 | $20.00 | $26.00 | $25.00 | $20.00 | $35.00 | $25.00 |
| 0138 | Concrete, A (702-90915) | CYS | 1 | $4,750.00 | $1,933.00 | $1,150.00 | $2,500.00 | $600.00 | $2,500.00 |
| 0139 | Concrete, C, substructure (702-92857) | CYS | 260.80 | $1,000.00 | $825.00 | $1,200.00 | $1,200.00 | $1,400.00 | $1,200.00 |
| 0140 | Reinforcing bars (703-06028) | LBS | 66,551 | $1.75 | $1.25 | $2.00 | $1.50 | $1.80 | $2.00 |
| 0141 | Reinforcing bars, epoxy coated (703-06029) | LBS | 501,185 | $1.50 | $1.35 | $1.75 | $1.50 | $2.00 | $1.75 |
| 0142 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 390 | $50.00 | $44.00 | $50.00 | $40.00 | $45.00 | $50.00 |
| 0143 | Concrete, C, superstructure (704-51002) | CYS | 1,061.10 | $900.00 | $875.00 | $1,250.00 | $750.00 | $1,250.00 | $1,250.00 |
| 0144 | Concrete bridge railing transition, type TPF-1 (706-06351) | EACH | 8 | $3,500.00 | $9,000.00 | $3,500.00 | $4,000.00 | $5,850.00 | $3,500.00 |
| 0145 | Concrete bridge railing transition, type TPF-1 , modified (706-06351) | EACH | 2 | $3,500.00 | $9,500.00 | $3,500.00 | $7,500.00 | $6,500.00 | $3,500.00 |
| 0146 | Concrete bridge railing transition, type TPS-1 (706-06353) | EACH | 2 | $3,500.00 | $9,500.00 | $3,500.00 | $7,500.00 | $5,850.00 | $3,500.00 |
| 0147 | Railing, steel type PF-1 (706-11404) | LFT | 1,334 | $113.00 | $100.00 | $100.00 | $100.00 | $100.00 | $105.00 |
| 0148 | Railing, steel type PS-1 (706-11418) | LFT | 267 | $118.00 | $105.00 | $105.00 | $105.00 | $105.00 | $136.00 |
| 0149 | Bridge railing pedestrian fence (706-11455) | LFT | 258 | $113.00 | $113.00 | $113.00 | $113.00 | $113.00 | $64.00 |
| 0150 | Railing, concrete type PF-1 (706-11602) | CYS | 79.80 | $750.00 | $1,900.00 | $800.00 | $1,200.00 | $2,500.00 | $800.00 |
| 0151 | Railing, concrete type PS-1 (706-11604) | CYS | 22 | $750.00 | $1,975.00 | $825.00 | $1,200.00 | $2,500.00 | $825.00 |
| 0152 | Concrete bridge railing transition, type TFC (706-11620) | EACH | 8 | $3,500.00 | $3,500.00 | $3,500.00 | $2,500.00 | $2,750.00 | $3,500.00 |
| 0153 | Structural member, concrete, bulb-T beam, 66 in. X 49 in. (707-11047) | LFT | 3,341 | $660.00 | $710.00 | $750.00 | $675.00 | $800.00 | $750.00 |
| 0154 | Surface seal , bridge no. 1 (709-51821) | LS | 1 | $7,500.00 | $1.00 | $7,500.00 | $0.01 | $1.00 | $7,500.00 |
| 0155 | Surface seal , bridge no. 2 (709-51821) | LS | 1 | $2,500.00 | $5,000.00 | $7,500.00 | $7,500.00 | $7,300.00 | $7,500.00 |
| 0156 | Surface seal , bridge no. 3 (709-51821) | LS | 1 | $2,500.00 | $5,000.00 | $7,500.00 | $7,500.00 | $7,300.00 | $7,500.00 |
| 0157 | Surface seal , bridge no. 4 (709-51821) | LS | 1 | $3,000.00 | $1.00 | $7,500.00 | $0.01 | $1.00 | $7,500.00 |
| 0158 | Patching concrete structures (710-09158) | SFT | 36 | $150.00 | $180.00 | $150.00 | $300.00 | $250.00 | $150.00 |
| 0159 | Structure, reinforced concrete, box sections, 9 FT X 6 FT (714-11073) | LFT | 104 | $1,595.00 | $1,888.00 | $1,462.50 | $1,595.00 | $1,595.00 | $1,491.32 |
| 0160 | Structure, reinforced concrete, box sections, 4 FT X 2 FT (714-11193) | LFT | 195 | $928.50 | $625.00 | $834.50 | $928.50 | $928.50 | $536.15 |
| 0161 | Pipe end section, diameter 48 in. (715-02246) | EACH | 4 | $5,610.00 | $3,972.00 | $5,494.00 | $5,610.00 | $5,610.00 | $4,189.83 |
| 0162 | Pipe end section, diameter 42 in. (715-04522) | EACH | 2 | $4,240.00 | $2,920.00 | $4,151.50 | $4,240.00 | $4,240.00 | $3,244.94 |
| 0163 | Pipe, type 1, circular, diameter 36 in. (715-05019) | LFT | 186 | $171.00 | $165.00 | $167.50 | $171.00 | $171.00 | $104.95 |
| 0164 | Pipe, type 2, circular, diameter 36 in. (715-05024) | LFT | 147 | $183.00 | $215.00 | $179.00 | $183.00 | $183.00 | $111.19 |
| 0165 | Pipe, type 4, circular, diameter 6 in. (715-05048) | LFT | 60,219 | $5.50 | $6.95 | $5.20 | $5.50 | $5.50 | $6.35 |
| 0166 | Pipe, underdrain outlet, diameter 6 in. (715-05053) | LFT | 10,216 | $23.50 | $21.50 | $23.10 | $23.50 | $23.50 | $11.45 |
| 0167 | Pipe, type 1, circular, diameter 12 in. (715-05118) | LFT | 125 | $60.00 | $87.00 | $58.80 | $60.00 | $60.00 | $32.96 |
| 0170 | Pipe, type 1, circular, diameter 24 in. (715-05123) | LFT | 468 | $111.00 | $130.00 | $108.50 | $111.00 | $111.00 | $65.72 |
| 0171 | Pipe, type 1, circular, diameter 30 in. (715-05125) | LFT | 1,099 | $133.00 | $204.00 | $130.50 | $133.00 | $133.00 | $109.44 |
| 0172 | Pipe, type 1, circular, diameter 48 in. (715-05128) | LFT | 350 | $242.00 | $315.00 | $237.00 | $242.00 | $242.00 | $184.96 |
| 0173 | Pipe, type 2, circular, diameter 8 in. (715-05147) | LFT | 40 | $97.50 | $63.00 | $95.60 | $97.50 | $97.50 | $26.99 |
| 0174 | Pipe, type 2, circular, diameter 12 in. (715-05149) | LFT | 2,719 | $64.50 | $83.00 | $63.20 | $64.50 | $64.50 | $37.54 |
| 0175 | Pipe, type 2, circular, diameter 15 in. (715-05151) | LFT | 2,041 | $66.00 | $93.50 | $64.80 | $66.00 | $69.08 | $42.17 |
| 0176 | Pipe, type 2, circular, diameter 18 in. (715-05152) | LFT | 1,097 | $76.50 | $100.00 | $75.10 | $76.50 | $76.50 | $43.27 |
| 0177 | Pipe, type 2, circular, diameter 24 in. (715-05154) | LFT | 1,024 | $106.00 | $125.00 | $103.50 | $106.00 | $106.00 | $64.73 |
| 0178 | Pipe, type 2, circular, diameter 30 in. (715-05156) | LFT | 105 | $134.50 | $152.00 | $131.50 | $134.50 | $134.50 | $89.19 |
| 0179 | Pipe, type 3, circular, diameter 15 in. (715-05169) | LFT | 183 | $72.50 | $98.00 | $70.80 | $72.50 | $72.50 | $37.24 |
| 0180 | Pipe, type 3, circular, diameter 18 in. (715-05171) | LFT | 89 | $89.50 | $90.00 | $87.70 | $89.50 | $89.50 | $50.08 |
| 0181 | Pipe, type 3, circular, diameter 30 in. (715-05175) | LFT | 50 | $201.00 | $145.00 | $197.00 | $201.00 | $201.00 | $87.26 |
| 0182 | Pipe, type 3, circular, diameter 36 in. (715-05177) | LFT | 305 | $250.50 | $222.00 | $245.50 | $250.50 | $250.50 | $114.53 |
| 0183 | Pipe, type 3, circular, diameter 42 in. (715-05178) | LFT | 78 | $298.00 | $230.00 | $292.00 | $298.00 | $298.00 | $148.05 |
| 0184 | Pipe, type 3, deformed, min. area 1.8 SFT (715-05363) | LFT | 38 | $211.00 | $310.00 | $206.50 | $211.00 | $211.00 | $118.35 |
| 0185 | Pipe, end bent drain, diameter 6 in. (715-05407) | LFT | 372 | $20.00 | $28.00 | $20.00 | $20.00 | $18.00 | $20.00 |
| 0186 | Pipe, type 1, circular, diameter 66 in. (715-07625) | LFT | 95 | $513.00 | $800.00 | $502.50 | $513.00 | $513.00 | $371.04 |
| 0187 | Concrete anchor, diameter 66 in. (715-07626) | EACH | 2 | $5,490.00 | $13,900 | $5,377.50 | $5,490.00 | $5,490.00 | $3,601.04 |
| 0188 | Video inspection for pipe (715-09064) | LFT | 7,119 | $3.25 | $1.85 | $1.60 | $1.60 | $1.60 | $1.12 |
| 0189 | Pipe extension, deformed, min. area 26.0 SFT , elliptical pipe 68 inch X 44 inch (715-10126) | LFT | 51 | $552.50 | $450.00 | $541.00 | $552.50 | $552.50 | $734.70 |
| 0190 | Pipe, roadway drain casting extension (715-10238) | EACH | 4 | $575.00 | $750.00 | $750.00 | $500.00 | $575.00 | $750.00 |
| 0191 | Pipe end section, diameter 12 in. (715-46000) | EACH | 11 | $823.50 | $850.00 | $806.50 | $823.50 | $823.50 | $1,327.87 |
| 0192 | Pipe end section, diameter 15 in. (715-46005) | EACH | 17 | $1,345.00 | $1,025.00 | $1,158.00 | $1,345.00 | $1,345.00 | $1,386.87 |
| 0193 | Pipe end section, diameter 18 in. (715-46010) | EACH | 4 | $1,360.00 | $1,318.00 | $1,172.50 | $1,360.00 | $1,360.00 | $1,463.87 |
| 0194 | Pipe end section, diameter 24 in. (715-46020) | EACH | 15 | $1,595.00 | $1,196.00 | $1,563.00 | $1,595.00 | $1,807.67 | $1,970.12 |
| 0195 | Pipe end section, diameter 30 in. (715-46030) | EACH | 10 | $2,280.00 | $2,100.00 | $2,234.50 | $2,280.00 | $2,280.00 | $2,276.05 |
| 0196 | Pipe end section, diameter 36 in. (715-46040) | EACH | 10 | $3,135.00 | $2,800.00 | $3,070.00 | $3,135.00 | $3,135.00 | $2,512.05 |
| 0197 | Pipe end section, min. area 1.8 SFT (715-46055) | EACH | 2 | $1,280.00 | $1,655.00 | $1,251.50 | $1,280.00 | $1,280.00 | $1,796.83 |
| 0198 | Outlet protector, type 1 (718-06528) | EACH | 71 | $975.00 | $1,967.00 | $1,500.00 | $165.00 | $1,200.00 | $1,244.25 |
| 0199 | Outlet protector, type 3 (718-06531) | EACH | 35 | $975.00 | $1,675.00 | $1,500.00 | $165.00 | $1,200.00 | $1,244.93 |
| 0200 | Video inspection for underdrain (718-06532) | LFT | 67,363 | $1.00 | $1.45 | $1.25 | $1.25 | $1.25 | $1.12 |
| 0201 | Geotextile for underdrains, type 2B (718-12308) | SYS | 38,664 | $3.50 | $3.60 | $3.10 | $3.50 | $3.54 | $3.00 |
| 0202 | Aggregate for underdrains (718-52610) | CYS | 4,244 | $71.50 | $70.00 | $69.90 | $71.50 | $67.79 | $79.26 |
| 0203 | Inlet, type E7 (720-45030) | EACH | 13 | $3,965.00 | $3,720.00 | $3,882.50 | $3,965.00 | $3,965.00 | $2,892.65 |
| 0204 | Inlet, type HA5 (720-45042) | EACH | 30 | $5,985.00 | $6,400.00 | $5,854.00 | $5,985.00 | $5,985.00 | $5,361.77 |
| 0205 | Inlet, type N12 (720-45065) | EACH | 13 | $6,685.00 | $7,400.00 | $6,539.50 | $6,685.00 | $6,685.00 | $5,899.61 |
| 0206 | Inlet, type N12, modified (720-45066) | EACH | 3 | $6,685.00 | $7,425.00 | $6,539.50 | $6,685.00 | $6,685.00 | $5,899.60 |
| 0207 | Inlet, type P12 (720-45069) | EACH | 5 | $7,795.00 | $6,200.00 | $7,626.00 | $7,795.00 | $7,795.00 | $4,766.61 |
| 0208 | Manhole, type D4 (720-45415) | EACH | 5 | $10,365 | $6,400.00 | $10,136 | $10,365 | $10,365 | $6,835.64 |
| 0209 | Manhole, type L4 (720-93501) | EACH | 1 | $15,210 | $10,950 | $14,869 | $15,210 | $15,210 | $7,701.31 |
| 0210 | Manhole, type C (720-94157) | EACH | 17 | $6,285.00 | $5,200.00 | $6,141.00 | $6,285.00 | $6,285.00 | $6,126.37 |
| 0211 | Inlet, type P12A, modified (720-95310) | EACH | 3 | $7,215.00 | $5,470.00 | $7,059.00 | $7,215.00 | $7,215.00 | $4,766.60 |
| 0212 | Inlet, type B15 (720-98174) | EACH | 18 | $6,485.00 | $4,860.00 | $6,339.50 | $6,485.00 | $6,485.00 | $2,453.91 |
| 0213 | Inlet, type C15 (720-98555) | EACH | 43 | $6,870.00 | $4,860.00 | $6,716.50 | $6,870.00 | $6,870.00 | $2,599.81 |
| 0214 | Hydrodemolition (722-01066) | SYS | 864 | $125.00 | $100.00 | $125.00 | $150.00 | $120.00 | $125.00 |
| 0215 | Bridge deck overlay budget (722-12380) | DOL | 14,408 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0216 | Bridge deck, remove existing concrete surface (722-12464) | SYS | 864 | $20.00 | $16.00 | $15.00 | $20.00 | $22.00 | $15.00 |
| 0217 | Longitudinal grooving (722-12732) | SYS | 4,820 | $5.00 | $7.00 | $5.00 | $5.00 | $7.50 | $5.00 |
| 0218 | Bridge deck patching, full depth (722-51401) | SFT | 20 | $50.00 | $15.00 | $50.00 | $50.00 | $170.00 | $50.00 |
| 0219 | Structure, reinforced concrete, three-sided (723-11211) | LFT | 184 | $3,900.00 | $4,600.00 | $5,500.00 | $5,500.00 | $5,500.00 | $5,112.85 |
| 0220 | Bearing assembly, elastomeric (726-92406) | EACH | 26 | $2,500.00 | $1,800.00 | $2,500.00 | $1,500.00 | $3,500.00 | $2,500.00 |
| 0221 | Controller, reset timing (801-02595) | EACH | 2 | $495.25 | $495.25 | $500.00 | $500.00 | $495.25 | $500.00 |
| 0222 | Construction sign, type C (801-03290) | EACH | 23 | $150.00 | $150.00 | $266.00 | $266.00 | $266.00 | $266.00 |
| 0223 | Construction sign, type D (801-03291) | EACH | 26 | $150.00 | $150.00 | $289.00 | $289.00 | $289.00 | $289.00 |
| 0224 | Road closure sign assembly (801-04308) | EACH | 22 | $600.00 | $600.00 | $266.00 | $266.00 | $266.00 | $266.00 |
| 0225 | Temporary pavement marking, 4 in. (801-06203) | LFT | 885 | $1.00 | $1.00 | $1.34 | $1.34 | $1.34 | $1.34 |
| 0226 | Temporary pavement marking, removable, 4 in. (801-06207) | LFT | 150,167 | $1.50 | $1.50 | $1.44 | $1.44 | $1.44 | $1.44 |
| 0227 | Temporary traffic signal installation, maintain (801-06539) | LS | 1 | $80,000 | $56,000 | $80,000 | $80,000 | $56,000 | $80,000 |
| 0228 | Detour route marker assembly (801-06625) | EACH | 168 | $250.00 | $250.00 | $167.00 | $167.00 | $167.00 | $167.00 |
| 0229 | Construction sign, type A (801-06640) | EACH | 509 | $300.00 | $300.00 | $231.00 | $231.00 | $231.00 | $231.00 |
| 0230 | Construction sign, type B (801-06645) | EACH | 138 | $150.00 | $150.00 | $118.00 | $118.00 | $118.00 | $118.00 |
| 0231 | Flashing arrow sign (801-06710) | DAY | 300 | $25.00 | $25.00 | $16.00 | $16.00 | $16.00 | $16.00 |
| 0232 | Maintaining traffic (801-06775) | LS | 1 | $925,239 | $500,000 | $995,000 | $885,395 | $900,000 | $2,294,949 |
| 0233 | Energy absorbing terminal, CZ, TL-3 (801-07024) | EACH | 5 | $18,480 | $18,480 | $9,300.00 | $18,480 | $22,300 | $13,850 |
| 0234 | Barricade, type III-A (801-07118) | LFT | 296 | $40.00 | $40.00 | $16.09 | $16.09 | $16.09 | $16.09 |
| 0235 | Barricade, type III-B (801-07119) | LFT | 360 | $40.00 | $40.00 | $16.09 | $16.09 | $16.09 | $16.09 |
| 0236 | Temporary traffic barrier, type 2 (801-08401) | LFT | 10,035 | $50.00 | $52.00 | $107.00 | $75.00 | $50.00 | $117.68 |
| 0237 | Truck mounted attenuator (801-12042) | DAY | 24 | $1,057.38 | $450.00 | $489.00 | $1,250.00 | $489.00 | $489.00 |
| 0238 | Law enforcement officer (801-12324) | HRS | 192 | $60.00 | $60.00 | $60.00 | $60.00 | $60.00 | $60.00 |
| 0239 | Temporary speed feedback assembly (801-12832) | EACH | 46 | $250.00 | $250.00 | $2,918.00 | $2,918.00 | $2,918.00 | $2,918.00 |
| 0240 | Signal head relocate (801-94295) | EACH | 4 | $600.00 | $600.00 | $1,500.00 | $1,500.00 | $600.00 | $1,500.00 |
| 0241 | Sign post, square, type 1, reinforced anchor base (802-05701) | LFT | 1,545 | $30.00 | $30.00 | $20.00 | $20.00 | $30.00 | $20.00 |
| 0242 | Sign post, square, type 2, reinforced anchor base (802-05702) | LFT | 689 | $30.00 | $30.00 | $25.00 | $25.00 | $30.00 | $25.00 |
| 0243 | Sign, panel, with legend (802-07057) | SFT | 1,744 | $58.00 | $58.00 | $55.00 | $55.00 | $58.00 | $55.00 |
| 0244 | Sign, sheet assembly, relocate (802-07058) | EACH | 4 | $150.00 | $150.00 | $285.00 | $285.00 | $150.00 | $285.00 |
| 0245 | Sign, sheet, and supports, remove (802-07059) | EACH | 22 | $50.00 | $50.00 | $125.00 | $125.00 | $50.00 | $125.00 |
| 0246 | Overhead sign structure, cantilever, type E (802-09577) | EACH | 4 | $90,000 | $90,000 | $78,500 | $78,500 | $90,000 | $78,500 |
| 0247 | Cantilever sign support foundation, drilled shaft 36 in. (802-09581) | EACH | 4 | $20,000 | $20,000 | $15,000 | $15,000 | $20,000 | $15,000 |
| 0248 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 547 | $30.00 | $30.00 | $15.00 | $15.00 | $30.00 | $15.00 |
| 0249 | Sign, sheet, with legend, 0.100 in. thickness (802-09840) | SFT | 799 | $30.00 | $30.00 | $17.00 | $17.00 | $30.00 | $17.00 |
| 0250 | Wide flange sign post support foundation, type A (802-12222) | EACH | 8 | $3,000.00 | $3,000.00 | $3,750.00 | $3,750.00 | $3,000.00 | $3,750.00 |
| 0251 | Wide flange sign post support foundation, type B (802-12223) | EACH | 18 | $4,750.00 | $4,750.00 | $4,000.00 | $4,000.00 | $4,750.00 | $4,000.00 |
| 0252 | Structural steel, breakaway (802-76095) | LBS | 5,790 | $20.00 | $13.00 | $8.75 | $8.75 | $13.00 | $8.75 |
| 0253 | Overhead sign structure, monotube (802-76100) | EACH | 1 | $70,000 | $70,000 | $29,855 | $29,855 | $70,000 | $29,855 |
| 0254 | Miscellaneous equipment for traffic signals (805-01579) | LS | 1 | $5,369.00 | $5,369.00 | $7,500.00 | $7,500.00 | $5,369.00 | $7,500.00 |
| 0255 | Signal pole foundation, 36 in. X 144 in. (805-01815) | EACH | 9 | $8,500.00 | $8,500.00 | $4,500.00 | $4,500.00 | $8,500.00 | $4,500.00 |
| 0256 | Transportation of salvageable signal equipment (805-02087) | LS | 1 | $1,500.00 | $1,500.00 | $5,000.00 | $5,000.00 | $1,500.00 | $5,000.00 |
| 0257 | Pedestrian signal head, countdown, 18 in. (805-02150) | EACH | 8 | $1,500.00 | $1,500.00 | $695.00 | $695.00 | $1,500.00 | $695.00 |
| 0258 | Signal pole foundation, 24 in. X 24 in. X 36 in. (805-02645) | EACH | 11 | $1,850.00 | $1,850.00 | $1,200.00 | $1,200.00 | $1,850.00 | $1,200.00 |
| 0259 | Signal pole, pedestal, 12 FT (805-04133) | EACH | 11 | $1,750.00 | $1,750.00 | $1,785.00 | $1,785.00 | $1,750.00 | $1,785.00 |
| 0260 | Controller and cabinet (805-04952) | EACH | 2 | $23,500 | $23,500 | $12,000 | $12,000 | $23,500 | $12,000 |
| 0261 | Handhole, signal, type 2 (805-11744) | EACH | 35 | $3,250.00 | $3,250.00 | $2,000.00 | $2,000.00 | $3,250.00 | $2,000.00 |
| 0263 | Conduit, HDPE, 2 in. schedule 40 (805-11814) | LFT | 4,053 | $18.50 | $18.50 | $35.00 | $35.00 | $18.50 | $35.00 |
| 0264 | Conduit, HDPE, 2 in. schedule 80 (805-11815) | LFT | 2,338 | $28.25 | $28.25 | $37.50 | $37.50 | $28.25 | $37.50 |
| 0265 | Pedestrian push button, APS (805-11817) | EACH | 8 | $1,875.00 | $1,875.00 | $1,375.00 | $1,375.00 | $1,875.00 | $1,375.00 |
| 0266 | Controller and cabinet, secondary menu driven, 8 phase (805-78109) | EACH | 1 | $30,000 | $30,000 | $20,000 | $20,000 | $30,000 | $20,000 |
| 0267 | Traffic signal head, no. 3 (805-78205) | EACH | 20 | $1,625.00 | $1,625.00 | $875.00 | $875.00 | $1,625.00 | $875.00 |
| 0268 | Span, catenary, and tether (805-78415) | EACH | 5 | $6,000.00 | $6,000.00 | $5,000.00 | $5,000.00 | $6,000.00 | $5,000.00 |
| 0269 | Disconnect hanger (805-78420) | EACH | 7 | $800.00 | $800.00 | $500.00 | $500.00 | $800.00 | $500.00 |
| 0270 | Signal service (805-78445) | EACH | 1 | $2,950.00 | $2,950.00 | $1,750.00 | $1,750.00 | $2,950.00 | $1,750.00 |
| 0271 | Signal cable, service, copper, 3C/8 gauge (805-78467) | LFT | 177 | $6.00 | $6.00 | $10.00 | $10.00 | $6.00 | $10.00 |
| 0272 | Signal cable, roadway loop, copper, 1C/14 gauge (805-78470) | LFT | 6,388 | $2.00 | $2.00 | $0.75 | $0.75 | $2.00 | $0.75 |
| 0273 | Signal cable, control, copper, 3C/14 gauge (805-78480) | LFT | 3,133 | $3.50 | $3.50 | $5.00 | $5.00 | $3.50 | $5.00 |
| 0274 | Signal cable, control, copper, 5C/14 gauge (805-78485) | LFT | 5,573 | $4.50 | $4.50 | $7.00 | $7.00 | $4.50 | $7.00 |
| 0275 | Signal cable, control, copper, 9C/14 gauge (805-78495) | LFT | 7,399 | $6.00 | $6.00 | $9.00 | $9.00 | $6.00 | $9.00 |
| 0276 | Signal cable, detector lead-in, copper, 2C/16 gauge (805-78510) | LFT | 7,905 | $3.50 | $3.50 | $5.00 | $5.00 | $3.50 | $5.00 |
| 0277 | Signal detector housing (805-78785) | EACH | 19 | $2,200.00 | $2,200.00 | $1,785.00 | $1,785.00 | $2,200.00 | $1,785.00 |
| 0278 | Saw cut for roadway loop detector and sealant (805-78795) | LFT | 1,092 | $25.00 | $25.00 | $15.00 | $15.00 | $25.00 | $15.00 |
| 0279 | Controller cabinet foundation, type P1 (805-78925) | EACH | 3 | $4,350.00 | $4,350.00 | $1,200.00 | $1,200.00 | $4,350.00 | $1,200.00 |
| 0280 | Signal pole, steel strain, 30 FT (805-81032) | EACH | 9 | $13,500 | $13,500 | $9,985.00 | $9,985.00 | $13,500 | $9,985.00 |
| 0281 | Lighting foundation, concrete, with grounding, 24 in. X 24 in. X 96 in. (807-03758) | EACH | 83 | $2,600.00 | $2,600.00 | $2,800.00 | $2,800.00 | $2,600.00 | $2,800.00 |
| 0282 | Luminaire, ornamental (807-03950) | EACH | 15 | $4,500.00 | $4,500.00 | $5,000.00 | $5,000.00 | $4,500.00 | $5,000.00 |
| 0283 | Conduit, steel, galvanized, 2 in. (807-06592) | LFT | 1,565 | $35.00 | $35.00 | $50.00 | $50.00 | $35.00 | $50.00 |
| 0284 | Wire, no. 4 copper, in plastic duct, in trench, 4 1/C (807-07580) | LFT | 63,895 | $13.00 | $13.00 | $37.00 | $37.00 | $13.00 | $37.00 |
| 0285 | Luminaire, high mast (807-12201) | EACH | 12 | $2,000.00 | $2,000.00 | $1,500.00 | $1,500.00 | $2,000.00 | $1,500.00 |
| 0286 | Luminaire, low lumen roadway (807-12202) | EACH | 68 | $500.00 | $500.00 | $1,000.00 | $1,000.00 | $500.00 | $1,000.00 |
| 0287 | Lighting foundation, high mast tower, concrete, with grounding (807-12792) | EACH | 2 | $40,000 | $40,000 | $18,000 | $18,000 | $40,000 | $18,000 |
| 0288 | High mast tower, 140 FT E.M.H. (807-82520) | EACH | 2 | $150,000 | $150,000 | $75,000 | $75,000 | $150,000 | $75,000 |
| 0289 | Light pole, 30 FT E.M.H., 5 FT mast arm, breakaway base (807-85480) | EACH | 34 | $14,000 | $14,000 | $10,000 | $10,000 | $14,000 | $10,000 |
| 0290 | Light pole, 40 FT E.M.H., 10 FT mast arm, breakaway base (807-85752) | EACH | 49 | $6,000.00 | $6,000.00 | $11,000 | $11,000 | $6,000.00 | $11,000 |
| 0291 | Service point, type II (807-86810) | EACH | 5 | $15,000 | $15,000 | $15,000 | $15,000 | $15,000 | $15,000 |
| 0292 | Cable, pole circuit, THWN, no. 10 copper, stranded 1/C (807-86889) | LFT | 13,317 | $2.00 | $2.00 | $1.50 | $1.50 | $2.00 | $1.50 |
| 0293 | Connector kit, fused (807-86915) | EACH | 166 | $80.00 | $80.00 | $120.00 | $120.00 | $80.00 | $120.00 |
| 0294 | Multiple compression fitting, non- waterproofed (807-86920) | EACH | 230 | $30.00 | $30.00 | $25.00 | $25.00 | $30.00 | $25.00 |
| 0295 | Insulation link, non- waterproofed (807-86930) | EACH | 240 | $20.00 | $20.00 | $25.00 | $25.00 | $20.00 | $25.00 |
| 0296 | Sign, underpass, and roadway lighting, location identification (807-86950) | EACH | 85 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| 0297 | Transverse marking, thermoplastic, crosswalk line, white, 24 in. (808-03439) | LFT | 140 | $17.00 | $9.81 | $14.22 | $14.22 | $14.22 | $14.22 |
| 0298 | Line, thermoplastic, broken, white, 4 in. (808-06701) | LFT | 871 | $1.00 | $1.37 | $3.11 | $3.11 | $3.11 | $3.11 |
| 0299 | Line, thermoplastic, solid, white, 4 in. (808-06703) | LFT | 923 | $1.00 | $0.78 | $2.61 | $2.61 | $2.61 | $2.61 |
| 0300 | Line, paint, broken, yellow, 4 in. (808-06712) | LFT | 1,661 | $1.00 | $1.00 | $0.88 | $0.88 | $0.88 | $0.88 |
| 0301 | Line, paint, solid, white, 4 in. (808-06713) | LFT | 14,114 | $1.00 | $1.00 | $0.36 | $0.36 | $0.36 | $0.36 |
| 0302 | Line, paint, solid, yellow, 4 in. (808-06714) | LFT | 15,036 | $1.00 | $1.00 | $0.36 | $0.36 | $0.36 | $0.36 |
| 0303 | Line, remove (808-06716) | LFT | 50,370 | $0.50 | $0.50 | $0.52 | $0.52 | $0.52 | $0.52 |
| 0304 | Retro-reflectivity testing (808-09381) | LS | 1 | $2,000.00 | $2,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 |
| 0305 | Transverse marking, multi-component, crosshatch line, white, 24 in. (808-10038) | LFT | 815 | $15.00 | $15.00 | $14.81 | $14.81 | $14.81 | $14.81 |
| 0306 | Transverse marking, multi-component, crosshatch line, white, 12 in. (808-10047) | LFT | 2,357 | $8.00 | $8.00 | $7.21 | $7.21 | $7.21 | $7.21 |
| 0307 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 51,592 | $1.00 | $1.00 | $1.06 | $1.06 | $1.06 | $1.06 |
| 0308 | Transverse marking, multi-component, stop line, white, 24 in. (808-10051) | LFT | 302 | $15.00 | $15.00 | $14.81 | $14.81 | $14.81 | $14.81 |
| 0309 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 15,315 | $1.00 | $1.00 | $1.06 | $1.06 | $1.06 | $1.06 |
| 0310 | Line, multi-component, dotted, yellow, 6 in. (808-10063) | LFT | 390 | $1.00 | $1.00 | $3.21 | $3.21 | $3.21 | $3.21 |
| 0311 | Line, multi-component, broken, white, 6 in. (808-10071) | LFT | 120 | $1.00 | $1.00 | $2.88 | $2.88 | $2.88 | $2.88 |
| 0312 | Pavement message marking, multi- component, lane indication arrow (808-10077) | EACH | 53 | $200.00 | $200.00 | $239.00 | $239.00 | $239.00 | $239.00 |
| 0313 | Transverse marking, multi-component, crosswalk line, white, 24 in. (808-10099) | LFT | 320 | $15.00 | $15.00 | $14.81 | $14.81 | $14.81 | $14.81 |
| 0314 | Transverse marking, thermoplastic, yield line, white, 24 in. (808-10118) | LFT | 182 | $17.00 | $23.03 | $23.81 | $23.81 | $23.81 | $23.81 |
| 0315 | Line, thermoplastic, dotted, white, 4 in. (808-11482) | LFT | 241 | $1.25 | $1.37 | $2.81 | $2.81 | $2.81 | $2.81 |
| 0316 | Line, thermoplastic, dotted, white, 6 in. (808-11650) | LFT | 3,599 | $2.00 | $1.91 | $5.11 | $5.11 | $5.11 | $5.11 |
| 0317 | Grooving for pavement markings (808-12032) | LFT | 48,243 | $0.75 | $0.75 | $0.68 | $0.68 | $0.68 | $0.68 |
| 0318 | Line, multi-component, dotted, white, 6 in. (808-12353) | LFT | 4,011 | $1.00 | $1.00 | $2.88 | $2.88 | $2.88 | $2.88 |
| 0319 | Line, multi-component, solid, white, 10 in. (808-12781) | LFT | 1,220 | $2.00 | $2.00 | $3.06 | $3.06 | $3.06 | $3.06 |
| 0320 | Line, multi-component, broken, yellow, 6 in. (808-12841) | LFT | 2,488 | $1.00 | $1.00 | $2.88 | $2.88 | $2.88 | $2.88 |
| 0321 | Line, thermoplastic, solid, white, 10 in. (808-12953) | LFT | 1,223 | $3.00 | $2.48 | $3.06 | $3.06 | $3.06 | $3.06 |
| 0322 | Line, thermoplastic, solid, white, 6 in. (808-75043) | LFT | 17,922 | $1.75 | $1.12 | $1.31 | $1.31 | $1.31 | $1.31 |
| 0323 | Line, thermoplastic, solid, yellow, 4 in. (808-75245) | LFT | 4,454 | $1.00 | $0.77 | $1.06 | $1.06 | $1.06 | $1.06 |
| 0324 | Line, thermoplastic, solid, yellow, 6 in. (808-75247) | LFT | 19,040 | $1.75 | $1.12 | $1.31 | $1.31 | $1.31 | $1.31 |
| 0325 | Transverse marking, thermoplastic, crosshatch line, white, 12 in. (808-75260) | LFT | 352 | $12.00 | $4.91 | $6.34 | $6.34 | $6.34 | $6.34 |
| 0326 | Transverse marking, thermoplastic, crosshatch line, yellow, 12 in. (808-75278) | LFT | 140 | $12.00 | $4.91 | $6.34 | $6.34 | $6.34 | $6.34 |
| 0327 | Pavement message marking, thermoplastic, lane indication arrow (808-75320) | EACH | 27 | $200.00 | $202.00 | $228.00 | $228.00 | $228.00 | $228.00 |
| 0328 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 14 | $21.38 | $40.00 | $15.00 | $34.00 | $16.00 | $250.00 |
| 0329 | Snowplowable raised pavement marker (808-75998) | EACH | 716 | $65.00 | $65.00 | $34.00 | $34.00 | $34.00 | $34.00 |
| 0330 | Line, thermoplastic, broken, white, 6 in. (808-96075) | LFT | 4,622 | $1.75 | $1.91 | $1.89 | $1.89 | $1.89 | $1.89 |
| 0331 | Bridge deck overlay, latex modified (722-51842) | SYS | 864 | $200.00 | |||||
| 0332 | Bridge deck overlay, silica fume modified (722-01061) | SYS | 864 | $150.00 | $145.00 | $150.00 | $185.00 | $150.00 | |
| 0333 | Pipe installation, trenchless, 12 in. (716-07630) | LFT | 452 | $298.18 | $840.00 | $1,112.50 | $1,050.00 | $1,100.00 | $783.57 |
| 0334 | Pipe installation, trenchless, 15 in. (716-07631) | LFT | 420 | $320.90 | $915.00 | $1,210.50 | $1,160.00 | $1,200.00 | $863.75 |
| 0335 | Pipe installation, trenchless, 18 in. (716-07632) | LFT | 137 | $363.82 | $1,161.80 | $1,544.50 | $1,420.00 | $1,500.00 | $1,096.27 |
| 0336 | Solar powered flashing beacon assembly (805-06742) | EACH | 3 | $8,000.00 | $8,000.00 | $8,000.00 | $21,852 | $8,000.00 | $21,852 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of May 14, 2025. Compiled by Mirage Metrics.