White Construction LLC: INDOT bid record
White Construction LLC submitted 47 bids on Indiana DOT contracts in the data, from 12 JAN 2022 to 18 JAN 2024, and was the low bidder on 7 of them (15%). When it was not low, its total sat a median +14% above the low bid.
- Owner
- Indiana DOT
- Low bid volume
- $68,587,696
- Latest bid
- 18 JAN 2024
- Data through
- 05 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2022 | 29 | 2 | 7% |
| 2023 | 14 | 5 | 36% |
| 2024 | 4 | 0 | 0% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| Crawfordsville | 31 | 6 | 19% |
| Greenfield | 10 | 1 | 10% |
| Seymour | 4 | 0 | 0% |
| Vincennes | 2 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Liquidated damages | 109-08359 | DOL | 46 | 46 (100%) | $1.00 | $1.00 |
| Contract liens | 109-08360 | DOL | 46 | 46 (100%) | $1.00 | $1.00 |
| Quality adjustments, failed materials | 109-08444 | DOL | 46 | 46 (100%) | $1.00 | $1.00 |
| Quality adjustments, temporary traffic control devices | 109-08443 | DOL | 46 | 46 (100%) | $1.00 | $1.00 |
| Stormwater management budget | 205-12108 | DOL | 44 | 44 (100%) | $1.00 | $1.00 |
| Quality adjustments, failure to maintain temporary erosion and sediment control measures | 109-11362 | DOL | 44 | 44 (100%) | $1.00 | $1.00 |
| Quality adjustments, HMA | 109-08440 | DOL | 39 | 39 (100%) | $1.00 | $1.00 |
| Payment adjustment PG asphalt binder | 109-09489 | DOL | 36 | 36 (100%) | $1.00 | $1.00 |
| Construction sign, A | 801-06640 | EACH | 39 | 32 (82%) | $190.00 | $193.50 |
| Barricade, III-A | 801-07118 | LFT | 35 | 27 (77%) | $16.00 | $16.00 |
| Road closure sign assembly | 801-04308 | EACH | 36 | 26 (72%) | $325.00 | $280.00 |
| Detour route marker assembly | 801-06625 | EACH | 34 | 26 (76%) | $127.50 | $140.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Milestone Contractors LP | 21 | 17 of 21 |
| Morphey Construction Inc. | 17 | 10 of 17 |
| Rieth-Riley Construction Co., Inc. | 17 | 14 of 17 |
| E & B Paving LLC | 12 | 7 of 12 |
| Calumet Civil Contractors Inc | 6 | 5 of 6 |
| Beaty Construction Inc | 6 | 3 of 6 |
| Crider & Crider Inc | 5 | 1 of 5 |
| CLR Inc | 5 | 5 of 5 |
| Feutz Contractors Inc | 4 | 2 of 4 |
| Gradex Inc | 4 | 1 of 4 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 18 JAN 2024 | R-42954-A | Crawfordsville | SMALL STRUCTURES AND DRAINS CONSTRUCTION | 4 of 4 | $3,495,000 | +36% |
| 18 JAN 2024 | B-42176-A | Vincennes | BRIDGE DECK REPLACEMENT, OVERLAY AND SIGNING INSTALLATION | 4 of 4 | $11,433,000 | +19% |
| 18 JAN 2024 | B-42237-A | Crawfordsville | BRIDGE DECK OVERLAY | 3 of 3 | $2,810,000 | +29% |
| 18 JAN 2024 | T-42333-A | Greenfield | ADA SIDEWALK RAMP CONSTRUCTION | 4 of 4 | $1,985,000 | +60% |
| 13 DEC 2023 | R-42179-A | Crawfordsville | ADDED TRAVEL LANES AND BRIDGE REPLACEMENT | 1 of 7 | $8,491,000 | Low, 1.0% under the second |
| 13 DEC 2023 | B-42243-A | Crawfordsville | SMALL STRUCTURE REPLACEMENT WITH BRIDGE | 2 of 4 | $8,100,000 | +13% |
| 10 MAY 2023 | R-40742-A | Crawfordsville | AUXILIARY LANES, ACCEL, DECEL OR TURN LANES, UTILITY RELOCAT | 2 of 3 | $6,197,000 | +7.0% |
| 15 MAR 2023 | R-37907-B | Crawfordsville | ROAD RECONSTRUCTION | 2 of 2 | $9,250,000 | +6.0% |
| 15 MAR 2023 | R-39860-A | Crawfordsville | ROAD RECONSTRUCTION | 3 of 3 | $7,525,000 | +25% |
| 15 MAR 2023 | R-44754-A | Crawfordsville | NEW ROAD AND BRIDGE CONSTRUCTION | 1 of 3 | $37,940,000 | Low, 14% under the second |
| 15 MAR 2023 | R-44783-A | Greenfield | DEMOLITION, REMOVE BUILDINGS, FOUNDATIONS | 2 of 6 | $662,234 | +4.0% |
| 15 MAR 2023 | B-40162-B | Crawfordsville | BRIDGE DECK REPLACEMENT | 2 of 2 | $8,500,000 | +4.0% |
| 15 MAR 2023 | B-43674-A | Crawfordsville | BRIDGE REMOVAL, SMALL STRUCTURE MAINTENANCE AND REPAIR | 1 of 2 | $2,127,000 | Low, 4.0% under the second |
| 10 FEB 2023 | R-40402-A | Crawfordsville | ROAD RECONSTRUCTION | 3 of 5 | $11,042,069 | +11% |
| 10 FEB 2023 | B-41589-B | Crawfordsville | BRIDGE AND SMALL STRUCTURE REPLACEMENT | 1 of 1 | $3,512,000 | Low |
| 19 JAN 2023 | R-40872-B | Crawfordsville | ROAD RECONSTRUCTION | 1 of 2 | $2,715,000 | Low, 1.0% under the second |
| 19 JAN 2023 | R-41393-A | Greenfield | ADDED TRAVEL LANES AND BRIDGE REPLACEMENT | 4 of 4 | $12,692,000 | +11% |
| 19 JAN 2023 | R-41504-A | Greenfield | PAVEMENT REPLACEMENT | 2 of 2 | $15,282,000 | +10% |
| 14 DEC 2022 | B-43149-B | Greenfield | SMALL STRUCTURE REPLACEMENT WITH BRIDGE | 2 of 2 | $2,958,533 | 0.0% |
| 07 DEC 2022 | R-41903-A | Greenfield | ROAD RECONSTR, INTERSECT IMPROVE, BRIDGE REPAIR AND NEW PATH | 3 of 3 | $11,552,046 | +4.0% |
| 07 DEC 2022 | B-41620-A | Crawfordsville | REPLACE SUPERSTRUCTURE | 2 of 2 | $2,658,552 | +4.0% |
| 16 NOV 2022 | R-41374-A | Crawfordsville | ADDED TRAVEL LANES | 6 of 6 | $5,555,852 | +16% |
| 13 OCT 2022 | B-42921-B | Crawfordsville | BRIDGE DECK OVERLAY | 2 of 2 | $1,552,753 | +6.0% |
| 14 SEP 2022 | R-40884-A | Seymour | ROAD RECONSTRUCTION | 4 of 6 | $3,890,929 | +27% |
| 14 SEP 2022 | B-39855-A | Crawfordsville | BRIDGE REPLACEMENT | 4 of 7 | $2,765,704 | +10% |
How this record was read
INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
- Every bid counted here matched its published total to within one dollar; INDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.