INDOT contract R-42763-A bid tabulation
NEW ROAD CONSTRUCTION. Let by Indiana DOT on July 9, 2025, Montgomery, Crawfordsville. 5 bids received; low bid $3,383,000 by Calumet Civil Contractors Inc.
- Owner
- Indiana DOT
- Letting
- 09 JUL 2025
- Pay items
- 103
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Calumet Civil Contractors Inc | $3,383,000 | Low |
| 2 | Milestone Contractors LP | $3,436,203 | +2.0% |
| 3 | Crider & Crider Inc | $3,762,484 | +11% |
| 4 | Rieth-Riley Construction Co., Inc. | $3,840,672 | +14% |
| 5 | William Charles Construction Company | $3,947,000 | +17% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Calumet Civil Contractors Inc | 2. Milestone Contractors LP | 3. Crider & Crider Inc | 4. Rieth-Riley Construction Co., Inc. | 5. William Charles Construction Company |
|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $35,000 | $34,291 | $52,500 | $65,000 | $93,163 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, pavement traffic markings (109-09377) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Mobilization and demobilization (110-01001) | LS | 1 | $165,000 | $159,500 | $185,000 | $136,000 | $194,000 |
| 0011 | Clearing right-of-way (201-52370) | LS | 1 | $30,000 | $34,100 | $75,000 | $58,000 | $85,000 |
| 0012 | Excavation, common (203-02000) | CYS | 10,405 | $31.00 | $22.00 | $22.50 | $44.50 | $70.00 |
| 0013 | Borrow (203-02070) | CYS | 10,195 | $17.00 | $24.00 | $18.50 | $43.00 | $0.01 |
| 0014 | Stormwater management budget (205-12108) | DOL | 67,295 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0015 | Stormwater management implementation (205-12616) | LS | 1 | $68,000 | $6,500.00 | $58,000 | $11,500 | $7,000.00 |
| 0016 | SWQCP preparation (205-12618) | LS | 1 | $3,000.00 | $3,000.00 | $6,000.00 | $4,300.00 | $2,500.00 |
| 0017 | Subgrade treatment, type II (207-08264) | SYS | 274 | $24.00 | $25.00 | $27.00 | $65.00 | $32.00 |
| 0018 | Subgrade treatment, type ibc (207-12635) | SYS | 22,840 | $16.00 | $18.00 | $19.00 | $14.00 | $16.50 |
| 0019 | Structure backfill, type 2 (211-09265) | CYS | 344 | $71.00 | $94.00 | $110.00 | $80.00 | $80.00 |
| 0020 | Geogrid, type IB (214-11796) | SYS | 274 | $2.65 | $1.50 | $5.60 | $2.80 | $4.00 |
| 0021 | Chemical modification, soils, cement (215-12637) | SYS | 2,491 | $17.10 | $25.00 | $15.75 | $21.50 | $15.75 |
| 0022 | Compacted aggregate, no. 2 (301-12231) | CYS | 38 | $126.00 | $120.00 | $121.00 | $135.00 | $105.00 |
| 0023 | Compacted aggregate, no. 8 (301-12233) | CYS | 38 | $85.00 | $130.00 | $148.00 | $145.00 | $110.00 |
| 0024 | Compacted aggregate, no. 53 (301-12234) | CYS | 2,085 | $80.00 | $79.00 | $109.00 | $79.00 | $90.00 |
| 0025 | Compacted aggregate, no. 53 (303-01180) | TON | 3,464 | $40.00 | $28.00 | $44.00 | $48.00 | $50.00 |
| 0026 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 104 | $42.00 | $34.00 | $2.11 | $33.00 | $35.00 |
| 0027 | QC/QA-HMA, 2, 58S, surface, 9.5 MM (401-000001) | TON | 1,708 | $107.00 | $105.00 | $118.00 | $118.00 | $118.00 |
| 0028 | QC/QA-HMA, 2, 58S, intermediate, 19.0 MM (401-000037) | TON | 3,880 | $91.00 | $93.00 | $93.00 | $93.00 | $93.00 |
| 0029 | QC/QA-HMA, 2, 58S, base, 19.0 MM (401-000052) | TON | 943 | $91.00 | $111.00 | $93.00 | $93.00 | $93.00 |
| 0030 | QC/QA-HMA, 3, 58E, intermediate, OG, 19.0 MM (401-000062) | TON | 2,616 | $85.00 | $100.00 | $93.00 | $93.00 | $93.00 |
| 0031 | Joint adhesive, surface (401-10258) | LFT | 9,932 | $0.45 | $0.92 | $0.01 | $0.01 | $0.01 |
| 0032 | Joint adhesive, intermediate (401-10259) | LFT | 9,879 | $0.45 | $1.15 | $0.01 | $0.01 | $0.01 |
| 0033 | Asphalt for tack coat (406-05520) | TON | 22 | $1.00 | $100.00 | $650.00 | $650.00 | $650.00 |
| 0034 | Guardrail terminal system, W-beam curved, type 2 (601-01701) | EACH | 1 | $4,150.00 | $3,500.00 | $3,100.00 | $3,450.00 | $3,500.00 |
| 0035 | Guardrail end treatment, type OS , SKT 350 (601-94689) | EACH | 1 | $4,750.00 | $3,600.00 | $3,400.00 | $3,300.00 | $3,600.00 |
| 0036 | Guardrail, W-beam, 6 FT 3 in. spacing (601-99105) | LFT | 38 | $40.00 | $41.00 | $41.00 | $28.00 | $41.00 |
| 0037 | Fence, wood, reset (603-02736) | LFT | 117 | $132.00 | $112.00 | $105.00 | $60.00 | $112.00 |
| 0038 | Fence gate, relocate (603-02969) | LS | 1 | $2,787.00 | $1,750.00 | $1,700.00 | $650.00 | $1,750.00 |
| 0039 | HMA for approaches, type B (610-07487) | TON | 151 | $150.00 | $154.00 | $220.00 | $220.00 | $220.00 |
| 0040 | Right-of-way marker (615-06490) | EACH | 71 | $240.00 | $225.00 | $211.00 | $285.00 | $225.00 |
| 0041 | Monument, type B (615-06505) | EACH | 9 | $1,075.00 | $1,200.00 | $1,150.00 | $1,150.00 | $1,200.00 |
| 0042 | Monument, type C (615-06510) | EACH | 1 | $550.00 | $2,107.00 | $2,107.00 | $725.00 | $2,107.00 |
| 0043 | Monument, section corner (615-06527) | EACH | 3 | $725.00 | $1,300.00 | $1,200.00 | $1,040.00 | $1,300.00 |
| 0044 | Riprap, revetment (616-06405) | TON | 2,228 | $65.00 | $70.00 | $84.00 | $48.50 | $70.00 |
| 0045 | Geotextile for riprap, type 1A (616-12246) | SYS | 2,970 | $3.50 | $1.80 | $5.50 | $1.20 | $4.50 |
| 0046 | Geotextile for riprap, type 2A (616-12248) | SYS | 113 | $9.00 | $1.90 | $6.10 | $7.00 | $8.00 |
| 0047 | Mobilization and demobilization for seeding (621-01004) | EACH | 6 | $800.00 | $800.00 | $800.00 | $625.00 | $800.00 |
| 0048 | Fertilizer, for permanent seeding , for permanent seeding (621-06545) | TON | 3 | $800.00 | $800.00 | $800.00 | $1,495.00 | $800.00 |
| 0049 | Seed mixture, type U (621-06554) | LBS | 1,009 | $6.50 | $6.50 | $6.50 | $7.60 | $6.50 |
| 0050 | Mulching material (621-06565) | TON | 11 | $510.00 | $510.00 | $510.00 | $770.00 | $510.00 |
| 0051 | Water (621-06567) | KGAL | 34 | $1.00 | $34.00 | $1.00 | $10.00 | $1.00 |
| 0052 | Sodding (621-06574) | SYS | 4,217 | $8.98 | $6.88 | $5.50 | $4.98 | $5.50 |
| 0053 | Field office, type C (628-09403) | MOS | 16 | $3,200.00 | $4,000.00 | $3,000.00 | $4,510.00 | $3,800.00 |
| 0054 | Computer system equipment (628-11976) | EACH | 1 | $1,500.00 | $1,050.00 | $3,000.00 | $380.00 | $1,000.00 |
| 0055 | Pipe, type 4, circular, diameter 6 in. (715-05048) | LFT | 6,879 | $11.00 | $9.00 | $6.50 | $9.00 | $11.00 |
| 0056 | Pipe, underdrain outlet, diameter 6 in. (715-05053) | LFT | 595 | $25.00 | $35.00 | $37.00 | $35.00 | $50.00 |
| 0057 | Pipe, type 1, circular, diameter 24 in. (715-05123) | LFT | 254 | $123.00 | $100.00 | $111.50 | $162.00 | $120.00 |
| 0058 | Pipe, type 2, circular, diameter 12 in. (715-05149) | LFT | 129 | $95.00 | $75.00 | $107.00 | $100.00 | $70.00 |
| 0059 | Pipe, type 3, circular, diameter 12 in. (715-05168) | LFT | 89 | $95.00 | $75.00 | $107.00 | $135.00 | $75.00 |
| 0060 | Pipe, type 1, deformed, min. area 3.3 SFT (715-05233) | LFT | 57 | $250.00 | $133.00 | $253.50 | $270.00 | $140.00 |
| 0061 | Pipe end section, min. area 3.3 SFT (715-06471) | EACH | 2 | $3,000.00 | $2,100.00 | $4,200.00 | $2,950.00 | $1,200.00 |
| 0062 | Video inspection for pipe (715-09064) | LFT | 649 | $5.05 | $5.00 | $5.05 | $5.05 | $5.10 |
| 0063 | Pipe end section, min. area 6.3 SFT (715-11529) | EACH | 4 | $3,500.00 | $2,500.00 | $5,000.00 | $4,050.00 | $1,600.00 |
| 0064 | Pipe, type 1, deformed, min. area 6.3 SFT (715-11774) | LFT | 120 | $325.00 | $185.00 | $387.00 | $380.00 | $165.00 |
| 0065 | Pipe end section, diameter 12 in. (715-46000) | EACH | 1 | $1,600.00 | $1,300.00 | $1,500.00 | $2,340.00 | $1,035.00 |
| 0066 | Pipe end section, diameter 24 in. (715-46020) | EACH | 8 | $2,000.00 | $1,700.00 | $2,000.00 | $3,230.00 | $1,800.00 |
| 0067 | Outlet protector, type 2 (718-06529) | EACH | 27 | $400.00 | $2,150.00 | $1,600.00 | $2,150.00 | $2,400.00 |
| 0068 | Outlet protector, type 3 (718-06531) | EACH | 2 | $1,000.00 | $2,000.00 | $1,500.00 | $2,000.00 | $3,000.00 |
| 0069 | Video inspection for underdrain (718-06532) | LFT | 3,000 | $1.25 | $1.30 | $1.25 | $1.25 | $1.50 |
| 0070 | Geotextile for underdrains, type 1A (718-12305) | SYS | 4,816 | $0.70 | $3.75 | $5.20 | $3.75 | $4.97 |
| 0071 | Aggregate for underdrains (718-52610) | CYS | 620 | $72.00 | $75.00 | $111.50 | $75.00 | $90.00 |
| 0072 | Inlet, type E7 (720-45030) | EACH | 1 | $4,200.00 | $3,200.00 | $4,281.00 | $3,360.00 | $3,800.00 |
| 0073 | Inlet, type F7 (720-45035) | EACH | 1 | $3,500.00 | $3,200.00 | $4,587.00 | $3,595.00 | $4,200.00 |
| 0074 | Road closure sign assembly (801-04308) | EACH | 6 | $418.00 | $288.00 | $355.00 | $288.00 | $355.00 |
| 0075 | Detour route marker assembly, multiple routes (801-06196) | EACH | 19 | $368.00 | $177.00 | $135.00 | $177.00 | $135.00 |
| 0077 | Temporary transverse pavement marking, removable, 24 in. (801-06218) | LFT | 88 | $12.78 | $12.44 | $10.00 | $12.44 | $10.00 |
| 0078 | Construction sign, type A (801-06640) | EACH | 22 | $362.00 | $211.00 | $195.00 | $211.00 | $195.00 |
| 0079 | Construction sign, type B (801-06645) | EACH | 10 | $99.00 | $106.00 | $100.00 | $106.00 | $100.00 |
| 0080 | Maintaining traffic (801-06775) | LS | 1 | $74,640 | $85,000 | $55,000 | $24,700 | $100,000 |
| 0081 | Barricade, type III-A (801-07118) | LFT | 144 | $19.00 | $15.44 | $18.00 | $15.44 | $18.00 |
| 0082 | Barricade, type III-B (801-07119) | LFT | 24 | $22.00 | $15.44 | $18.00 | $15.44 | $18.00 |
| 0083 | Portable signal (801-12081) | LS | 1 | $8,500.00 | $17,955 | $52,500 | $11,970 | $12,200 |
| 0084 | Driveway assistance device (801-12482) | EACH | 1 | $4,000.00 | $3,284.00 | $15,750 | $3,284.00 | $5,400.00 |
| 0085 | Sign post, square, type 1, reinforced anchor base (802-05701) | LFT | 379 | $23.00 | $22.00 | $23.00 | $38.00 | $22.00 |
| 0086 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 118 | $34.00 | $45.00 | $34.00 | $45.00 | $45.00 |
| 0087 | Sign, sheet, with legend, 0.100 in. thickness (802-09840) | SFT | 74 | $42.00 | $46.00 | $42.00 | $47.00 | $46.00 |
| 0088 | Sign, sheet, with legend, 0.125 in. thickness (802-09842) | SFT | 9 | $52.00 | $54.00 | $52.00 | $49.00 | $54.00 |
| 0089 | Line, thermoplastic, solid, white, 4 in. (808-06703) | LFT | 8,810 | $0.72 | $0.96 | $1.05 | $0.96 | $1.05 |
| 0090 | Line, remove (808-06716) | LFT | 4,664 | $0.76 | $0.54 | $0.55 | $0.54 | $0.55 |
| 0091 | Retro-reflectivity testing (808-09381) | LS | 1 | $5,380.00 | $3,000.00 | $3,500.00 | $3,000.00 | $3,500.00 |
| 0092 | Line, thermoplastic, dotted, white, 4 in. (808-11482) | LFT | 50 | $1.60 | $5.44 | $6.00 | $5.44 | $6.00 |
| 0093 | Grooving for pavement markings (808-12032) | LFT | 25,700 | $0.89 | $0.67 | $0.66 | $0.67 | $0.66 |
| 0094 | Line, thermoplastic, solid, white, 10 in. (808-12667) | LFT | 820 | $5.74 | $3.11 | $2.08 | $3.11 | $2.08 |
| 0095 | Line, thermoplastic, dotted, white, 10 in. (808-12850) | LFT | 180 | $5.81 | $6.19 | $8.00 | $6.19 | $8.00 |
| 0096 | Line, thermoplastic, solid, white, 6 in. (808-75043) | LFT | 1,660 | $1.04 | $1.23 | $1.25 | $1.23 | $1.25 |
| 0097 | Line, thermoplastic, solid, yellow, 4 in. (808-75245) | LFT | 10,126 | $0.72 | $0.96 | $1.05 | $0.96 | $1.05 |
| 0098 | Line, thermoplastic, solid, yellow, 6 in. (808-75247) | LFT | 3,618 | $1.04 | $1.23 | $1.25 | $1.23 | $1.25 |
| 0099 | Transverse marking, thermoplastic, crosshatch line, yellow, 12 in. (808-75278) | LFT | 320 | $4.92 | $5.81 | $4.95 | $5.81 | $4.95 |
| 0100 | Transverse marking, thermoplastic, stop line, white, 24 in. (808-75297) | LFT | 95 | $9.83 | $14.22 | $12.55 | $14.22 | $12.55 |
| 0101 | Pavement message marking, thermoplastic, lane indication arrow (808-75320) | EACH | 8 | $208.00 | $219.00 | $145.00 | $219.00 | $145.00 |
| 0102 | Pavement message marking, thermoplastic, 'only' (808-75325) | EACH | 5 | $280.00 | $244.00 | $165.00 | $244.00 | $165.00 |
| 0103 | Temporary pavement marking, removable, 4 in. (801-06207) | LFT | 13,747 | $1.64 | $1.96 | $1.30 | $1.96 | $1.30 |
| 0104 | Geotextile for pavement, type 2A (214-12238) | SYS | 17,389 | $2.38 | $2.25 | $4.80 | $2.75 | $4.42 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of July 9, 2025. Compiled by Mirage Metrics.