INDOT contract R-44765-A bid tabulation
SAFETY REVISIONS. Let by Indiana DOT on September 10, 2025, Monroe, Seymour. 5 bids received; low bid $6,273,000 by Calumet Civil Contractors Inc.
- Owner
- Indiana DOT
- Letting
- 10 SEP 2025
- Pay items
- 173
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Calumet Civil Contractors Inc | $6,273,000 | Low |
| 2 | Crider & Crider Inc | $6,440,562 | +3.0% |
| 3 | Morphey Construction Inc. | $6,873,000 | +10% |
| 4 | E & B Paving LLC | $6,985,720 | +11% |
| 5 | Milestone Contractors LP | $8,537,691 | +36% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Calumet Civil Contractors Inc | 2. Crider & Crider Inc | 3. Morphey Construction Inc. | 4. E & B Paving LLC | 5. Milestone Contractors LP |
|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $59,000 | $150,000 | $56,400 | $45,000 | $55,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, PCCP (109-08441) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, pavement traffic markings (109-09377) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0011 | Mobilization and demobilization (110-01001) | LS | 1 | $261,265 | $225,000 | $343,650 | $345,000 | $427,000 |
| 0012 | Clearing right-of-way (201-52370) | LS | 1 | $42,600 | $128,000 | $137,460 | $135,000 | $220,000 |
| 0013 | Pavement removal (202-02240) | SYS | 273 | $22.50 | $24.45 | $45.00 | $40.00 | $26.00 |
| 0014 | Center curb, concrete, remove (202-02273) | SYS | 88 | $47.50 | $82.46 | $30.00 | $50.00 | $105.00 |
| 0015 | Curb, concrete, remove (202-02278) | LFT | 6,498 | $11.00 | $10.14 | $15.00 | $14.50 | $11.00 |
| 0016 | Concrete steps, remove (202-03875) | EACH | 17 | $850.00 | $90.58 | $250.00 | $450.00 | $750.00 |
| 0017 | Wall, stone, reset (202-04126) | LFT | 69 | $100.00 | $47.02 | $250.00 | $155.00 | $480.00 |
| 0018 | Sidewalk concrete, remove (202-52710) | SYS | 2,811 | $14.00 | $18.31 | $20.00 | $18.00 | $20.00 |
| 0019 | Retaining wall, remove (202-90747) | LFT | 246 | $15.00 | $26.81 | $15.00 | $36.00 | $48.00 |
| 0020 | Inlet, remove (202-91385) | EACH | 26 | $650.00 | $671.68 | $250.00 | $500.00 | $900.00 |
| 0021 | Stump, remove (202-91922) | EACH | 23 | $225.00 | $372.55 | $500.00 | $520.00 | $320.00 |
| 0022 | Manhole, remove (202-93047) | EACH | 7 | $700.00 | $798.82 | $500.00 | $1,050.00 | $1,100.00 |
| 0023 | Pipe, remove (202-96133) | LFT | 1,312 | $22.00 | $52.44 | $20.00 | $33.00 | $52.00 |
| 0024 | Excavation, common (203-02000) | CYS | 5,270 | $45.00 | $75.02 | $30.00 | $86.00 | $74.00 |
| 0025 | Excavation, rock (203-02010) | CYS | 235 | $125.00 | $100.00 | $250.00 | $100.00 | $260.00 |
| 0026 | Stormwater management budget (205-12108) | DOL | 19,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0027 | Stormwater management implementation (205-12616) | LS | 1 | $50,000 | $19,465 | $500.00 | $35,000 | $22,000 |
| 0028 | SWQCP preparation (205-12618) | LS | 1 | $3,500.00 | $2,250.00 | $2,000.00 | $3,870.00 | $2,250.00 |
| 0029 | Excavation, X (206-51215) | CYS | 4 | $100.00 | $4,000.00 | $250.00 | $4,000.00 | $4,900.00 |
| 0030 | Subgrade treatment, type II (207-08264) | SYS | 760 | $21.00 | $26.96 | $25.00 | $38.00 | $40.00 |
| 0031 | Subgrade treatment, type IC (207-09935) | SYS | 10,119 | $34.00 | $32.51 | $40.00 | $34.00 | $45.00 |
| 0032 | Structure backfill, type 2 (211-09265) | CYS | 1,516 | $65.00 | $80.10 | $60.00 | $70.00 | $80.00 |
| 0033 | Structure backfill, type 3 (211-09266) | CYS | 42 | $70.00 | $86.98 | $60.00 | $85.00 | $112.00 |
| 0034 | Structure backfill, type 5 (211-09268) | CYS | 205 | $210.00 | $208.68 | $175.00 | $190.00 | $350.00 |
| 0035 | Geogrid, type IB (214-11796) | SYS | 760 | $3.00 | $4.45 | $2.00 | $3.60 | $3.30 |
| 0036 | Compacted aggregate, no. 53 (301-12234) | CYS | 442 | $70.00 | $81.94 | $120.00 | $140.00 | $102.00 |
| 0037 | Dense graded subbase (302-07455) | CYS | 129 | $120.00 | $86.49 | $150.00 | $115.00 | $115.00 |
| 0038 | HMA patching, full depth, type B (304-12623) | TON | 2,908 | $140.00 | $145.00 | $160.00 | $125.00 | $185.00 |
| 0039 | PCC base patching, 8 in. (305-07463) | SYS | 229 | $115.00 | $125.00 | $110.00 | $75.00 | $150.00 |
| 0040 | Milling, asphalt, 2 in. (306-08036) | SYS | 12,200 | $2.50 | $3.00 | $3.00 | $3.00 | $5.00 |
| 0041 | Milling, approach (306-08432) | SYS | 567 | $4.50 | $9.00 | $9.00 | $9.00 | $12.00 |
| 0042 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 1,661 | $130.00 | $130.00 | $130.00 | $130.00 | $134.00 |
| 0043 | QC/QA-HMA, 2, 58S, intermediate, 19.0 MM (401-000037) | TON | 479 | $110.00 | $135.00 | $135.00 | $135.00 | $124.00 |
| 0044 | QC/QA-HMA, 2, 58S, base, 25.0 MM (401-000046) | TON | 798 | $115.00 | $115.00 | $115.00 | $115.00 | $112.00 |
| 0045 | Joint adhesive (401-11526) | LFT | 349 | $2.20 | $4.60 | $4.60 | $4.60 | $3.00 |
| 0046 | Void reducing asphalt membrane for HMA (401-12439) | LFT | 3,504 | $4.80 | $5.50 | $5.50 | $5.50 | $7.00 |
| 0047 | Asphalt for tack coat (406-05520) | TON | 5 | $0.01 | $650.00 | $650.00 | $650.00 | $850.00 |
| 0048 | PCCP, 13 in. (502-06330) | SYS | 58 | $182.00 | $70.00 | $100.00 | $160.00 | $220.00 |
| 0049 | PCCP, 13 in. , stamped and integrally colored concrete (502-06330) | SYS | 365 | $150.00 | $270.00 | $300.00 | $275.00 | $335.00 |
| 0050 | PCCP patching, full depth (506-06333) | SYS | 24 | $210.00 | $82.00 | $137.00 | $265.00 | $650.00 |
| 0051 | Sidewalk, concrete (604-06070) | SYS | 2,873 | $67.00 | $54.00 | $68.00 | $80.00 | $83.00 |
| 0052 | Sidewalk, concrete , bus platform, 6 inch (604-06070) | SYS | 177 | $130.00 | $99.00 | $186.00 | $235.00 | $240.00 |
| 0053 | Pavers (604-07569) | SYS | 51 | $200.00 | $475.76 | $462.00 | $875.00 | $810.00 |
| 0054 | Pavers , street name (604-07569) | SYS | 8 | $500.00 | $1,463.76 | $1,318.00 | $1,160.00 | $1,500.00 |
| 0055 | Stamped concrete sidewalk (604-07823) | SYS | 271 | $125.00 | $90.00 | $105.00 | $225.00 | $190.00 |
| 0056 | Curb ramp, concrete (604-08086) | SYS | 909 | $200.00 | $95.00 | $160.00 | $210.00 | $210.00 |
| 0057 | Detectable warning surfaces (604-12083) | SYS | 160 | $400.00 | $510.00 | $499.00 | $510.00 | $500.00 |
| 0058 | Steps, concrete (604-44251) | CYS | 2 | $1,200.00 | $1,025.00 | $3,000.00 | $3,200.00 | $4,600.00 |
| 0059 | Hand rail, steel (604-92237) | LFT | 52 | $504.00 | $514.22 | $504.00 | $450.00 | $520.00 |
| 0060 | Curb, concrete (605-06120) | LFT | 9,227 | $30.00 | $25.00 | $36.00 | $50.00 | $42.00 |
| 0061 | Center curb, concrete, type D (605-06215) | LFT | 10 | $400.00 | $125.00 | $155.00 | $240.00 | $225.00 |
| 0062 | HMA for approaches, type B (610-07487) | TON | 607 | $150.00 | $200.00 | $237.00 | $195.00 | $193.00 |
| 0063 | PCCP for approaches, 9 in. (610-09108) | SYS | 618 | $117.00 | $107.00 | $127.00 | $150.00 | $160.00 |
| 0064 | Riprap, revetment (616-06405) | TON | 6 | $112.00 | $115.22 | $225.00 | $210.00 | $290.00 |
| 0065 | Geotextile for riprap, type 2A (616-12248) | SYS | 14 | $6.00 | $77.70 | $50.00 | $11.00 | $95.00 |
| 0066 | Topsoil , amended, planting soil (621-06570) | CYS | 1,095 | $106.00 | $100.00 | $105.00 | $90.00 | $135.00 |
| 0067 | Sodding, nursery (621-06575) | SYS | 4,763 | $21.00 | $11.70 | $13.00 | $15.00 | $15.00 |
| 0068 | Mulch, hardwood shredded bark (621-98038) | CYS | 46 | $125.00 | $125.00 | $165.00 | $125.00 | $125.00 |
| 0069 | Plant, deciduous tree, single stem, over 2 in. to 2.5 in. (622-05650) | EACH | 62 | $525.00 | $525.00 | $739.00 | $525.00 | $525.00 |
| 0070 | Plant, deciduous tree, single stem, over 2.5 in. to 3.5 in. (622-05651) | EACH | 39 | $600.00 | $600.00 | $837.00 | $600.00 | $600.00 |
| 0071 | Plant, perennial , ornamental grasses (622-05654) | EACH | 688 | $25.00 | $25.00 | $24.77 | $25.00 | $25.00 |
| 0072 | Field office, type C (628-09403) | MOS | 16 | $3,200.00 | $1,569.84 | $2,500.00 | $2,900.00 | $3,980.00 |
| 0073 | Computer system equipment (628-11976) | EACH | 2 | $1,500.00 | $599.17 | $800.00 | $750.00 | $1,400.00 |
| 0074 | Topsoil processing and distribution (629-000149) | SYS | 4,763 | $23.00 | $3.96 | $8.00 | $5.25 | $15.00 |
| 0075 | Topsoil amendment budget (629-000150) | DOL | 9,526 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0076 | Concrete, A (702-90915) | CYS | 5 | $1,900.00 | $2,200.00 | $2,200.00 | $5,000.00 | $1,800.00 |
| 0077 | Reinforcing bars, epoxy coated (703-06029) | LBS | 1,124 | $4.00 | $2.00 | $4.50 | $7.00 | $4.00 |
| 0078 | Pipe, slotted drain, diameter 4 in. , 0.064 in. (715-000187) | LFT | 52 | $180.00 | $212.24 | $225.00 | $270.00 | $230.00 |
| 0079 | Pipe, type 2, circular, diameter 36 in. (715-05024) | LFT | 25 | $195.00 | $167.65 | $278.00 | $310.00 | $390.00 |
| 0080 | Pipe, type 2, circular, diameter 15 in. (715-05032) | LFT | 324 | $70.00 | $112.45 | $85.00 | $122.00 | $210.00 |
| 0081 | Pipe, type 2, circular, diameter 12 in. (715-05149) | LFT | 208 | $68.00 | $109.80 | $73.00 | $113.00 | $208.00 |
| 0082 | Pipe, type 2, circular, diameter 18 in. (715-05152) | LFT | 179 | $95.00 | $220.61 | $128.00 | $150.00 | $230.00 |
| 0083 | Pipe, type 2, circular, diameter 24 in. (715-05154) | LFT | 320 | $107.00 | $131.70 | $131.00 | $140.00 | $230.00 |
| 0084 | Pipe, type 2, circular, diameter 30 in. (715-05156) | LFT | 240 | $147.00 | $173.60 | $181.00 | $190.00 | $290.00 |
| 0085 | Stormwater quality structure (715-09475) | EACH | 3 | $34,000 | $20,567 | $22,800 | $20,300 | $26,000 |
| 0086 | Pipe end section, diameter 24 in. (715-46020) | EACH | 1 | $1,700.00 | $1,174.30 | $1,600.00 | $1,650.00 | $1,600.00 |
| 0087 | Manhole, type J15, modified (720-01092) | EACH | 17 | $7,000.00 | $6,087.24 | $7,700.00 | $6,100.00 | $7,700.00 |
| 0088 | Catch basin, type , PVC drain basin (720-04666) | EACH | 1 | $2,000.00 | $2,631.44 | $3,600.00 | $3,300.00 | $5,000.00 |
| 0089 | Manhole, type J5, modified (720-08660) | EACH | 3 | $7,000.00 | $6,185.67 | $7,800.00 | $5,000.00 | $7,500.00 |
| 0090 | Inlet, type HA5 (720-45042) | EACH | 11 | $4,000.00 | $4,297.25 | $4,500.00 | $4,000.00 | $5,300.00 |
| 0091 | Manhole, type C4 (720-45410) | EACH | 4 | $5,300.00 | $5,094.51 | $5,500.00 | $4,800.00 | $5,500.00 |
| 0092 | Manhole, type L4 (720-93501) | EACH | 1 | $19,000 | $11,783 | $17,200 | $11,800 | $14,000 |
| 0093 | Manhole, type K4 (720-94612) | EACH | 3 | $11,000 | $7,489.71 | $10,500 | $6,500.00 | $9,600.00 |
| 0094 | Manhole, type J4 (720-95422) | EACH | 1 | $6,500.00 | $5,060.54 | $7,300.00 | $5,400.00 | $7,300.00 |
| 0095 | Inlet, type B15 (720-98174) | EACH | 15 | $4,000.00 | $4,311.01 | $4,500.00 | $4,000.00 | $5,200.00 |
| 0096 | Inlet, type C15 (720-98555) | EACH | 47 | $4,000.00 | $4,277.43 | $4,900.00 | $4,150.00 | $5,200.00 |
| 0097 | Aggregate for drainage fill (732-11770) | CYS | 16 | $65.00 | $275.00 | $265.50 | $170.00 | $170.00 |
| 0098 | Modular block wall (732-11810) | SFT | 333 | $15.00 | $60.00 | $58.00 | $23.00 | $67.00 |
| 0099 | Modular block wall erection (732-11811) | SFT | 333 | $20.00 | $32.00 | $68.00 | $65.00 | $78.00 |
| 0100 | Road closure sign assembly (801-04308) | EACH | 16 | $186.00 | $190.00 | $186.00 | $186.00 | $186.00 |
| 0101 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 12,422 | $1.84 | $1.85 | $1.84 | $1.84 | $1.84 |
| 0102 | Temporary pavement marking, removable, 24 in. (801-06577) | LFT | 127 | $10.47 | $10.50 | $10.47 | $10.47 | $10.47 |
| 0103 | Detour route marker assembly (801-06625) | EACH | 55 | $169.00 | $170.00 | $169.00 | $169.00 | $169.00 |
| 0104 | Construction sign, type A (801-06640) | EACH | 27 | $277.00 | $280.00 | $277.00 | $277.00 | $277.00 |
| 0105 | Construction sign, type B (801-06645) | EACH | 160 | $60.00 | $60.00 | $60.00 | $60.00 | $60.00 |
| 0106 | Maintaining traffic (801-06775) | LS | 1 | $165,000 | $207,265 | $202,104 | $108,212 | $458,323 |
| 0107 | Barricade, type III-A (801-07118) | LFT | 762 | $17.00 | $17.00 | $17.00 | $17.00 | $17.00 |
| 0108 | Barricade, type III-B (801-07119) | LFT | 160 | $29.00 | $29.00 | $29.00 | $29.00 | $29.00 |
| 0109 | Temporary curb ramp (801-11990) | EACH | 2 | $2,000.00 | $4,644.82 | $5,000.00 | $2,000.00 | $4,200.00 |
| 0110 | Fixed temporary signal (801-12082) | LS | 1 | $44,000 | $40,200 | $7,500.00 | $40,200 | $40,200 |
| 0111 | Temporary accessible pedestrian path (801-12641) | SYS | 11 | $106.16 | $40.00 | $420.00 | $220.00 | $330.00 |
| 0112 | Temporary pedestrian channelizer (801-12862) | LFT | 84 | $19.47 | $30.00 | $40.00 | $40.00 | $40.00 |
| 0113 | Signal head relocate (801-94295) | EACH | 14 | $550.00 | $825.00 | $850.00 | $825.00 | $825.00 |
| 0114 | Sign post, square, type 1, unreinforced anchor base (802-05704) | LFT | 533 | $30.00 | $30.00 | $48.00 | $30.00 | $30.00 |
| 0115 | Sign, sheet, and supports, remove (802-07059) | EACH | 66 | $50.00 | $40.00 | $50.00 | $40.00 | $40.00 |
| 0116 | Sign, sheet, relocate (802-07060) | EACH | 7 | $250.00 | $300.00 | $75.00 | $300.00 | $300.00 |
| 0117 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 457 | $30.00 | $40.00 | $36.00 | $40.00 | $40.00 |
| 0118 | Sign, sheet, with legend, 0.100 in. thickness (802-09840) | SFT | 51 | $32.00 | $55.00 | $38.00 | $55.00 | $55.00 |
| 0119 | Sign, sheet, with legend, 0.125 in. thickness (802-09842) | SFT | 39 | $34.00 | $62.00 | $40.00 | $62.00 | $62.00 |
| 0120 | Traffic signal equipment, remove (805-01300) | EACH | 2 | $8,500.00 | $3,500.00 | $3,000.00 | $3,460.00 | $3,460.00 |
| 0121 | Handhole, signal, type 1 (805-01842) | EACH | 9 | $2,500.00 | $2,000.00 | $4,000.00 | $1,950.00 | $1,950.00 |
| 0122 | Pedestrian signal head, countdown, 18 in. (805-02150) | EACH | 16 | $1,000.00 | $820.00 | $2,000.00 | $820.00 | $820.00 |
| 0123 | Controller and cabinet, type P1 (805-02445) | EACH | 2 | $35,000 | $36,000 | $33,000 | $36,000 | $36,000 |
| 0124 | Signal pole foundation, 24 in. X 24 in. X 36 in. (805-02645) | EACH | 15 | $2,000.00 | $1,520.00 | $3,500.00 | $1,520.00 | $1,520.00 |
| 0125 | Video vehicle detector system (805-04782) | EACH | 2 | $35,000 | $36,000 | $33,000 | $36,000 | $36,000 |
| 0126 | Signal pole, pedestal, 4 FT (805-05405) | EACH | 4 | $1,000.00 | $1,000.00 | $1,500.00 | $980.00 | $980.00 |
| 0127 | Signal cantilever structure, single arm 15 FT (805-11373) | EACH | 1 | $18,500 | $19,000 | $18,500 | $18,800 | $18,800 |
| 0128 | Signal cantilever structure, single arm 20 FT (805-11374) | EACH | 1 | $19,000 | $19,500 | $19,500 | $19,350 | $19,350 |
| 0129 | Signal cantilever structure, single arm 25 FT (805-11375) | EACH | 2 | $20,000 | $20,500 | $35,000 | $20,340 | $20,340 |
| 0130 | Signal cantilever structure, single arm 30 FT (805-11376) | EACH | 3 | $21,000 | $21,050 | $52,500 | $21,050 | $21,050 |
| 0131 | Signal cantilever structure, single arm 35 FT (805-11377) | EACH | 1 | $22,000 | $22,000 | $21,000 | $21,780 | $21,780 |
| 0132 | Signal cantilever structure, drilled shaft foundation, type A (805-11383) | EACH | 8 | $13,500 | $8,000.00 | $9,500.00 | $7,850.00 | $7,850.00 |
| 0133 | Conduit, HDPE, 2 in. schedule 80 (805-11815) | LFT | 1,341 | $30.00 | $52.00 | $47.00 | $52.00 | $52.00 |
| 0134 | Pedestrian push button, APS (805-11817) | EACH | 16 | $1,200.00 | $1,000.00 | $2,500.00 | $1,000.00 | $1,000.00 |
| 0135 | Traffic signal head, no. 3 (805-78205) | EACH | 17 | $1,200.00 | $1,100.00 | $1,500.00 | $1,100.00 | $1,100.00 |
| 0136 | Traffic signal head, no. 4 (805-78225) | EACH | 6 | $1,500.00 | $1,360.00 | $2,000.00 | $1,360.00 | $1,360.00 |
| 0137 | Traffic signal head, no. 5 (805-78230) | EACH | 1 | $2,100.00 | $2,000.00 | $2,500.00 | $1,980.00 | $1,980.00 |
| 0138 | Signal service (805-78445) | EACH | 1 | $2,500.00 | $2,250.00 | $5,400.00 | $2,240.00 | $2,240.00 |
| 0139 | Signal cable, service, copper, 3C/8 gauge (805-78467) | LFT | 283 | $5.00 | $3.00 | $15.00 | $3.00 | $3.00 |
| 0140 | Signal cable, control, copper, 5C/14 gauge (805-78485) | LFT | 4,061 | $5.00 | $3.00 | $4.00 | $3.00 | $3.00 |
| 0141 | Signal cable, control, copper, 7C/14 gauge (805-78490) | LFT | 1,376 | $5.50 | $3.50 | $6.00 | $3.50 | $3.50 |
| 0142 | Signal cable, control, copper, 9C/14 gauge (805-78495) | LFT | 878 | $5.75 | $3.80 | $8.00 | $3.80 | $3.80 |
| 0143 | Controller cabinet foundation, type P1 (805-78925) | EACH | 2 | $3,500.00 | $3,000.00 | $4,000.00 | $2,950.00 | $2,950.00 |
| 0144 | Signal pole, pedestal, 10 FT (805-90005) | EACH | 11 | $1,500.00 | $1,500.00 | $2,000.00 | $1,450.00 | $1,450.00 |
| 0145 | Pavement message marking, thermoplastic, bike symbol (808-02977) | EACH | 30 | $402.00 | $405.00 | $402.00 | $402.00 | $402.00 |
| 0146 | Transverse marking, thermoplastic, crosswalk line, white, 24 in. (808-03439) | LFT | 982 | $7.39 | $7.50 | $7.39 | $7.39 | $7.39 |
| 0147 | Pavement message marking, remove (808-05866) | SYS | 16 | $39.00 | $40.00 | $39.00 | $39.00 | $39.00 |
| 0148 | Transverse marking, remove (808-06368) | LFT | 109 | $5.60 | $5.75 | $5.60 | $5.60 | $5.60 |
| 0149 | Line, thermoplastic, solid, white, 4 in. (808-06703) | LFT | 1,440 | $0.82 | $0.85 | $0.82 | $0.82 | $0.82 |
| 0150 | Line, remove (808-06716) | LFT | 9,657 | $0.88 | $0.90 | $0.88 | $0.88 | $0.88 |
| 0151 | Retro-reflectivity testing (808-09381) | LS | 1 | $3,061.00 | $3,100.00 | $3,061.00 | $3,061.00 | $3,061.00 |
| 0152 | Pavement marking , mma, solid, green (808-09968) | SFT | 5,849 | $10.00 | $9.50 | $9.50 | $9.50 | $9.50 |
| 0153 | Line, thermoplastic, dotted, white, 4 in. (808-11482) | LFT | 43 | $2.51 | $2.55 | $2.51 | $2.51 | $2.51 |
| 0154 | Transverse marking, thermoplastic, yield line, white, 18 in. (808-11953) | LFT | 30 | $15.60 | $16.00 | $15.60 | $15.60 | $15.60 |
| 0155 | Grooving for pavement markings (808-12032) | LFT | 9,058 | $1.03 | $1.05 | $1.03 | $1.03 | $1.03 |
| 0156 | Transverse marking, thermoplastic, crosswalk line, white, 12 in. (808-74815) | LFT | 338 | $3.45 | $3.50 | $3.45 | $3.45 | $3.45 |
| 0157 | Line, thermoplastic, broken, yellow, 4 in. (808-75240) | LFT | 524 | $1.95 | $2.00 | $1.95 | $1.95 | $1.95 |
| 0158 | Line, thermoplastic, solid, yellow, 4 in. (808-75245) | LFT | 7,051 | $0.81 | $0.85 | $0.81 | $0.81 | $0.81 |
| 0159 | Transverse marking, thermoplastic, crosshatch line, white, 12 in. (808-75260) | LFT | 8 | $3.45 | $3.50 | $3.45 | $3.45 | $3.45 |
| 0160 | Transverse marking, thermoplastic, crosshatch line, yellow, 12 in. (808-75278) | LFT | 80 | $3.45 | $3.50 | $3.45 | $3.45 | $3.45 |
| 0161 | Transverse marking, thermoplastic, stop line, white, 24 in. (808-75297) | LFT | 234 | $7.39 | $7.50 | $7.39 | $7.39 | $7.39 |
| 0162 | Transverse marking, thermoplastic, crosswalk line, white, 6 in. (808-75300) | LFT | 196 | $1.73 | $1.75 | $1.73 | $1.73 | $1.73 |
| 0163 | Pavement message marking, thermoplastic, lane indication arrow (808-75320) | EACH | 35 | $158.00 | $160.00 | $158.00 | $158.00 | $158.00 |
| 0164 | Snowplowable raised pavement marker (808-75998) | EACH | 12 | $230.00 | $300.00 | $300.00 | $500.00 | $230.00 |
| 0165 | Curb, concrete , depressed (605-06120) | LFT | 1,499 | $44.00 | $28.00 | $36.00 | $55.00 | $59.00 |
| 0166 | Curb, concrete , 14 in. (605-06120) | LFT | 214 | $54.00 | $200.00 | $162.00 | $105.00 | $140.00 |
| 0167 | Pipe, type 2, circular, diameter 36 in. , water main grade (715-05024) | LFT | 43 | $570.00 | $322.84 | $425.00 | $430.00 | $580.00 |
| 0168 | Pipe, type 2, circular, diameter 15 in. , water main grade (715-05032) | LFT | 929 | $124.00 | $128.83 | $104.00 | $136.00 | $226.00 |
| 0169 | Pipe, type 2, circular, diameter 12 in. , water main grade (715-05149) | LFT | 893 | $88.00 | $115.30 | $97.00 | $124.00 | $200.00 |
| 0170 | Pipe, type 2, circular, diameter 18 in. , water main grade (715-05152) | LFT | 505 | $153.00 | $153.47 | $114.00 | $168.00 | $230.00 |
| 0171 | Pipe, type 2, circular, diameter 24 in. , water main grade (715-05154) | LFT | 401 | $250.00 | $167.07 | $210.00 | $182.00 | $275.00 |
| 0172 | Pipe, type 2, circular, diameter 30 in. , water main grade (715-05156) | LFT | 241 | $280.00 | $232.99 | $250.00 | $260.00 | $372.00 |
| 0173 | Cap , existing utility line (715-06050) | EACH | 21 | $1,100.00 | $3,587.08 | $382.00 | $1,300.00 | $2,600.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of September 10, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.