INDOT contract R-44460-A bid tabulation

SMALL STRUCTURE REPLACEMENT. Let by Indiana DOT on August 5, 2026, Owen, Seymour. 8 bids received; low bid $1,471,572 by Crider & Crider Inc.

Owner
Indiana DOT
Letting
05 AUG 2026
Pay items
67
Data through
05 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Crider & Crider Inc$1,471,572Low
2Force Construction Co Inc$1,525,690+4.0%
3Rieth-Riley Construction Co., Inc.$1,540,189+5.0%
4E & B Paving LLC$1,578,110+7.0%
5Milestone Contractors LP$1,672,338+14%
6CLR Inc$1,673,966+14%
7Morphey Construction Inc.$1,748,000+19%
8Ragle, Inc.$1,788,437+22%
INDOT contract R-44460-A: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Crider & Crider Inc2. Force Construction Co Inc3. Rieth-Riley Construction Co., Inc.4. E & B Paving LLC5. Milestone Contractors LP6. CLR Inc
0001Construction engineering (105-06845)LS1$50,000$9,112.00$5,900.00$15,000$6,500.00$35,000
0002Railroad flagging budget (107-12976)DOL51,500$1.00$1.00$1.00$1.00$1.00$1.00
0003Liquidated damages (109-08359)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0004Contract liens (109-08360)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0005Quality adjustments, HMA (109-08440)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0006Quality adjustments, temporary traffic control devices and markings (109-08443)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0007Quality adjustments, failed materials (109-08444)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0008Payment adjustment, PG asphalt binder (109-09489)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0009Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362)DOL1$1.00$1.00$1.00$1.00$1.00$1.00
0010Mobilization and demobilization (110-01001)LS1$68,000$76,500$44,977$75,000$83,500$84,325
0011Clearing right-of-way (201-52370)LS1$29,000$15,420$22,872$14,523$25,000$33,700
0012Pipe, remove (202-96133)LFT165$200.00$20.00$51.00$50.00$18.00$72.00
0013Excavation, common (203-02000)CYS1,005$70.00$41.00$75.82$65.00$120.00$35.00
0014Pump around (205-11626)EACH2$8,000.00$8,782.00$14,338$10,000$12,100$25,000
0015Stormwater management budget (205-12108)DOL10,600$1.00$1.00$1.00$1.00$1.00$1.00
0016Stormwater management implementation (205-12616)LS1$6,000.00$13,700$5,452.48$6,500.00$6,799.05$1,900.00
0017Subgrade treatment, type IC (207-09935)SYS2,832$35.00$34.00$48.00$46.00$30.00$25.00
0018Structure backfill, type 2 (211-09265)CYS322$80.00$82.00$101.03$75.00$72.00$70.00
0019Structure backfill, type 5 (211-09268)CYS648$190.00$232.00$188.69$245.00$185.00$140.00
0020Geotextile for pavement, type 2B (214-12239)SYS2,200$3.00$3.70$3.40$5.10$3.40$6.25
0021Compacted aggregate, no. 8 (301-12233)CYS121$120.00$74.00$136.02$115.00$130.00$190.00
0022Compacted aggregate, no. 53 (303-01180)TON147$50.00$43.00$73.68$95.00$97.00$125.00
0023Milling, asphalt, 1 1/2 in. (306-08034)SYS237$17.00$23.00$21.24$15.00$37.00$13.00
0024QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005)TON191$190.00$199.00$240.03$230.00$188.00$209.00
0025QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041)TON306$190.00$197.00$177.89$220.00$186.00$207.00
0026QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047)TON1,070$125.00$129.00$139.52$130.00$122.00$122.00
0027Joint adhesive (401-11526)LFT288$1.25$1.30$0.58$5.00$1.20$1.20
0028Asphalt for tack coat (406-05520)TON3$750.00$795.00$0.01$750.00$750.00$750.00
0029Guardrail connector system, W-beam, curved, type 1 (601-01625)EACH1$1,825.00$2,808.00$1,825.00$1,825.00$1,825.00$3,650.00
0030Guardrail, remove (601-02241)LFT460$5.00$8.50$5.00$5.00$5.00$3.50
0031Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281)LFT363$22.00$26.00$22.00$22.00$22.00$25.00
0032Guardrail height transition, MGS (601-12289)EACH1$950.00$1,483.00$950.00$950.00$950.00$1,050.00
0033Guardrail end treatment, type OS (601-94689)EACH2$3,000.00$3,179.00$2,995.00$2,995.00$2,995.00$3,325.00
0034HMA for approaches, type B (610-07487)TON202$220.00$223.00$240.90$180.00$210.00$233.00
0035Monument, type B (615-06505)EACH2$1,150.00$1,987.00$1,125.00$1,125.00$1,125.00$425.00
0036Riprap, class 2 (616-05689)TON173$95.00$95.00$146.11$125.00$85.00$130.00
0037Riprap, revetment (616-06405)TON67$150.00$73.00$126.89$140.00$85.00$115.00
0038Geotextile for riprap, type 1A (616-12246)SYS312$3.50$4.30$3.22$5.00$3.10$8.00
0039Mobilization and demobilization for seeding (621-01004)EACH2$400.00$848.00$800.00$400.00$200.00$1,100.00
0040Mulched seeding, type R (621-06559)SYS1,780$3.30$2.40$2.25$3.25$4.00$1.85
0041Topsoil (621-06570)CYS24$180.00$158.00$107.41$210.00$160.00$75.00
0042Computer system equipment (628-11976)EACH2$500.00$907.00$1,114.35$1,000.00$1,150.00$100.00
0043Field office, type D (628-12683)MOS6$1,950.00$4,535.00$3,788.77$4,000.00$3,400.00$1,400.00
0044Temporary shoring (702-04325)LS1$30,000$39,750$70,006$22,000$128,000$21,000
0045Waterproofing membrane, type 2 (714-000086)SFT5,421$2.10$3.90$4.51$3.25$2.65$2.50
0046Structure, coated reinforced concrete, box sections, 15 FT X 7 FT (714-12697)LFT112$2,750.00$2,669.00$2,689.41$2,919.50$3,303.00$4,625.00
0047Pipe, type 1, circular, diameter 36 in. (715-05019)LFT50$250.00$150.00$388.81$400.00$225.00$161.00
0048Pipe end section, diameter 36 in. (715-46040)EACH1$2,250.00$2,191.00$2,776.18$2,000.00$2,650.00$1,500.00
0049Temporary pavement marking, removable, 6 in. (801-06209)LFT9,096$2.00$2.10$2.22$1.99$2.00$1.58
0050Temporary transverse pavement marking, removable, 24 in. (801-06218)LFT240$11.75$12.00$13.15$12.00$12.00$9.23
0051Temporary pavement marking, removable, 8 in. (801-06469)LFT143$3.75$4.00$4.40$2.50$2.50$4.15
0052Construction sign, type A (801-06640)EACH24$190.00$200.00$236.00$200.00$200.00$300.00
0053Construction sign, type B (801-06645)EACH16$105.00$109.00$107.00$120.00$120.00$103.00
0054Maintaining traffic (801-06775)LS1$12,000$87,003$28,928$25,000$31,700$51,386
0055Energy absorbing terminal, CZ, TL-2 (801-07023)EACH2$6,000.00$10,070$5,800.00$5,800.00$5,800.00$6,425.00
0056Barricade, type III-A (801-07118)LFT50$16.00$17.00$13.00$17.25$17.25$15.00
0057Temporary traffic barrier, anchored, type 2 (801-08508)LFT925$55.00$71.00$39.89$60.00$97.00$50.00
0058Portable signal (801-12081)LS1$20,000$12,400$10,000$30,000$7,000.00$45,000
0059Driveway assistance device (801-12482)EACH2$2,650.00$4,572.00$3,000.00$9,000.00$5,000.00$1,000.00
0060Temporary worksite speed limit sign assembly, continuous (801-12883)EACH4$950.00$999.00$342.00$825.00$825.00$1,050.00
0061Line, remove (808-06716)LFT4,845$0.71$0.75$0.58$0.70$0.70$0.71
0062Line, multi-component, solid, white, 6 in. (808-10049)LFT1,938$1.00$1.00$3.42$1.20$1.20$0.98
0063Line, multi-component, solid, yellow, 6 in. (808-10057)LFT1,838$1.00$1.00$3.42$1.20$1.20$0.98
0064Line, multi-component, broken, white, 6 in. (808-10071)LFT25$2.00$2.10$3.42$1.80$1.80$2.00
0065Grooving for pavement markings (808-12032)LFT3,826$0.80$0.85$1.35$0.80$0.80$0.78
0066Line, multi-component, broken, yellow, 6 in. (808-12841)LFT25$2.00$2.10$3.42$1.80$1.80$2.00
0067Guardrail, MGS, structure top-mounted posts (601-12293)EACH4$420.00$689.00$420.00$420.00$420.00$475.00
INDOT contract R-44460-A: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.

Every contract let that day: INDOT letting of August 5, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.