KYTC contract 25-1039 bid tabulation
BRIDGE WITH GRADE, DRAIN & SURFACE KY 115 STRUCTURE OVER I-24. Let by Kentucky Transportation Cabinet on December 11, 2025. 4 bids received; low bid $3,555,000 by Hall Contracting of Kentucky Inc, -5.3% against the engineer's estimate of $3,753,612.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 11 DEC 2025
- Pay items
- 88
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Hall Contracting of Kentucky Inc | $3,555,000 | Low | -5.0% |
| 2 | Ragle Inc | $3,748,123 | +5.0% | 0.0% |
| 3 | Jim Smith Contracting Company LLC | $3,765,158 | +6.0% | 0.0% |
| 4 | American Contracting & Services Inc | $3,810,498 | +7.0% | +2.0% |
Engineer's estimate: $3,753,612.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Hall Contracting of Kentucky Inc | 2. Ragle Inc | 3. Jim Smith Contracting Company LLC | 4. American Contracting & Services Inc |
|---|---|---|---|---|---|---|---|
| 0010 | Crushed stone base | TON A A | 1,220 | $38.00 | $48.00 | $53.22 | $54.00 |
| 0020 | Asphalt seal aggregate | TON A A | 12.20 | $443.00 | $275.00 | $443.00 | $450.00 |
| 0030 | Asphalt seal coat | TON A A | 1.50 | $1,564.50 | $2,000.00 | $1,564.50 | $1,600.00 |
| 0040 | CL3 asph base 1.00D PG64-22 | TON A A | 142 | $196.20 | $175.00 | $196.20 | $200.00 |
| 0050 | CL3 asph base 1.00D PG76-22 | TON A A | 131 | $213.10 | $175.00 | $213.10 | $215.00 |
| 0060 | CL3 asph surf 0.50A PG76-22 | TON A A | 52 | $422.40 | $300.00 | $422.40 | $425.00 |
| 0070 | Asphalt material for tack non-tracking | TON A A | 0.50 | $2,100.00 | $1,800.00 | $2,100.00 | $2,100.00 |
| 0080 | Crushed aggregate size no 2 | TON A A | 1,108 | $45.00 | $45.00 | $36.88 | $50.00 |
| 0090 | Perforated pipe-4 in | LF A A | 200 | $13.00 | $20.00 | $20.53 | $30.00 |
| 0100 | Perforated pipe-6 in | LF A A | 100 | $15.00 | $26.00 | $46.00 | $32.00 |
| 0110 | Non-perforated pipe-4 in | LF A A | 64 | $18.00 | $27.00 | $37.17 | $75.00 |
| 0120 | Non-perforated pipe-6 in | LF A A | 32 | $20.00 | $33.00 | $41.49 | $85.00 |
| 0130 | Inspect & certify edge drain system | LS A A | 1 | $3,000.00 | $1,500.00 | $2,500.00 | $2,500.00 |
| 0140 | Perf pipe headwall TY 1-4 in | EACH A A | 4 | $700.00 | $1,750.00 | $897.12 | $2,400.00 |
| 0150 | Perf pipe headwall TY 4-6 in | EACH A A | 4 | $900.00 | $1,650.00 | $959.20 | $2,500.00 |
| 0160 | Flume inlet type 2 | EACH A A | 2 | $6,000.00 | $6,300.00 | $8,200.00 | $4,000.00 |
| 0170 | Standard header curb mod | LF A A | 156 | $55.00 | $30.00 | $87.25 | $75.00 |
| 0180 | Delineator for guardrail BI directional white | EACH A A | 12 | $15.52 | $15.50 | $15.52 | $20.00 |
| 0190 | Barricade-type III | EACH A A | 22 | $80.00 | $275.00 | $471.22 | $200.00 |
| 0200 | Temp ditch | LF A A | 446 | $2.00 | $2.00 | $0.50 | $7.00 |
| 0210 | Clean temp ditch | LF A A | 223 | $1.00 | $1.50 | $0.25 | $6.00 |
| 0220 | Embankment in place | CUYD A A | 4,317 | $66.00 | $28.00 | $26.79 | $55.00 |
| 0230 | Water | MGAL A A | 8 | $1.00 | $50.00 | $77.60 | $1.00 |
| 0240 | Guardrail-steel W beam-S face | LF A A | 187.50 | $33.13 | $33.13 | $33.13 | $34.00 |
| 0250 | Guardrail end treatment type 1 | EACH A A | 2 | $3,551.47 | $3,551.47 | $3,551.47 | $3,600.00 |
| 0260 | Guardrail end treatment type 2M | EACH A A | 2 | $1,912.36 | $1,912.36 | $1,912.36 | $2,000.00 |
| 0270 | Channel lining class III | TON A A | 346 | $50.00 | $57.14 | $46.64 | $70.00 |
| 0280 | Clearing and grubbing | LS A A | 1 | $50,000 | $5,000.00 | $18,000 | $10,000 |
| 0290 | Temporary signs | SQFT A A | 500 | $8.50 | $20.00 | $12.02 | $15.00 |
| 0300 | Fabric-geotextile class 1 | SQYD A A | 2,794 | $2.37 | $3.00 | $2.32 | $3.00 |
| 0310 | Fabric-geotextile class 1A | SQYD A A | 1,122 | $4.62 | $3.00 | $4.42 | $3.30 |
| 0320 | Maintain & control traffic | LS A A | 1 | $100,000 | $40,000 | $15,732 | $125,000 |
| 0330 | Portable changeable message sign | EACH A A | 6 | $4,200.00 | $10,500 | $1,264.13 | $4,900.00 |
| 0340 | Shoulder rumble strips | LF A A | 414 | $7.50 | $10.00 | $12.05 | $19.50 |
| 0350 | Temp silt fence | LF A A | 446 | $4.50 | $3.00 | $2.26 | $5.00 |
| 0360 | Silt trap type A | EACH A A | 1 | $250.00 | $250.00 | $255.18 | $2,500.00 |
| 0370 | Silt trap type B | EACH A A | 1 | $250.00 | $425.00 | $244.87 | $1,500.00 |
| 0380 | Silt trap type C | EACH A A | 1 | $250.00 | $360.00 | $244.87 | $500.00 |
| 0390 | Clean silt trap type A | EACH A A | 1 | $25.00 | $50.00 | $81.43 | $1,500.00 |
| 0400 | Clean silt trap type B | EACH A A | 1 | $25.00 | $40.00 | $81.43 | $750.00 |
| 0410 | Clean silt trap type C | EACH A A | 1 | $25.00 | $50.00 | $81.43 | $200.00 |
| 0420 | Staking | LS A A | 1 | $75,000 | $40,000 | $12,077 | $20,000 |
| 0430 | Arrow panel | EACH A A | 2 | $1,300.00 | $6,000.00 | $1,022.87 | $4,000.00 |
| 0440 | Conc barrier wall type 9T | LF A A | 2,000 | $42.00 | $40.00 | $121.96 | $65.00 |
| 0450 | Erosion control blanket | SQYD A A | 1,466 | $2.57 | $2.00 | $2.57 | $2.60 |
| 0460 | Temp mulch | SQYD A A | 1,428 | $0.42 | $1.50 | $0.42 | $1.00 |
| 0470 | Temp seeding and protection | SQYD A A | 1,428 | $0.45 | $1.50 | $0.45 | $1.00 |
| 0480 | Initial fertilizer | TON A A | 0.30 | $1,684.60 | $2,450.00 | $1,684.60 | $1,700.00 |
| 0490 | Maintenance fertilizer | TON A A | 0.20 | $1,684.60 | $2,450.00 | $1,684.60 | $1,700.00 |
| 0500 | Seeding and protection | SQYD A A | 3,691 | $0.76 | $2.00 | $0.76 | $1.00 |
| 0510 | Agricultural limestone | TON A A | 0.20 | $89.01 | $2,100.00 | $89.00 | $100.00 |
| 0520 | Pave striping-temp paint-6 in | LF A A | 1,000 | $1.25 | $2.50 | $1.25 | $1.25 |
| 0530 | Pave striping-thermo-6 in W | LF A A | 251 | $6.00 | $6.00 | $6.00 | $6.00 |
| 0540 | Pave striping-thermo-6 in Y | LF A A | 177 | $6.00 | $6.00 | $6.00 | $6.00 |
| 0550 | Inlaid pavement marker-MW | EACH A A | 3 | $300.00 | $160.00 | $700.00 | $500.00 |
| 0560 | Inlaid pavement marker-MY | EACH A A | 3 | $300.00 | $160.00 | $700.00 | $500.00 |
| 0570 | Concrete-class A | CUYD A A | 11.60 | $1,000.00 | $1,650.00 | $1,700.74 | $800.00 |
| 0580 | Steel reinforcement | LB A A | 525 | $1.50 | $1.75 | $2.33 | $4.00 |
| 0590 | Crash cushion TY 6 class D TL3 | EACH A A | 1 | $50,000 | $66,567 | $66,567 | $67,000 |
| 0600 | Crash cushion TY 6 class T TL3 | EACH A A | 4 | $4,600.00 | $6,000.00 | $5,567.50 | $9,000.00 |
| 0610 | Temporary pipe | LF A A | 100 | $60.00 | $50.00 | $65.91 | $60.00 |
| 0620 | Object marker TY 3 | EACH A A | 7 | $46.15 | $35.00 | $46.15 | $50.00 |
| 0630 | Remove crash cushion | EACH A A | 1 | $3,000.00 | $750.00 | $2,500.00 | $2,500.00 |
| 0640 | Remove barrier wall transition | LS A A | 1 | $4,000.00 | $2,000.00 | $9,153.70 | $4,000.00 |
| 0650 | G/R steel W beam-S face (7 FT post) | LF A A | 625 | $35.27 | $35.27 | $35.27 | $36.00 |
| 0660 | Water blasting existing stripe | LF A A | 1,000 | $3.50 | $1.00 | $3.50 | $3.50 |
| 0670 | Turf reinforcement mat 1 | SQYD A A | 1,091 | $11.26 | $10.00 | $11.26 | $12.00 |
| 0680 | Pave stripe-perm paint-6 in wet ref-W | LF A A | 310 | $9.00 | $9.00 | $2.00 | $9.00 |
| 0690 | Pave stripe-perm paint-6 in wet ref-Y | LF A A | 248 | $9.00 | $9.00 | $2.00 | $9.00 |
| 0700 | Thrie beam guardrail transition TL-2 | EACH A A | 4 | $4,500.00 | $3,054.79 | $3,142.04 | $3,100.00 |
| 0710 | Electronic delivery MGMT system - agg | LS A A | 1 | $1.00 | $1.00 | $6,207.64 | $3,500.00 |
| 0720 | Structure granular backfill | CUYD A A | 436 | $80.00 | $72.00 | $94.19 | $100.00 |
| 0730 | Armored edge for concrete | LF A A | 65.60 | $100.00 | $95.00 | $69.84 | $130.00 |
| 0740 | Foundation preparation | LS A A | 1 | $60,000 | $88,000 | $103,709 | $130,000 |
| 0750 | Crushed aggregate slope prot | TON A A | 365 | $52.00 | $50.00 | $44.90 | $90.00 |
| 0760 | Test piles | LF A A | 248 | $120.00 | $136.00 | $327.12 | $150.00 |
| 0770 | Piles-steel HP14X89 | LF A A | 2,087 | $120.00 | $145.00 | $114.17 | $120.00 |
| 0780 | Pile points-14 in | EACH A A | 34 | $170.00 | $200.00 | $201.64 | $350.00 |
| 0790 | Concrete-class A | CUYD A A | 233.10 | $950.00 | $1,400.00 | $1,202.01 | $730.00 |
| 0800 | Concrete-class AA | CUYD A A | 369.90 | $1,050.00 | $1,080.00 | $1,379.28 | $775.00 |
| 0810 | Steel reinforcement | LB A A | 30,722 | $1.50 | $1.80 | $1.76 | $1.70 |
| 0820 | Steel reinforcement-epoxy coated | LB A A | 112,507 | $1.65 | $1.91 | $1.78 | $1.80 |
| 0830 | Concrete sealing | SQFT A A | 19,410 | $1.20 | $1.45 | $2.14 | $3.00 |
| 0840 | PPC I-beam HN 48-49 | LF A A | 1,228 | $750.00 | $890.00 | $748.28 | $890.00 |
| 0850 | Rail system single slope - 40 in | LF A A | 496 | $150.00 | $145.00 | $147.93 | $150.00 |
| 0860 | Mobilization for concrete surf treatment | LS A A | 1 | $2,000.00 | $150.00 | $33,213 | $5,000.00 |
| 0870 | Mobilization | LS A A | 1 | $166,800 | $170,000 | $176,765 | $177,188 |
| 0880 | Demobilization | LS A A | 1 | $50,435 | $55,000 | $53,031 | $56,395 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of December 11, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.