KYTC contract 25-1310 bid tabulation

BRIDGE REPLACEMENT SETSER BRANCH ROAD (CR 1215). Let by Kentucky Transportation Cabinet on May 22, 2025. 5 bids received; low bid $549,091 by Hinkle Construction Services LLC, -4.1% against the engineer's estimate of $572,284.

Owner
Kentucky Transportation Cabinet
Letting
22 MAY 2025
Pay items
57
Data through
22 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Hinkle Construction Services LLC$549,091Low-4.0%
2Frederick & May Construction Co$556,368+1.0%-3.0%
3M & M Services Co Inc$576,336+5.0%+1.0%
4Bush & Burchett Inc$595,041+8.0%+4.0%
5Walker Construction & Materials LLC$721,215+31%+26%
KYTC contract 25-1310: bids by rank

Engineer's estimate: $572,284.

Bid tabulation

LinePay itemUnitQuantity1. Hinkle Construction Services LLC2. Frederick & May Construction Co3. M & M Services Co Inc4. Bush & Burchett Inc5. Walker Construction & Materials LLC
0010Dga baseTON A A135$56.36$95.75$65.00$95.75$99.00
0020Asphalt seal aggregateTON A A2.20$983.92$930.00$2,200.00$930.00$1,250.00
0030Asphalt seal coatTON A A0.26$4,549.32$4,300.00$2,200.00$4,300.00$10,000
0040CL2 asph base 1.00D PG64-22TON A A188$343.10$324.30$135.00$324.30$350.00
0050CL2 asph surf 0.38D PG64-22TON A A37$379.55$358.75$135.00$358.75$500.00
0060Asphalt material for tackTON A A0.37$714.14$675.00$1,500.00$675.00$1,000.00
0070Culvert pipe-15 inLF A A36$118.40$100.00$85.00$108.00$200.00
0080Pipe culvert headwall-15 inEACH A A2$2,013.60$1,500.00$4,500.00$1,500.00$2,000.00
0090Delineator for guardrail BI directional whiteEACH A A4$19.48$18.14$20.00$19.00$15.00
0100Barricade-type IIIEACH A A2$116.91$125.00$350.00$200.00$175.00
0110Remove pavementSQYD A A88$14.21$15.00$45.00$15.00$30.00
0120Temp ditchLF A A148$1.66$1.00$15.00$1.00$0.50
0130Clean temp ditchLF A A74$0.01$0.10$15.00$1.00$0.20
0140Roadway excavationCUYD A A220$83.63$112.00$35.00$50.00$150.00
0150WaterMGAL A A1$0.01$1.00$10.00$1.00$1.00
0160Guardrail terminal section no 1EACH A A3$95.14$88.60$95.00$89.00$110.00
0170Guardrail end treatment type 7EACH A A1$2,434.33$2,266.92$2,500.00$2,267.00$1,500.00
0180Witness postEACH A A8$126.85$186.61$190.00$187.00$225.00
0190Channel lining class IITON A A108$54.04$55.00$105.00$55.00$75.00
0200Clearing and grubbingLS A A1$9,755.00$44,008$11,500$50,000$75,000
0210Temporary signsSQFT A A145$18.71$20.00$15.00$17.00$17.00
0220Fabric-geotextile class 1SQYD A A108$3.01$3.00$10.00$5.00$25.00
0230Fabric-geotextile class 2 for pipeSQYD A A48$2.00$2.00$2.00$2.00$2.00
0240Maintain & control trafficLS A A1$57,909$12,000$45,000$37,000$25,000
0250Temp silt fenceLF A A148$7.57$3.00$3.00$4.00$3.00
0260Silt trap type AEACH A A1$123.08$100.00$50.00$100.00$500.00
0270Silt trap type BEACH A A1$759.13$100.00$50.00$100.00$500.00
0280Silt trap type CEACH A A1$664.04$100.00$50.00$100.00$250.00
0290Clean silt trap type AEACH A A1$0.01$10.00$15.00$1.00$50.00
0300Clean silt trap type BEACH A A1$0.01$10.00$15.00$1.00$50.00
0310Clean silt trap type CEACH A A1$0.01$10.00$15.00$1.00$50.00
0320StakingLS A A1$2,647.12$7,500.00$14,500$10,000$9,000.00
0330Erosion control blanketSQYD A A108$3.91$3.64$4.00$4.00$25.00
0340Temp mulchSQYD A A800$0.43$0.40$0.50$0.40$4.00
0350Temp seeding and protectionSQYD A A600$0.48$0.45$0.50$0.45$4.00
0360Initial fertilizerTON A A0.73$1,288.62$1,200.00$1,350.00$1,200.00$2,000.00
0370Maintenance fertilizerTON A A0.73$1,288.62$1,200.00$1,350.00$1,200.00$2,000.00
0380Seeding and protectionSQYD A A1,092$2.37$2.21$3.00$2.21$6.25
0390Agricultural limestoneTON A A2.19$91.28$85.00$105.00$85.00$200.00
0400G/R steel W beam-S face (7 FT post)LF A A145$52.68$49.06$55.00$50.00$50.00
0410R/W monument type 3EACH A A8$148.90$205.15$225.00$206.00$300.00
0420Structure granular backfillCUYD A A82$143.19$81.00$65.00$100.00$115.00
0430Remove structureLS A A1$17,283$7,500.00$45,000$16,000$30,000
0440Armored edge for concreteLF A A33.10$70.39$150.00$105.00$115.00$150.00
0450Foundation preparationLS A A1$28,506$35,000$48,000$60,000$51,151
0460Cyclopean stone rip rapTON A A202$68.76$60.00$56.00$60.00$75.00
0470Test pilesLF A A75$106.71$154.00$300.00$200.00$130.00
0480Piles-steel HP12X53LF A A204$117.70$144.00$205.00$100.00$130.00
0490Pile points-12 inEACH A A8$151.99$208.00$225.00$150.00$190.00
0500Concrete-class ACUYD A A21$1,630.20$1,700.00$1,400.00$1,500.00$2,500.00
0510Concrete-class AACUYD A A19.90$2,828.39$3,000.00$1,800.00$2,500.00$3,500.00
0520Steel reinforcement-epoxy coatedLB A A4,214$2.77$2.80$2.25$2.50$1.90
0530Precast PC box beam CB17-48LF A A198$388.37$425.00$450.00$450.00$450.00
0540Concrete sealingSQFT A A1,327$3.34$3.00$3.00$3.00$3.00
0550Deep beam bridge guardrailLF A A83$358.63$333.97$380.00$334.00$350.00
0560Mobilization for concrete surf treatmentLS A A1$1,323.53$1,000.00$2,800.00$1,000.00$1,750.00
0570DemobilizationLS A A1$9,000.00$8,223.00$15,000$9,000.00$11,999
KYTC contract 25-1310: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.

Every contract let that day: KYTC letting of May 22, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy