KYTC contract 25-1310 bid tabulation
BRIDGE REPLACEMENT SETSER BRANCH ROAD (CR 1215). Let by Kentucky Transportation Cabinet on May 22, 2025. 5 bids received; low bid $549,091 by Hinkle Construction Services LLC, -4.1% against the engineer's estimate of $572,284.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 22 MAY 2025
- Pay items
- 57
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Hinkle Construction Services LLC | $549,091 | Low | -4.0% |
| 2 | Frederick & May Construction Co | $556,368 | +1.0% | -3.0% |
| 3 | M & M Services Co Inc | $576,336 | +5.0% | +1.0% |
| 4 | Bush & Burchett Inc | $595,041 | +8.0% | +4.0% |
| 5 | Walker Construction & Materials LLC | $721,215 | +31% | +26% |
Engineer's estimate: $572,284.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Hinkle Construction Services LLC | 2. Frederick & May Construction Co | 3. M & M Services Co Inc | 4. Bush & Burchett Inc | 5. Walker Construction & Materials LLC |
|---|---|---|---|---|---|---|---|---|
| 0010 | Dga base | TON A A | 135 | $56.36 | $95.75 | $65.00 | $95.75 | $99.00 |
| 0020 | Asphalt seal aggregate | TON A A | 2.20 | $983.92 | $930.00 | $2,200.00 | $930.00 | $1,250.00 |
| 0030 | Asphalt seal coat | TON A A | 0.26 | $4,549.32 | $4,300.00 | $2,200.00 | $4,300.00 | $10,000 |
| 0040 | CL2 asph base 1.00D PG64-22 | TON A A | 188 | $343.10 | $324.30 | $135.00 | $324.30 | $350.00 |
| 0050 | CL2 asph surf 0.38D PG64-22 | TON A A | 37 | $379.55 | $358.75 | $135.00 | $358.75 | $500.00 |
| 0060 | Asphalt material for tack | TON A A | 0.37 | $714.14 | $675.00 | $1,500.00 | $675.00 | $1,000.00 |
| 0070 | Culvert pipe-15 in | LF A A | 36 | $118.40 | $100.00 | $85.00 | $108.00 | $200.00 |
| 0080 | Pipe culvert headwall-15 in | EACH A A | 2 | $2,013.60 | $1,500.00 | $4,500.00 | $1,500.00 | $2,000.00 |
| 0090 | Delineator for guardrail BI directional white | EACH A A | 4 | $19.48 | $18.14 | $20.00 | $19.00 | $15.00 |
| 0100 | Barricade-type III | EACH A A | 2 | $116.91 | $125.00 | $350.00 | $200.00 | $175.00 |
| 0110 | Remove pavement | SQYD A A | 88 | $14.21 | $15.00 | $45.00 | $15.00 | $30.00 |
| 0120 | Temp ditch | LF A A | 148 | $1.66 | $1.00 | $15.00 | $1.00 | $0.50 |
| 0130 | Clean temp ditch | LF A A | 74 | $0.01 | $0.10 | $15.00 | $1.00 | $0.20 |
| 0140 | Roadway excavation | CUYD A A | 220 | $83.63 | $112.00 | $35.00 | $50.00 | $150.00 |
| 0150 | Water | MGAL A A | 1 | $0.01 | $1.00 | $10.00 | $1.00 | $1.00 |
| 0160 | Guardrail terminal section no 1 | EACH A A | 3 | $95.14 | $88.60 | $95.00 | $89.00 | $110.00 |
| 0170 | Guardrail end treatment type 7 | EACH A A | 1 | $2,434.33 | $2,266.92 | $2,500.00 | $2,267.00 | $1,500.00 |
| 0180 | Witness post | EACH A A | 8 | $126.85 | $186.61 | $190.00 | $187.00 | $225.00 |
| 0190 | Channel lining class II | TON A A | 108 | $54.04 | $55.00 | $105.00 | $55.00 | $75.00 |
| 0200 | Clearing and grubbing | LS A A | 1 | $9,755.00 | $44,008 | $11,500 | $50,000 | $75,000 |
| 0210 | Temporary signs | SQFT A A | 145 | $18.71 | $20.00 | $15.00 | $17.00 | $17.00 |
| 0220 | Fabric-geotextile class 1 | SQYD A A | 108 | $3.01 | $3.00 | $10.00 | $5.00 | $25.00 |
| 0230 | Fabric-geotextile class 2 for pipe | SQYD A A | 48 | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 |
| 0240 | Maintain & control traffic | LS A A | 1 | $57,909 | $12,000 | $45,000 | $37,000 | $25,000 |
| 0250 | Temp silt fence | LF A A | 148 | $7.57 | $3.00 | $3.00 | $4.00 | $3.00 |
| 0260 | Silt trap type A | EACH A A | 1 | $123.08 | $100.00 | $50.00 | $100.00 | $500.00 |
| 0270 | Silt trap type B | EACH A A | 1 | $759.13 | $100.00 | $50.00 | $100.00 | $500.00 |
| 0280 | Silt trap type C | EACH A A | 1 | $664.04 | $100.00 | $50.00 | $100.00 | $250.00 |
| 0290 | Clean silt trap type A | EACH A A | 1 | $0.01 | $10.00 | $15.00 | $1.00 | $50.00 |
| 0300 | Clean silt trap type B | EACH A A | 1 | $0.01 | $10.00 | $15.00 | $1.00 | $50.00 |
| 0310 | Clean silt trap type C | EACH A A | 1 | $0.01 | $10.00 | $15.00 | $1.00 | $50.00 |
| 0320 | Staking | LS A A | 1 | $2,647.12 | $7,500.00 | $14,500 | $10,000 | $9,000.00 |
| 0330 | Erosion control blanket | SQYD A A | 108 | $3.91 | $3.64 | $4.00 | $4.00 | $25.00 |
| 0340 | Temp mulch | SQYD A A | 800 | $0.43 | $0.40 | $0.50 | $0.40 | $4.00 |
| 0350 | Temp seeding and protection | SQYD A A | 600 | $0.48 | $0.45 | $0.50 | $0.45 | $4.00 |
| 0360 | Initial fertilizer | TON A A | 0.73 | $1,288.62 | $1,200.00 | $1,350.00 | $1,200.00 | $2,000.00 |
| 0370 | Maintenance fertilizer | TON A A | 0.73 | $1,288.62 | $1,200.00 | $1,350.00 | $1,200.00 | $2,000.00 |
| 0380 | Seeding and protection | SQYD A A | 1,092 | $2.37 | $2.21 | $3.00 | $2.21 | $6.25 |
| 0390 | Agricultural limestone | TON A A | 2.19 | $91.28 | $85.00 | $105.00 | $85.00 | $200.00 |
| 0400 | G/R steel W beam-S face (7 FT post) | LF A A | 145 | $52.68 | $49.06 | $55.00 | $50.00 | $50.00 |
| 0410 | R/W monument type 3 | EACH A A | 8 | $148.90 | $205.15 | $225.00 | $206.00 | $300.00 |
| 0420 | Structure granular backfill | CUYD A A | 82 | $143.19 | $81.00 | $65.00 | $100.00 | $115.00 |
| 0430 | Remove structure | LS A A | 1 | $17,283 | $7,500.00 | $45,000 | $16,000 | $30,000 |
| 0440 | Armored edge for concrete | LF A A | 33.10 | $70.39 | $150.00 | $105.00 | $115.00 | $150.00 |
| 0450 | Foundation preparation | LS A A | 1 | $28,506 | $35,000 | $48,000 | $60,000 | $51,151 |
| 0460 | Cyclopean stone rip rap | TON A A | 202 | $68.76 | $60.00 | $56.00 | $60.00 | $75.00 |
| 0470 | Test piles | LF A A | 75 | $106.71 | $154.00 | $300.00 | $200.00 | $130.00 |
| 0480 | Piles-steel HP12X53 | LF A A | 204 | $117.70 | $144.00 | $205.00 | $100.00 | $130.00 |
| 0490 | Pile points-12 in | EACH A A | 8 | $151.99 | $208.00 | $225.00 | $150.00 | $190.00 |
| 0500 | Concrete-class A | CUYD A A | 21 | $1,630.20 | $1,700.00 | $1,400.00 | $1,500.00 | $2,500.00 |
| 0510 | Concrete-class AA | CUYD A A | 19.90 | $2,828.39 | $3,000.00 | $1,800.00 | $2,500.00 | $3,500.00 |
| 0520 | Steel reinforcement-epoxy coated | LB A A | 4,214 | $2.77 | $2.80 | $2.25 | $2.50 | $1.90 |
| 0530 | Precast PC box beam CB17-48 | LF A A | 198 | $388.37 | $425.00 | $450.00 | $450.00 | $450.00 |
| 0540 | Concrete sealing | SQFT A A | 1,327 | $3.34 | $3.00 | $3.00 | $3.00 | $3.00 |
| 0550 | Deep beam bridge guardrail | LF A A | 83 | $358.63 | $333.97 | $380.00 | $334.00 | $350.00 |
| 0560 | Mobilization for concrete surf treatment | LS A A | 1 | $1,323.53 | $1,000.00 | $2,800.00 | $1,000.00 | $1,750.00 |
| 0570 | Demobilization | LS A A | 1 | $9,000.00 | $8,223.00 | $15,000 | $9,000.00 | $11,999 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of May 22, 2025. Compiled by Mirage Metrics.