KYTC contract 25-5376 bid tabulation
BRIDGE REPLACEMENT LAWRENCEBURG ROAD (KY 53). Let by Kentucky Transportation Cabinet on April 24, 2025, Washington, District 4. 4 bids received; low bid $2,587,610 by Frederick & May Construction Co, -21% against the engineer's estimate of $3,264,104.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 24 APR 2025
- Pay items
- 57
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Frederick & May Construction Co | $2,587,610 | Low | -21% |
| 2 | Hinkle Construction Services LLC | $2,716,037 | +5.0% | -17% |
| 3 | Haydon Bridge Company Inc | $3,126,966 | +21% | -4.0% |
| 4 | Hall Contracting of Kentucky Inc | $4,388,000 | +70% | +34% |
Engineer's estimate: $3,264,104.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Frederick & May Construction Co | 2. Hinkle Construction Services LLC | 3. Haydon Bridge Company Inc | 4. Hall Contracting of Kentucky Inc |
|---|---|---|---|---|---|---|---|
| 0010 | Dga base | TON A | 298 | $40.00 | $60.70 | $100.00 | $60.00 |
| 0020 | Asphalt seal aggregate | TON A | 8 | $280.00 | $297.00 | $280.00 | $1,100.00 |
| 0030 | Asphalt seal coat | TON A | 1 | $3,500.00 | $3,713.00 | $3,500.00 | $2,600.00 |
| 0040 | Leveling & wedging PG64-22 | TON A | 31 | $225.00 | $238.00 | $225.00 | $190.00 |
| 0050 | CL2 asph base 1.00D PG64-22 | TON A | 256 | $170.00 | $180.00 | $190.00 | $210.00 |
| 0060 | CL2 asph surf 0.38D PG64-22 | TON A | 63 | $225.00 | $238.00 | $245.00 | $260.00 |
| 0070 | Asphalt material for tack | TON A | 2 | $675.00 | $716.00 | $675.00 | $2.00 |
| 0080 | Mobilization for mill & text | LS A | 1 | $2,500.00 | $2,970.00 | $2,800.00 | $3,500.00 |
| 0090 | Asphalt pave milling & texturing | TON A | 30 | $45.00 | $180.00 | $170.00 | $200.00 |
| 0100 | Longitudinal edge key | LF A | 100 | $25.00 | $26.50 | $25.00 | $60.00 |
| 0110 | Entrance pipe-24 in | LF A | 30 | $100.00 | $126.60 | $170.00 | $160.00 |
| 0120 | Barricade-type III | EACH A | 24 | $50.00 | $150.00 | $1.00 | $125.00 |
| 0130 | Granular embankment | CUYD A | 310 | $57.00 | $88.00 | $90.00 | $70.00 |
| 0140 | Embankment in place | CUYD A | 608 | $20.00 | $14.20 | $50.00 | $150.00 |
| 0150 | Remove fence | LF A | 190 | $11.35 | $6.80 | $12.00 | $11.35 |
| 0160 | Guardrail terminal section no 1 | EACH A | 1 | $81.88 | $117.00 | $90.00 | $81.88 |
| 0170 | Guardrail end treatment type 1 | EACH A | 3 | $3,698.29 | $4,135.00 | $3,950.00 | $3,698.29 |
| 0180 | Remove guardrail | LF A | 570 | $4.38 | $5.30 | $4.60 | $4.38 |
| 0190 | Clearing and grubbing | LS A | 1 | $85,117 | $19,930 | $150,000 | $24,000 |
| 0200 | Temporary signs | SQFT A | 1,110 | $8.50 | $8.40 | $10.00 | $5.00 |
| 0210 | Maintain & control traffic | LS A | 1 | $250.00 | $23,000 | $32,500 | $250,000 |
| 0220 | Portable changeable message sign | EACH A | 2 | $5,200.00 | $4,410.00 | $8,000.00 | $3,180.00 |
| 0230 | Staking | LS A | 1 | $14,000 | $7,000.00 | $12,000 | $36,000 |
| 0240 | Remove structure | LS A | 1 | $150,000 | $151,130 | $135,000 | $480,000 |
| 0250 | SBM alum sheet signs .080 in | SQFT A | 11 | $58.33 | $53.00 | $60.00 | $58.33 |
| 0260 | Steel post type 1 | LF A | 14 | $44.53 | $53.00 | $45.00 | $44.53 |
| 0270 | Pave striping-perm paint-4 in | LF A | 468 | $1.50 | $1.55 | $1.60 | $4.00 |
| 0280 | Pave striping-dur TY 1-4 in Y | LF A | 502 | $7.00 | $7.40 | $10.00 | $8.00 |
| 0290 | Object marker TY 3 | EACH A | 3 | $37.72 | $107.00 | $40.00 | $37.72 |
| 0300 | Erosion control | LS A | 1 | $7,500.00 | $12,315 | $25,000 | $80,000 |
| 0310 | G/R steel W beam-S face (7 FT post) | LF A | 500 | $33.24 | $34.00 | $34.00 | $33.24 |
| 0320 | Barcode sign inventory | EACH A | 4 | $46.06 | $53.00 | $50.00 | $46.06 |
| 0330 | Structure granular backfill | CUYD A | 161 | $57.00 | $118.00 | $90.00 | $70.00 |
| 0340 | Armored edge for concrete | LF A | 168 | $160.00 | $92.00 | $150.00 | $138.00 |
| 0350 | Foundation preparation | LS A | 1 | $126,000 | $159,000 | $75,000 | $280,000 |
| 0360 | Cyclopean stone rip rap | TON A | 466 | $58.00 | $69.00 | $75.00 | $80.00 |
| 0370 | Test piles | LF A | 56 | $179.00 | $126.00 | $325.00 | $170.00 |
| 0380 | Piles-steel HP12X53 | LF A | 235 | $169.00 | $150.00 | $90.00 | $170.00 |
| 0390 | Pile points-12 in | EACH A | 12 | $200.00 | $143.00 | $500.00 | $160.00 |
| 0400 | Concrete-class A | CUYD A | 167 | $1,600.00 | $1,875.00 | $1,410.00 | $2,320.00 |
| 0410 | Concrete-class AA | CUYD A | 309 | $1,155.00 | $1,070.00 | $1,505.00 | $1,900.00 |
| 0420 | Steel reinforcement | LB A | 25,961 | $1.50 | $1.55 | $2.10 | $1.50 |
| 0430 | Steel reinforcement-epoxy coated | LB A | 83,520 | $1.60 | $1.65 | $1.90 | $1.60 |
| 0440 | Approach slab | SQYD A | 133 | $500.00 | $610.00 | $775.00 | $550.00 |
| 0450 | Precast PC I beam type 3 | LF A | 1,274 | $384.00 | $397.00 | $450.00 | $484.00 |
| 0460 | Drilled shaft-rock 48 in | LF A | 48 | $2,280.00 | $2,585.00 | $3,170.00 | $5,590.00 |
| 0470 | Rock soundings | LF A | 66 | $28.75 | $92.00 | $135.00 | $59.00 |
| 0480 | Rock corings | LF A | 120 | $63.25 | $145.00 | $190.00 | $155.00 |
| 0490 | CSL testing (4 tubes) | EACH A | 6 | $1,000.00 | $2,500.00 | $1,250.00 | $8,000.00 |
| 0500 | Drilled shaft-54 in-common | LF A | 54 | $1,960.00 | $2,335.00 | $3,170.00 | $2,700.00 |
| 0510 | Concrete sealing | SQFT A | 22,658 | $2.50 | $1.50 | $2.40 | $3.50 |
| 0520 | Deck drain | EACH A | 16 | $450.00 | $970.00 | $950.00 | $1,200.00 |
| 0530 | Rail system single slope - 40 in | LF A | 647 | $150.00 | $136.00 | $140.00 | $170.00 |
| 0540 | Thrie beam guardrail transition TL-3 | EACH A | 4 | $4,402.00 | $6,215.00 | $5,750.00 | $5,100.00 |
| 0550 | Mobilization for concrete surf treatment | LS A | 1 | $2,500.00 | $1,650.00 | $750.00 | $3,600.00 |
| 0560 | Mobilization | LS A | 1 | $105,000 | $125,000 | $146,500 | $205,759 |
| 0570 | Demobilization | LS A | 1 | $38,241 | $40,000 | $44,336 | $61,807 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of April 24, 2025. Compiled by Mirage Metrics.