KYTC contract 25-5380 bid tabulation

BRIDGE REPLACEMENT OTTER CREEK ROAD (CR 1160). Let by Kentucky Transportation Cabinet on April 24, 2025, Clay, District 11. 5 bids received; low bid $216,487 by Kay & Kay Contracting LLC, -48% against the engineer's estimate of $419,657.

Owner
Kentucky Transportation Cabinet
Letting
24 APR 2025
Pay items
32
Data through
22 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Kay & Kay Contracting LLC$216,487Low-48%
2Irvine Contracting Limited Liability Company$351,019+62%-16%
3Hinkle Construction Services LLC$387,028+79%-8.0%
4Jave LLC$432,597+100%+3.0%
5M & M Services Co Inc$503,924+133%+20%
KYTC contract 25-5380: bids by rank

Engineer's estimate: $419,657.

Bid tabulation

LinePay itemUnitQuantity1. Kay & Kay Contracting LLC2. Irvine Contracting Limited Liability Company3. Hinkle Construction Services LLC4. Jave LLC5. M & M Services Co Inc
0010Dga baseTON A158.54$46.50$75.00$57.50$130.47$65.00
0020CL2 asph base 1.00D PG64-22TON A10.76$112.00$800.00$850.00$840.00$450.00
0030CL2 asph surf 0.38D PG64-22TON A5.30$106.00$1,500.00$1,590.00$1,575.00$1,000.00
0040Granular embankmentCUYD A6.03$253.00$166.00$197.00$522.60$400.00
0050Asphalt pave milling & texturingTON A3.70$20.00$1,100.00$1,165.00$1,155.00$650.00
0060Delineator for guardrail BI directional whiteEACH A6$17.22$18.00$17.90$17.85$18.00
0070Barricade-type IIIEACH A4$230.00$50.00$154.00$105.00$350.00
0080Guardrail-steel W beam-S faceLF A156$37.76$38.50$68.40$68.25$45.00
0090Guardrail terminal section no 1EACH A2$88.43$110.00$115.00$115.50$92.00
0100Guardrail end treatment type 7EACH A2$2,007.15$1,500.00$2,315.00$2,310.00$2,400.00
0110Temp guardrailLF A437$28.82$15.00$15.75$15.75$34.00
0120Clearing and grubbingLS A1$6,500.00$33,654$9,425.00$18,728$18,000
0130Temporary signsSQFT A95.50$16.00$18.00$20.00$10.50$15.00
0140Edge keyLF A22$16.00$200.00$212.00$210.00$35.00
0150Maintain & control trafficLS A1$10,500$3,500.00$71,000$2,625.00$65,000
0160Diversions (by-pass detours)LS A1$46,600$110,000$85,000$136,322$98,000
0170Portable changeable message signEACH A3$1,484.00$2,226.00$1,950.00$3,895.50$4,500.00
0180StakingLS A1$2,000.00$5,000.00$2,675.00$3,250.00$8,500.00
0190Foundation preparationLS A1$4,500.00$8,000.00$9,800.00$8,175.70$85,000
0200Erosion controlLS A1$3,500.00$6,000.00$3,500.00$10,400$8,500.00
0210Structure granular backfillCUYD A28$126.00$150.00$109.00$170.38$65.00
0220Waterproofing membraneSQYD A50$43.00$90.00$82.50$105.30$300.00
0230Cyclopean stone rip rapTON A31$81.00$62.00$96.50$166.99$105.00
0240Concrete-class ACUYD A0.50$13,050$14,000$13,100$24,458$6,800.00
0250Steel reinforcementLB A200$6.80$13.00$2.25$6.50$5.00
0260Remove superstructureLS A1$7,450.00$15,000$11,750$27,323$15,000
0270Precast PC box beam B17-48LF A106$426.00$450.00$427.00$530.99$560.00
0280Concrete patching repairSQFT A50$151.00$145.00$480.00$237.90$305.00
0290Concrete sealingSQFT A725$2.50$3.00$4.00$8.84$4.00
0300Rail system side mounted MGSLF A63$290.09$325.00$273.00$378.30$300.00
0310Concrete coatingSQFT A800$3.25$5.00$17.00$8.13$10.00
0320DemobilizationLS A1$3,199.32$5,638.00$6,000.00$6,393.05$7,702.10
KYTC contract 25-5380: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.

Every contract let that day: KYTC letting of April 24, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy