KYTC contract 25-7000 bid tabulation

CULVERT REPLACEMENT BLAIR BRANCH ROAD (CR 1339). Let by Kentucky Transportation Cabinet on January 23, 2025, Letcher, District 12. 7 bids received; low bid $221,176 by Keetech Constr Horizontal Directional Drilling & Utilities, -45% against the engineer's estimate of $404,440.

Owner
Kentucky Transportation Cabinet
Letting
23 JAN 2025
Pay items
25
Data through
22 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Keetech Constr Horizontal Directional Drilling & Utilities$221,176Low-45%
2Walker Construction & Materials LLC$234,234+6.0%-42%
3Delmae LLC$249,656+13%-38%
4Jave LLC$261,384+18%-35%
5Hinkle Construction Services LLC$268,850+22%-34%
6Mountain Enterprises Inc$321,763+45%-20%
7Bush & Burchett Inc$346,567+57%-14%
KYTC contract 25-7000: bids by rank

Engineer's estimate: $404,440.

Bid tabulation

LinePay itemUnitQuantity1. Keetech Constr Horizontal Directional Drilling & Utilities2. Walker Construction & Materials LLC3. Delmae LLC4. Jave LLC5. Hinkle Construction Services LLC6. Mountain Enterprises Inc
0010Dga baseTON A120$67.10$57.00$50.00$69.11$70.63$67.10
0020Asphalt seal aggregateTON A1$2,350.00$1,000.00$2,350.00$2,420.50$2,473.68$2,350.00
0030Asphalt seal coatTON A1$3,650.00$1,000.00$3,650.00$3,759.50$3,842.11$3,650.00
0040CL2 asph base 1.00D PG64-22TON A48$465.00$245.00$465.00$478.95$489.47$465.00
0050CL2 asph surf 0.38D PG64-22TON A8$585.00$945.00$585.00$602.55$615.79$585.00
0060Fabric-geotextile class 2SQYD A245$7.00$4.00$2.00$13.50$5.85$2.00
0070Asphalt material for tack non-trackingTON A1$1,450.00$2.00$1,450.00$1,493.50$1,526.31$1,450.00
0080Barricade-type IIIEACH A2$200.00$160.00$150.00$103.00$169.40$200.00
0090Roadway excavationCUYD A50$80.00$10.00$85.00$53.87$115.00$200.00
0100Granular embankmentCUYD A20$50.00$65.00$100.00$218.70$144.76$150.00
0110WaterMGAL A20$1.00$1.00$1.00$1.35$0.01$0.25
0120Guardrail-steel W beam-S faceLF A62.50$65.00$82.00$80.00$82.40$84.21$129.53
0130Guardrail terminal section no 1EACH A1$150.00$205.00$200.00$206.00$210.53$202.51
0140Guardrail end treatment type 7EACH A3$1,850.00$2,100.00$2,000.00$2,060.00$2,105.26$3,500.00
0150Clearing and grubbingLS A1$10,000$40,000$20,000$22,518$2,946.64$33,000
0160Edge keyLF A20.90$67.00$80.00$67.50$69.01$70.53$67.00
0170Maintain & control trafficLS A1$7,500.00$5,000.00$15,000$14,978$48,250$12,000
0180Portable changeable message signEACH A2$8,000.00$750.00$1,000.00$764.26$948.66$1,000.00
0190StakingLS A1$4,000.00$5,000.00$2,500.00$3,375.00$2,700.00$2,100.00
0200Remove structureLS A1$5,000.00$5,000.00$5,000.00$8,151.30$3,000.00$37,500
0210SoddingSQYD A40$45.00$25.00$35.00$67.50$37.69$152.92
0215Cyclopean stone rip rapTON A82$68.00$75.00$55.00$112.48$90.70$92.00
0220Erosion controlLS A1$10,000$975.00$1,500.00$7,290.00$3,166.49$4,000.00
0230Aluminum structural plate box culvertLF A40.50$1,987.65$3,000.00$3,250.00$2,972.70$3,100.00$3,360.00
0240DemobilizationLS A1$20,000$3,525.00$6,000.00$3,862.82$3,975.00$4,826.44
KYTC contract 25-7000: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.

Every contract let that day: KYTC letting of January 23, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy