KYTC contract 25-7000 bid tabulation
CULVERT REPLACEMENT BLAIR BRANCH ROAD (CR 1339). Let by Kentucky Transportation Cabinet on January 23, 2025, Letcher, District 12. 7 bids received; low bid $221,176 by Keetech Constr Horizontal Directional Drilling & Utilities, -45% against the engineer's estimate of $404,440.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 23 JAN 2025
- Pay items
- 25
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Keetech Constr Horizontal Directional Drilling & Utilities | $221,176 | Low | -45% |
| 2 | Walker Construction & Materials LLC | $234,234 | +6.0% | -42% |
| 3 | Delmae LLC | $249,656 | +13% | -38% |
| 4 | Jave LLC | $261,384 | +18% | -35% |
| 5 | Hinkle Construction Services LLC | $268,850 | +22% | -34% |
| 6 | Mountain Enterprises Inc | $321,763 | +45% | -20% |
| 7 | Bush & Burchett Inc | $346,567 | +57% | -14% |
Engineer's estimate: $404,440.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Keetech Constr Horizontal Directional Drilling & Utilities | 2. Walker Construction & Materials LLC | 3. Delmae LLC | 4. Jave LLC | 5. Hinkle Construction Services LLC | 6. Mountain Enterprises Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Dga base | TON A | 120 | $67.10 | $57.00 | $50.00 | $69.11 | $70.63 | $67.10 |
| 0020 | Asphalt seal aggregate | TON A | 1 | $2,350.00 | $1,000.00 | $2,350.00 | $2,420.50 | $2,473.68 | $2,350.00 |
| 0030 | Asphalt seal coat | TON A | 1 | $3,650.00 | $1,000.00 | $3,650.00 | $3,759.50 | $3,842.11 | $3,650.00 |
| 0040 | CL2 asph base 1.00D PG64-22 | TON A | 48 | $465.00 | $245.00 | $465.00 | $478.95 | $489.47 | $465.00 |
| 0050 | CL2 asph surf 0.38D PG64-22 | TON A | 8 | $585.00 | $945.00 | $585.00 | $602.55 | $615.79 | $585.00 |
| 0060 | Fabric-geotextile class 2 | SQYD A | 245 | $7.00 | $4.00 | $2.00 | $13.50 | $5.85 | $2.00 |
| 0070 | Asphalt material for tack non-tracking | TON A | 1 | $1,450.00 | $2.00 | $1,450.00 | $1,493.50 | $1,526.31 | $1,450.00 |
| 0080 | Barricade-type III | EACH A | 2 | $200.00 | $160.00 | $150.00 | $103.00 | $169.40 | $200.00 |
| 0090 | Roadway excavation | CUYD A | 50 | $80.00 | $10.00 | $85.00 | $53.87 | $115.00 | $200.00 |
| 0100 | Granular embankment | CUYD A | 20 | $50.00 | $65.00 | $100.00 | $218.70 | $144.76 | $150.00 |
| 0110 | Water | MGAL A | 20 | $1.00 | $1.00 | $1.00 | $1.35 | $0.01 | $0.25 |
| 0120 | Guardrail-steel W beam-S face | LF A | 62.50 | $65.00 | $82.00 | $80.00 | $82.40 | $84.21 | $129.53 |
| 0130 | Guardrail terminal section no 1 | EACH A | 1 | $150.00 | $205.00 | $200.00 | $206.00 | $210.53 | $202.51 |
| 0140 | Guardrail end treatment type 7 | EACH A | 3 | $1,850.00 | $2,100.00 | $2,000.00 | $2,060.00 | $2,105.26 | $3,500.00 |
| 0150 | Clearing and grubbing | LS A | 1 | $10,000 | $40,000 | $20,000 | $22,518 | $2,946.64 | $33,000 |
| 0160 | Edge key | LF A | 20.90 | $67.00 | $80.00 | $67.50 | $69.01 | $70.53 | $67.00 |
| 0170 | Maintain & control traffic | LS A | 1 | $7,500.00 | $5,000.00 | $15,000 | $14,978 | $48,250 | $12,000 |
| 0180 | Portable changeable message sign | EACH A | 2 | $8,000.00 | $750.00 | $1,000.00 | $764.26 | $948.66 | $1,000.00 |
| 0190 | Staking | LS A | 1 | $4,000.00 | $5,000.00 | $2,500.00 | $3,375.00 | $2,700.00 | $2,100.00 |
| 0200 | Remove structure | LS A | 1 | $5,000.00 | $5,000.00 | $5,000.00 | $8,151.30 | $3,000.00 | $37,500 |
| 0210 | Sodding | SQYD A | 40 | $45.00 | $25.00 | $35.00 | $67.50 | $37.69 | $152.92 |
| 0215 | Cyclopean stone rip rap | TON A | 82 | $68.00 | $75.00 | $55.00 | $112.48 | $90.70 | $92.00 |
| 0220 | Erosion control | LS A | 1 | $10,000 | $975.00 | $1,500.00 | $7,290.00 | $3,166.49 | $4,000.00 |
| 0230 | Aluminum structural plate box culvert | LF A | 40.50 | $1,987.65 | $3,000.00 | $3,250.00 | $2,972.70 | $3,100.00 | $3,360.00 |
| 0240 | Demobilization | LS A | 1 | $20,000 | $3,525.00 | $6,000.00 | $3,862.82 | $3,975.00 | $4,826.44 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of January 23, 2025. Compiled by Mirage Metrics.