MoDOT contract 251114-H06 bid tabulation
JSE0057-ROUTE 34-BOLLINGER, CAPE GIRARDEAU COUNTY. Let by Missouri DOT on November 14, 2025, Bollinger, Southeast. 5 bids received; low bid $3,519,000 by Pace Construction Company, LLC.
- Owner
- Missouri DOT
- Letting
- 14 NOV 2025
- Pay items
- 41
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Pace Construction Company, LLC | $3,519,000 | Low |
| 2 | Emery Sapp & Sons, Inc. | $4,120,943 | +17% |
| 3 | Apex Paving Co. | $4,131,642 | +17% |
| 4 | Magruder Paving, LLC | $4,483,016 | +27% |
| 5 | Above And Below Contracting, LLC | $5,075,980 | +44% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Pace Construction Company, LLC | 2. Emery Sapp & Sons, Inc. | 3. Apex Paving Co. | 4. Magruder Paving, LLC | 5. Above And Below Contracting, LLC |
|---|---|---|---|---|---|---|---|---|
| 0010 | Removal of improvements (2022010) | LS | 1 | $14,626 | $13,600 | $12,640 | $12,640 | $21,351 |
| 0020 | Misc.shaping slopes class III - modified material requirement (2159910) | 100F | 22 | $1,400.00 | $1,506.00 | $1,400.00 | $1,400.00 | $1,767.63 |
| 0030 | Misc.permanent aggregate edge treatment (3049910) | TON | 3,359.30 | $31.65 | $37.15 | $36.45 | $47.23 | $55.20 |
| 0040 | Gravel (A) or crushed stone (B) (3105002) | TON | 250 | $16.00 | $38.50 | $36.45 | $47.23 | $59.23 |
| 0050 | Bituminous pavement mixture PG64-22, (BP-1) (4011209) | TON | 39,301.40 | $64.00 | $75.90 | $80.55 | $79.81 | $93.77 |
| 0060 | Tack coat (4071005) | GAL | 26,037 | $2.40 | $2.60 | $2.30 | $3.26 | $3.30 |
| 0070 | Emulsified asphalt, seal coat (4091048) | GAL | 1,516 | $3.00 | $3.25 | $3.00 | $3.00 | $3.60 |
| 0080 | Seal coat aggregate, grade A1 (4094001) | SY | 3,989 | $5.00 | $5.40 | $0.53 | $5.00 | $6.00 |
| 0090 | Impact attenuator 55 MPH (sand barrel array) (6122012) | EACH | 4 | $3,750.00 | $4,033.00 | $3,750.00 | $5,950.00 | $4,500.00 |
| 0100 | Replacement sand barrel (6122020) | EACH | 4 | $350.00 | $376.00 | $350.00 | $310.00 | $420.00 |
| 0110 | Impact attenuator (relocation) (6122030) | EACH | 8 | $1,500.00 | $1,613.00 | $1,500.00 | $1,950.00 | $1,800.00 |
| 0120 | Construction signs (6161005) | SF | 2,001 | $6.50 | $7.00 | $6.50 | $6.00 | $7.80 |
| 0130 | Channelizer (trim-line) (6161025) | EACH | 150 | $10.00 | $10.80 | $10.00 | $22.00 | $12.00 |
| 0140 | Changeable message sign without communication interface, contractor furnished retained (6161098A) | EACH | 4 | $3,500.00 | $3,764.00 | $3,500.00 | $3,000.00 | $4,200.00 |
| 0150 | Work zone traffic signal system (6162000A) | EACH | 1 | $5,000.00 | $5,500.00 | $15,000 | $14,400 | $6,000.00 |
| 0160 | Mobilization (6181000) | LS | 1 | $213,000 | $236,000 | $171,000 | $215,975 | $303,714 |
| 0170 | Preformed thermoplastic pavement marking, 24 in. yellow (6200018) | LF | 128 | $20.00 | $27.00 | $20.00 | $20.00 | $30.00 |
| 0180 | Preformed thermoplastic pavement marking, left/right arrow (6200021) | EACH | 10 | $300.00 | $350.00 | $300.00 | $300.00 | $390.00 |
| 0190 | Temporary removable marking tape 4 in., white (6205301B) | LF | 2,058 | $1.50 | $1.61 | $1.50 | $2.00 | $1.80 |
| 0200 | Temporary removable marking tape 4 in., yellow (6205303B) | LF | 4,000 | $1.50 | $1.61 | $1.50 | $2.00 | $1.80 |
| 0210 | Temporary removable marking tape, 24 in., white (6205309) | LF | 44 | $4.00 | $4.30 | $4.00 | $10.00 | $4.80 |
| 0220 | 4 in. yellow class 2 pavement marking paint (25-mil, type L beads) (6205901B) | LF | 116,470 | $0.15 | $0.20 | $0.15 | $0.15 | $0.23 |
| 0230 | 6 in. white class 2 pavement marking paint (25-mil, type L beads) (6205902B) | LF | 159,168 | $0.14 | $0.31 | $0.14 | $0.14 | $0.35 |
| 0240 | Pavement marking removal (6207001) | LF | 6,102 | $1.25 | $0.90 | $1.25 | $1.50 | $1.50 |
| 0250 | Coldmilling bituminous pavement for removal of surfacing (3 in. thick or less) (6221001) | SY | 22,681 | $3.25 | $2.70 | $1.86 | $9.42 | $2.73 |
| 0260 | Modified coldmilling (depth transitions) (6224010) | SY | 19,064 | $2.35 | $4.70 | $5.22 | $7.23 | $9.60 |
| 0270 | Bituminous shoulder rumble strip (6261000A) | STA | 1,406.90 | $25.00 | $15.50 | $12.25 | $25.65 | $7.36 |
| 0280 | Bituminous centerline rumble strip (6261001) | STA | 754.20 | $25.00 | $18.60 | $12.25 | $25.31 | $10.15 |
| 0290 | MGS guardrail (6061060) | LF | 750 | $28.00 | $30.00 | $28.00 | $28.00 | $44.57 |
| 0300 | MGS bridge approach transition section (regular/no curb) (6061069) | EACH | 12 | $4,000.00 | $4,300.00 | $4,000.00 | $4,000.00 | $5,497.60 |
| 0310 | Type A crashworthy end terminal (MASH) (6063014) | EACH | 12 | $3,800.00 | $4,086.00 | $3,800.00 | $3,800.00 | $5,001.82 |
| 0320 | Misc.end post modification (7039902) | EACH | 4 | $5,150.00 | $6,237.00 | $5,150.00 | $5,150.00 | $1,200.00 |
| 0330 | Cleaning and epoxy coating (7040113) | SF | 2,240 | $9.00 | $9.50 | $8.89 | $8.89 | $10.67 |
| 0340 | Protective coating - concrete bents and piers (epoxy) (7110200) | LS | 1 | $6,024.82 | $6,479.00 | $6,024.82 | $6,024.82 | $7,229.79 |
| 0350 | Surface preparation for applying epoxy-mastic primer (7125102) | LS | 1 | $3,299.31 | $3,548.00 | $3,299.31 | $3,299.31 | $3,959.18 |
| 0360 | Aluminum epoxy-mastic primer (7125960) | LS | 1 | $2,199.54 | $2,365.00 | $2,199.54 | $2,199.54 | $2,639.45 |
| 0370 | Misc.end post modification (7039902) | EACH | 4 | $5,150.00 | $6,237.00 | $5,150.00 | $5,150.00 | $1,200.00 |
| 0380 | Protective coating - concrete bents and piers (epoxy) (7110200) | LS | 1 | $22,378 | $24,065 | $22,378 | $22,378 | $26,853 |
| 0390 | Misc.end post modification (7039902) | EACH | 4 | $5,150.00 | $6,237.00 | $5,150.00 | $5,150.00 | $1,200.00 |
| 0400 | Cleaning and epoxy coating (7040113) | SF | 3,384 | $3.70 | $4.00 | $3.70 | $3.70 | $4.44 |
| 0410 | Protective coating - concrete bents and piers (epoxy) (7110200) | LS | 1 | $8,346.43 | $8,975.00 | $8,346.43 | $8,346.43 | $10,016 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of November 14, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.