MoDOT contract 260220-G04 bid tabulation
JSR0366 - ROUTE Y - WEBESTER COUNTY. Let by Missouri DOT on February 20, 2026, Webster, Southwest. 3 bids received; low bid $2,336,408 by Hartman and Company, Inc..
- Owner
- Missouri DOT
- Letting
- 20 FEB 2026
- Pay items
- 59
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Hartman and Company, Inc. | $2,336,408 | Low |
| 2 | Robertson Contractors, Inc. | $3,219,211 | +38% |
| 3 | Louis-Company, LLC | $3,943,824 | +69% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Hartman and Company, Inc. | 2. Robertson Contractors, Inc. | 3. Louis-Company, LLC |
|---|---|---|---|---|---|---|
| 0010 | Clearing and grubbing (2013000) | ACRE | 1 | $14,100 | $6,500.00 | $30,000 |
| 0020 | Removal of improvements (2022010) | LS | 1 | $15,000 | $18,500 | $198,365 |
| 0030 | Unclassified excavation (2035000) | CY | 5,135 | $3.90 | $28.00 | $28.26 |
| 0040 | Compacting embankment (2036000) | CY | 3,496 | $15.30 | $6.85 | $20.00 |
| 0050 | Compacting in cut (2037075) | STA | 4 | $940.50 | $850.00 | $1,153.59 |
| 0060 | Type 1 aggregate for base (6 in. thick) (3040163) | SY | 2,052 | $12.80 | $22.00 | $20.00 |
| 0070 | Gravel (A) (3101002) | TON | 13 | $128.00 | $55.00 | $19.48 |
| 0080 | Concrete pavement (8 in. non-reinforced, 15 FT. joints) (5021308) | SY | 2,051.50 | $70.00 | $120.00 | $178.00 |
| 0090 | Rock lining (6097000) | CY | 39 | $125.00 | $125.00 | $110.81 |
| 0100 | Furnishing type 2 rock blanket (6113020) | CY | 1,578 | $61.70 | $50.53 | $75.27 |
| 0110 | Placing type 2 rock blanket (6113040) | CY | 1,578 | $10.90 | $29.00 | $21.52 |
| 0120 | Misc.articulated concrete block (acb) system (6119905) | SY | 4,240 | $124.50 | $215.00 | $200.00 |
| 0130 | Construction signs (6161005) | SF | 602 | $10.80 | $8.00 | $10.25 |
| 0140 | Type 3 moveable barricade (6161030) | EACH | 10 | $225.00 | $185.00 | $237.00 |
| 0150 | Changeable message sign with communication interface, contractor furnished retained (6161099) | EACH | 3 | $5,700.00 | $4,500.00 | $5,764.77 |
| 0160 | Temporary traffic barrier, contractor furnished retained (6173600D) | LF | 50 | $100.00 | $48.60 | $185.75 |
| 0170 | Mobilization (6181000) | LS | 1 | $42,920 | $280,000 | $325,687 |
| 0180 | 4 in. white class 1 pavement marking paint (18-mil, type P beads) (6206000D) | LF | 2,100 | $0.55 | $0.90 | $1.15 |
| 0190 | 4 in. yellow class 1 pavement marking paint (18-mil, type P beads) (6206001D) | LF | 2,100 | $0.55 | $0.90 | $1.15 |
| 0200 | Permanent erosion control geotextile (6240103A) | SY | 2,796 | $4.60 | $3.35 | $3.20 |
| 0210 | Contractor furnished surveying and staking (6274000) | LS | 1 | $12,800 | $20,000 | $42,000 |
| 0220 | Misc.24" X 38" reinforced concrete elliptical culvert, group A (7309903) | LF | 72 | $207.50 | $135.00 | $163.77 |
| 0230 | 30 in. or allowed substitute group A flared end section (7320630A) | EACH | 1 | $1,830.00 | $1,350.00 | $5,637.67 |
| 0240 | Misc.24" X 38" or allowed substitute group A flared end section (7329902) | EACH | 4 | $2,540.00 | $1,600.00 | $2,741.85 |
| 0250 | Misc.seeding and mulching - cool season grasses (8059901) | LS | 1 | $3,850.00 | $1,750.00 | $4,932.08 |
| 0260 | Rock ditch check (8061005) | LF | 110 | $12.00 | $18.50 | $15.37 |
| 0270 | Alternate ditch check (8061006) | LF | 90 | $4.00 | $13.00 | $5.12 |
| 0280 | Sediment removal (8061016) | CY | 32 | $243.50 | $0.01 | $98.89 |
| 0290 | Silt fence (8061019) | LF | 1,160 | $3.00 | $3.30 | $3.84 |
| 0300 | Type C berm (8061050) | LF | 545 | $17.90 | $18.00 | $41.99 |
| 0310 | MGS bridge approach transition section (regular/no curb) (6061069) | EACH | 4 | $4,610.00 | $5,320.00 | $4,759.67 |
| 0320 | Type A crashworthy end terminal (MASH) (6063014) | EACH | 4 | $2,990.00 | $3,700.00 | $4,230.89 |
| 0330 | Breakaway assembly (perforated square steel tube) (9031241) | EACH | 16 | $250.00 | $250.00 | $448.37 |
| 0340 | 2.25 in. PSST post insert (6 FT.) - 12 GA. (9031272A) | EACH | 16 | $46.40 | $135.15 | $128.11 |
| 0350 | 2.5 in. PSST post - 12 GA. (9031280) | LF | 256 | $12.00 | $12.00 | $32.03 |
| 0360 | Concrete post anchor for 2.5 in. PSST. - 7 GA. (9031285) | EACH | 16 | $390.00 | $390.00 | $384.32 |
| 0370 | SH-flat sheet (9035004A) | SF | 9 | $19.70 | $19.70 | $25.62 |
| 0380 | SHF-flat sheet fluorescent (9035069A) | SF | 336 | $22.40 | $22.40 | $25.62 |
| 0390 | Class 1 excavation (2061000) | CY | 10 | $155.00 | $115.00 | $500.00 |
| 0400 | Class 2 excavation (2062000) | CY | 54 | $143.50 | $65.00 | $46.14 |
| 0410 | Cofferdams-BENT2 (2066002) | LS | 1 | $40,400 | $40,000 | $110,000 |
| 0420 | Cofferdams-BENT3 (2066003) | LS | 1 | $35,900 | $40,000 | $110,000 |
| 0430 | Bridge approach slab (minor road) (5031011A) | SY | 110 | $325.00 | $450.00 | $539.93 |
| 0440 | Rock sockets (4 FT 6 in. dia.) (7011207) | LF | 56 | $1,170.00 | $1,850.00 | $2,300.00 |
| 0450 | Video camera inspection (7011300) | EACH | 4 | $300.00 | $800.00 | $64.05 |
| 0460 | Foundation inspection holes (7011400) | LF | 96 | $129.00 | $250.00 | $450.00 |
| 0470 | Sonic logging testing (7011600) | EACH | 4 | $850.00 | $1,350.00 | $1,665.38 |
| 0480 | Galvanized structural steel piles (12 in) (7021212) | LF | 188 | $172.50 | $200.00 | $306.00 |
| 0490 | Pre-bore for piling (7026000) | LF | 172 | $130.00 | $250.00 | $179.81 |
| 0500 | Pile point reinforcement (7027000) | EACH | 8 | $131.00 | $300.00 | $192.16 |
| 0510 | Class B concrete (substructure) (7032003) | CY | 101.50 | $1,610.00 | $1,585.00 | $2,400.00 |
| 0520 | Type D barrier (7034219A) | LF | 389 | $172.00 | $158.00 | $182.88 |
| 0530 | Slab on concrete beam (7034222) | SY | 526 | $679.50 | $615.00 | $600.00 |
| 0540 | 33 in., prestressed concrete spread box beam (7056051A) | LF | 523 | $498.00 | $530.00 | $580.00 |
| 0550 | Reinforcing steel (bridges) (7061060) | LB | 25,550 | $2.80 | $2.45 | $0.96 |
| 0560 | Steel intermediate diaphragm for P/S concrete girders (7123301) | EACH | 6 | $1,470.00 | $1,450.00 | $1,415.91 |
| 0570 | Vertical drain at end bents (7151001) | EACH | 2 | $3,500.00 | $2,150.00 | $3,972.55 |
| 0580 | Plain neoprene bearing pad (7161000) | EACH | 6 | $574.00 | $305.00 | $161.42 |
| 0590 | Laminated neoprene bearing pad (7161002) | EACH | 12 | $425.00 | $350.00 | $161.41 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of February 20, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.