MoDOT contract 260417-C06 bid tabulation
JKU0125 - ROUTE 291 - CLAY COUNTY. Let by Missouri DOT on April 17, 2026, Clay, Kansas City. 3 bids received; low bid $1,997,220 by Comanche Construction, Inc..
- Owner
- Missouri DOT
- Letting
- 17 APR 2026
- Pay items
- 57
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Comanche Construction, Inc. | $1,997,220 | Low |
| 2 | Clarkson Construction Company | $2,648,941 | +33% |
| 3 | Louis-Company, LLC | $2,654,532 | +33% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Comanche Construction, Inc. | 2. Clarkson Construction Company | 3. Louis-Company, LLC |
|---|---|---|---|---|---|---|
| 0010 | Removal of improvements (2022010) | LS | 1 | $138,238 | $400,000 | $33,081 |
| 0020 | Linear grading class 1 (2071000) | STA | 17.80 | $2,057.63 | $2,899.01 | $1,622.32 |
| 0030 | Shaping slopes, class III (2153000) | 100F | 2 | $1,552.13 | $1,508.65 | $1,896.30 |
| 0040 | Type 5 aggregate for base (6 in. thick) (3040506) | SY | 1,361 | $26.23 | $43.73 | $23.52 |
| 0050 | Misc.optional pavement (4019905) | SY | 1,361 | $89.08 | $85.00 | $106.84 |
| 0060 | Concrete approach pavement (5041000) | SY | 191.60 | $267.49 | $241.01 | $272.76 |
| 0070 | Furnishing type 1 rock ditch liner (6096010A) | CY | 10 | $82.31 | $110.97 | $108.10 |
| 0080 | Placing type 1 rock ditch liner (6096041) | CY | 10 | $128.60 | $121.46 | $120.54 |
| 0090 | Furnishing type 2 rock blanket (6113020) | CY | 662 | $77.16 | $87.72 | $81.17 |
| 0100 | Placing type 2 rock blanket (6113040) | CY | 662 | $51.44 | $45.49 | $29.13 |
| 0110 | Impact attenuator 55 MPH (sand barrel array) (6122012) | EACH | 1 | $1,949.61 | $1,895.00 | $4,807.83 |
| 0120 | Replacement sand barrel (6122020) | EACH | 4 | $334.37 | $325.00 | $345.66 |
| 0130 | Impact attenuator (relocation) (6122030) | EACH | 1 | $1,949.61 | $1,895.00 | $1,432.92 |
| 0140 | Construction signs (6161005) | SF | 308 | $6.17 | $6.00 | $8.80 |
| 0150 | Channelizer (trim-line) (6161025) | EACH | 68 | $15.43 | $15.00 | $37.71 |
| 0160 | Type 3 moveable barricade (6161030) | EACH | 3 | $138.89 | $135.00 | $314.24 |
| 0170 | Flashing arrow panel (6161040) | EACH | 1 | $1,491.79 | $1,450.00 | $1,885.42 |
| 0180 | Changeable message sign without communication interface, contractor furnished retained (6161098A) | EACH | 2 | $2,520.61 | $2,450.00 | $5,970.51 |
| 0190 | Temporary long-term rumble strips (6162002) | EACH | 12 | $1,337.46 | $1,300.00 | $2,011.12 |
| 0200 | Temporary traffic barrier anchored, contractor furnished retained (6173700B) | LF | 994 | $41.28 | $35.86 | $62.60 |
| 0210 | Relocating temporary traffic barrier (6175010A) | LF | 994 | $5.14 | $27.93 | $17.09 |
| 0220 | Mobilization (6181000) | LS | 1 | $129,000 | $253,000 | $107,015 |
| 0230 | Railroad plan submittal (6181015) | LS | 1 | $177,283 | $150,000 | $351,946 |
| 0240 | Additional mobilization for seeding (6181020) | EACH | 4 | $600.00 | $600.00 | $600.00 |
| 0250 | Temporary removable marking tape 4 in., white (6205301B) | LF | 4,063 | $1.99 | $1.93 | $2.01 |
| 0260 | Temporary removable marking tape 4 in., yellow (6205303B) | LF | 3,248 | $1.99 | $1.93 | $2.01 |
| 0270 | Temporary non-removable marking tape left/right arrow (6205440A) | EACH | 2 | $97.74 | $95.00 | $150.84 |
| 0280 | 6 in. white class 2 pavement marking paint (25-mil, type L beads) (6205902B) | LF | 1,446 | $0.36 | $0.35 | $1.76 |
| 0290 | 6 in. yellow class 2 pavement marking paint (25-mil, type L beads) (6205903B) | LF | 1,156 | $0.36 | $0.35 | $1.76 |
| 0300 | Pavement marking removal (6207001) | LF | 7,311 | $0.56 | $0.54 | $0.63 |
| 0310 | Pavement marking removal (symbols) (6207002) | EACH | 2 | $91.57 | $89.00 | $56.57 |
| 0320 | Permanent erosion control geotextile (6240103A) | SY | 875 | $4.94 | $3.63 | $3.77 |
| 0330 | Misc.optional rumble strips (6269909) | STA | 17.80 | $231.48 | $758.43 | $251.39 |
| 0340 | Contractor furnished surveying and staking (6274000) | LS | 1 | $8,230.54 | $22,000 | $3,770.85 |
| 0350 | Mulching (8025006) | ACRE | 0.10 | $10,288 | $12,000 | $15,084 |
| 0360 | Seeding - cool season grasses (8051000A) | ACRE | 0.10 | $10,288 | $18,000 | $22,625 |
| 0370 | Alternate ditch check (8061006) | LF | 823 | $16.36 | $7.15 | $8.99 |
| 0380 | Sediment removal (8061016) | CY | 36 | $59.36 | $90.73 | $32.81 |
| 0390 | Silt fence (8061019) | LF | 1,250 | $3.94 | $2.10 | $2.64 |
| 0400 | MGS guardrail, 8 FT. posts, 6 FT. - 3 in. spacing (6061061) | LF | 538 | $32.41 | $31.50 | $39.59 |
| 0410 | MGS bridge approach transition section (regular/no curb) (6061069) | EACH | 2 | $4,218.88 | $4,100.70 | $5,154.37 |
| 0420 | Type A crashworthy end terminal (6063015) | EACH | 2 | $3,514.67 | $3,416.22 | $4,294.02 |
| 0430 | Removal of miscellaneous acm (non-friable) (2024043) | SF | 16 | $116.01 | $400.00 | $439.93 |
| 0440 | Class 1 excavation (2061000) | CY | 90 | $164.85 | $166.48 | $20.09 |
| 0450 | Temporary shoring (2065500) | LS | 1 | $38,507 | $90,000 | $34,382 |
| 0460 | Removal of existing bridge deck (2162500) | SF | 6,690 | $28.64 | $60.60 | $35.00 |
| 0470 | Bridge approach slab (major) (5031010A) | SY | 171 | $527.70 | $583.17 | $573.24 |
| 0480 | Slab on steel (7034212) | SY | 739 | $727.68 | $663.72 | $521.11 |
| 0490 | Type D barrier (7034219A) | LF | 364 | $161.88 | $222.87 | $2,063.27 |
| 0500 | Protective coating - concrete bents and piers (epoxy) (7110200) | LS | 1 | $8,873.95 | $7,100.00 | $9,643.94 |
| 0510 | Strengthening existing beams (7121250) | LS | 1 | $51,253 | $31,096 | $25,368 |
| 0520 | Slab drain (7123610) | EACH | 20 | $441.56 | $1,251.79 | $447.31 |
| 0530 | Surface preparation for applying epoxy-mastic primer (7125102) | LS | 1 | $8,763.01 | $5,980.00 | $9,523.40 |
| 0540 | Gray epoxy-mastic primer (7125961) | LS | 1 | $5,842.02 | $5,980.00 | $6,348.93 |
| 0550 | Non-destructive testing (7126000) | LF | 51 | $106.14 | $55.00 | $69.13 |
| 0560 | Misc.girder chair repair (7129902) | EACH | 10 | $1,143.81 | $642.58 | $785.59 |
| 0570 | Vertical drain at end bents (7151001) | EACH | 2 | $5,780.22 | $2,993.29 | $8,494.32 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of April 17, 2026. Compiled by Mirage Metrics.