MoDOT contract 261016-G11 bid tabulation
JSU0080 - ROUTE 266 - GREENE COUNTY. Let by Missouri DOT on October 16, 2026, Greene, Southwest. 7 bids received; low bid $3,370,375 by Radmacher Brothers Excavating Co., Inc..
- Owner
- Missouri DOT
- Letting
- 16 OCT 2026
- Pay items
- 78
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Radmacher Brothers Excavating Co., Inc. | $3,370,375 | Low |
| 2 | Emery Sapp & Sons, Inc. | $3,423,547 | +2.0% |
| 3 | Hartman and Company, Inc. | $3,475,000 | +3.0% |
| 4 | KCI Construction Company | $3,633,203 | +8.0% |
| 5 | APAC-Central, Inc. | $3,935,583 | +17% |
| 6 | Hamilton and Dad, Inc. | $4,322,066 | +28% |
| 7 | D & E Plumbing and Heating, Inc. | $5,426,967 | +61% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Radmacher Brothers Excavating Co., Inc. | 2. Emery Sapp & Sons, Inc. | 3. Hartman and Company, Inc. | 4. KCI Construction Company | 5. APAC-Central, Inc. | 6. Hamilton and Dad, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Clearing and grubbing (2013000) | ACRE | 1 | $6,540.00 | $20,405 | $9,600.00 | $4,800.00 | $37,900 | $3,055.00 |
| 0020 | Removal of improvements (2022010) | LS | 1 | $62,350 | $18,888 | $74,700 | $13,000 | $70,100 | $22,505 |
| 0030 | Unclassified excavation (2035000) | CY | 7,511 | $16.30 | $19.24 | $10.80 | $21.00 | $24.21 | $24.80 |
| 0040 | Embankment in place (2035500) | CY | 5,296 | $6.65 | $12.46 | $15.50 | $11.00 | $30.65 | $14.50 |
| 0050 | Compacting embankment (2036000) | CY | 4,511 | $3.35 | $3.62 | $9.30 | $5.50 | $6.35 | $17.70 |
| 0060 | Class 3 excavation (2063000) | CY | 325 | $11.30 | $7.90 | $31.80 | $20.00 | $33.10 | $35.65 |
| 0070 | Class 4 excavation (2063300) | CY | 75 | $38.75 | $15.80 | $77.00 | $69.00 | $57.40 | $45.80 |
| 0080 | Linear grading class 1 (2071000) | STA | 5.90 | $3,500.00 | $1,472.52 | $2,590.00 | $2,100.00 | $1,608.75 | $600.00 |
| 0090 | Type 5 aggregate for base (4 in. thick) (3040504) | SY | 1,777 | $10.30 | $8.83 | $15.60 | $11.00 | $12.70 | $5.60 |
| 0100 | Type 5 aggregate for base (6 in. thick) (3040506) | SY | 22,458 | $10.15 | $8.14 | $6.40 | $10.00 | $12.45 | $7.70 |
| 0105 | Gravel (A) or crushed stone (B) (3105003) | SY | 71 | $16.20 | $13.25 | $37.60 | $22.00 | $75.00 | $11.60 |
| 0140 | Concrete pavement (9 in. non-reinforced 15 FT. joints) (5021309) | SY | 17,568.90 | $72.50 | $83.51 | $81.80 | $82.00 | $86.05 | $104.40 |
| 0150 | Misc.8 in. truck apron (pigmented & textured) (5029905) | SY | 3,227.80 | $87.50 | $94.35 | $113.00 | $96.00 | $97.20 | $159.90 |
| 0155 | Paved approach, 8 in. (6085008) | SY | 1,777.10 | $69.00 | $72.88 | $86.80 | $95.00 | $107.55 | $124.65 |
| 0160 | Misc.modified 8 in. concrete median strip (6089905) | SY | 1,661.20 | $65.50 | $108.74 | $64.70 | $56.00 | $92.70 | $122.15 |
| 0170 | Rock lining (6097000) | CY | 61 | $96.50 | $133.08 | $69.10 | $136.00 | $198.50 | $65.00 |
| 0180 | Truck mounted attenuator (TMA) (6123001) | LS | 1 | $2,790.00 | $1.10 | $6,000.00 | $750.00 | $1,500.00 | $6,897.00 |
| 0190 | Construction signs (6161005) | SF | 1,382 | $8.05 | $6.61 | $6.00 | $8.00 | $8.60 | $8.55 |
| 0200 | Channelizer (trim-line) (6161025) | EACH | 80 | $32.25 | $55.10 | $50.00 | $31.00 | $33.20 | $27.30 |
| 0210 | Type 3 moveable barricade (6161030) | EACH | 24 | $231.00 | $275.51 | $250.00 | $165.00 | $176.70 | $176.50 |
| 0220 | Changeable message sign with communication interface, contractor furnished retained (6161099) | EACH | 6 | $7,840.00 | $5,190.60 | $4,710.00 | $5,200.00 | $5,567.70 | $5,561.00 |
| 0230 | Mobilization (6181000) | LS | 1 | $311,624 | $87,125 | $150,870 | $398,500 | $115,035 | $120,789 |
| 0240 | Additional mobilization for seeding (6181020) | EACH | 4 | $600.00 | $600.00 | $600.00 | $600.00 | $600.00 | $600.00 |
| 0250 | Preformed thermoplastic pavement marking, 24 in. white (6200015) | LF | 214 | $19.30 | $16.53 | $15.00 | $21.00 | $22.50 | $22.45 |
| 0260 | Preformed thermoplastic pavement marking, 24 in. yellow (6200018) | LF | 230 | $19.30 | $16.53 | $15.00 | $21.00 | $22.50 | $22.45 |
| 0270 | Preformed thermoplastic pavement marking, 24 in. X 36 in., yield line triangle (6200042A) | EACH | 42 | $35.50 | $110.20 | $100.00 | $65.00 | $69.60 | $69.50 |
| 0280 | 4 in. white class 1 pavement marking paint (18-mil, type P beads) (6206000D) | LF | 9,343 | $0.60 | $0.28 | $0.25 | $0.55 | $0.60 | $0.60 |
| 0290 | 4 in. yellow class 1 pavement marking paint (18-mil, type P beads) (6206001D) | LF | 18,141 | $0.55 | $0.28 | $0.25 | $0.55 | $0.60 | $0.60 |
| 0300 | 8 in. white class 1 pavement marking paint (18-mil, type P beads) (6206108B) | LF | 70 | $5.90 | $0.55 | $0.50 | $1.10 | $1.20 | $1.15 |
| 0310 | Separation geotextile (6240104A) | SY | 320 | $3.80 | $1.01 | $12.20 | $2.50 | $4.30 | $3.75 |
| 0320 | Contractor furnished surveying and staking (6274000) | LS | 1 | $49,800 | $60,345 | $41,500 | $16,000 | $53,000 | $72,442 |
| 0330 | Class B-1 concrete (culverts) (7034041) | CY | 36 | $1,490.00 | $1,422.08 | $1,580.00 | $950.00 | $1,909.20 | $1,128.30 |
| 0340 | Reinforcing steel (culverts) (7061030) | LB | 5,580 | $0.65 | $2.10 | $2.70 | $1.50 | $3.80 | $6.70 |
| 0350 | 15 in. pipe group C (7250415) | LF | 263 | $75.50 | $41.54 | $72.70 | $76.00 | $59.55 | $66.50 |
| 0360 | 18 in. pipe group C (7250418) | LF | 137 | $81.00 | $53.34 | $67.20 | $84.00 | $81.25 | $76.80 |
| 0370 | 24 in. pipe group C (7250424) | LF | 132 | $91.00 | $82.51 | $82.60 | $108.00 | $88.60 | $97.30 |
| 0380 | 18 in. pipe group A (7261018) | LF | 70 | $79.00 | $80.10 | $101.50 | $105.00 | $90.20 | $85.50 |
| 0390 | 30 in. pipe group A (7261030) | LF | 41 | $125.00 | $117.67 | $238.00 | $165.00 | $136.25 | $136.50 |
| 0400 | 36 in. pipe group A (7261036) | LF | 107 | $175.00 | $182.27 | $167.50 | $185.00 | $142.35 | $167.70 |
| 0410 | 18 in. or allowed substitute group A flared end section (7320618A) | EACH | 2 | $676.00 | $1,201.13 | $1,420.00 | $1,750.00 | $819.45 | $1,000.00 |
| 0420 | 30 in. or allowed substitute group A flared end section (7320630A) | EACH | 2 | $1,320.00 | $2,141.39 | $2,090.00 | $2,100.00 | $1,711.25 | $1,519.00 |
| 0430 | 36 in. or allowed substitute group A flared end section (7320636A) | EACH | 2 | $1,960.00 | $2,433.13 | $2,740.00 | $2,500.00 | $2,125.50 | $2,104.00 |
| 0440 | 15 in. or allowed substitute group C flared end section (7320815A) | EACH | 14 | $481.00 | $1,318.58 | $616.50 | $1,300.00 | $592.60 | $667.00 |
| 0450 | 18 in. or allowed substitute group C flared end section (7320818A) | EACH | 4 | $528.00 | $1,201.13 | $844.50 | $1,800.00 | $625.50 | $894.00 |
| 0460 | 24 in. or allowed substitute group C flared end section (7320824A) | EACH | 4 | $640.00 | $1,882.93 | $960.50 | $2,100.00 | $944.25 | $965.00 |
| 0470 | Mulching (8025006) | ACRE | 3 | $1,680.00 | $2,093.87 | $1,600.00 | $2,107.18 | $1,837.25 | $5,031.00 |
| 0480 | Seeding - cool season grasses (8051000A) | ACRE | 3 | $3,050.00 | $2,093.87 | $2,900.00 | $2,405.44 | $3,330.00 | $3,912.00 |
| 0490 | Rock ditch check (8061005) | LF | 640 | $15.80 | $27.55 | $15.00 | $13.00 | $17.25 | $12.00 |
| 0500 | Sediment removal (8061016) | CY | 130 | $44.75 | $13.93 | $31.20 | $16.00 | $40.70 | $14.00 |
| 0510 | Silt fence (8061019) | LF | 6,621 | $2.10 | $3.31 | $2.00 | $3.45 | $2.65 | $2.90 |
| 0520 | Lighting pole, 30 FT. type at (9011030) | EACH | 23 | $4,070.00 | $2,600.81 | $4,350.00 | $2,360.00 | $4,611.00 | $4,652.00 |
| 0530 | Bracket arm, 6 FT. (9011106) | EACH | 2 | $688.00 | $645.79 | $735.00 | $586.00 | $779.10 | $786.00 |
| 0540 | Bracket arm, 8 FT. (9011108) | EACH | 2 | $711.00 | $663.42 | $760.00 | $602.00 | $805.60 | $812.00 |
| 0550 | Bracket arm, 10 FT. (9011110) | EACH | 4 | $1,080.00 | $1,052.45 | $1,150.00 | $955.00 | $1,219.00 | $1,229.00 |
| 0560 | Bracket arm, 12 FT. (9011112) | EACH | 4 | $1,110.00 | $1,077.80 | $1,190.00 | $978.00 | $1,256.10 | $1,267.00 |
| 0570 | Bracket arm, 15 FT. (9011115) | EACH | 11 | $1,170.00 | $1,124.07 | $1,250.00 | $1,020.00 | $1,325.00 | $1,336.00 |
| 0580 | Luminaire, LED-A (9011311) | EACH | 23 | $403.00 | $523.46 | $430.00 | $475.00 | $455.80 | $460.00 |
| 0590 | Base mounted control station 240 volt - 4 circuit (9012230) | EACH | 2 | $12,120 | $15,153 | $13,000 | $13,750 | $13,727 | $13,849 |
| 0600 | Conduit, 4 in. rigid, in trench (9013004) | LF | 74 | $26.75 | $27.55 | $28.50 | $25.00 | $30.25 | $30.50 |
| 0610 | Conduit, 4 in. rigid, pushed (9014004) | LF | 303 | $39.00 | $49.60 | $41.80 | $45.00 | $44.30 | $44.65 |
| 0620 | Trenching type I (9015010) | LF | 2,927 | $7.95 | $11.02 | $8.50 | $10.00 | $9.05 | $9.10 |
| 0630 | Pull box, concrete, standard (9016120) | EACH | 11 | $5,060.00 | $6,323.49 | $5,400.00 | $5,738.00 | $5,729.30 | $5,780.00 |
| 0640 | Cable, 2 AWG 1 conductor (9017002) | LF | 200 | $5.35 | $0.01 | $5.70 | $7.50 | $6.05 | $6.10 |
| 0650 | Cable, 8 AWG 1 conductor (9017008) | LF | 790 | $2.10 | $2.06 | $2.30 | $1.87 | $2.40 | $2.40 |
| 0660 | Cable, 10 AWG 1 conductor, pole and bracket (9017110) | LF | 1,950 | $1.60 | $1.10 | $1.70 | $1.00 | $1.80 | $1.80 |
| 0670 | Wire, 8 AWG, bare neutral (9017208) | LF | 400 | $2.10 | $2.06 | $2.30 | $1.87 | $2.40 | $2.40 |
| 0680 | Cable-conduit, 1 in., 2 conductors and 1 bare neutral, 8 AWG (9017407) | LF | 3,470 | $7.00 | $8.46 | $7.50 | $7.68 | $7.95 | $8.00 |
| 0690 | Pole foundation (30 FT. mounting height) (9018230) | EACH | 23 | $2,960.00 | $2,318.69 | $3,170.00 | $2,104.00 | $3,354.90 | $3,384.00 |
| 0700 | Power supply assembly, type 2, 240/120 volt service, lighting only (9018612) | EACH | 2 | $843.00 | $9,367.32 | $900.00 | $8,500.00 | $954.00 | $962.00 |
| 0710 | I-beam posts (9031210) | LB | 340 | $21.00 | $22.04 | $20.00 | $20.00 | $21.90 | $21.40 |
| 0720 | Breakaway assembly (perforated square steel tube) (9031241) | EACH | 16 | $105.00 | $110.20 | $100.00 | $100.00 | $109.30 | $107.00 |
| 0730 | 2 in. PSST post - 12 GA. (9031270A) | LF | 689 | $21.00 | $22.04 | $20.00 | $13.00 | $21.90 | $21.40 |
| 0740 | Concrete post anchor for 2 in. PSST. - 7 GA. (9031274) | EACH | 55 | $105.00 | $110.20 | $100.00 | $100.00 | $109.30 | $107.00 |
| 0750 | 2.5 in. PSST post - 12 GA. (9031280) | LF | 432 | $21.00 | $22.04 | $20.00 | $20.00 | $21.90 | $21.40 |
| 0760 | Concrete post anchor for 2.5 in. PSST. - 7 GA. (9031285) | EACH | 34 | $105.00 | $110.20 | $100.00 | $100.00 | $109.30 | $107.00 |
| 0770 | SH-flat sheet (9035004A) | SF | 598 | $21.00 | $22.04 | $20.00 | $20.00 | $21.90 | $21.40 |
| 0780 | ST-structural (9035011A) | SF | 135 | $21.00 | $22.04 | $20.00 | $20.00 | $21.90 | $21.40 |
| 0790 | SHF-flat sheet fluorescent (9035069A) | SF | 170 | $31.50 | $33.06 | $30.00 | $30.00 | $32.80 | $32.10 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of October 16, 2026. Compiled by Mirage Metrics.