NJDOT contract 25600 bid tabulation
2026 WORLD CUP ITS IMPROVEMENTS. Let by New Jersey DOT on April 15, 2025, Bergen, Essex, Hudson, Passaic, H4. 4 bids received; low bid $20,550,000 by Tiffany Electric, Inc..
- Owner
- New Jersey DOT
- Letting
- 15 APR 2025
- Pay items
- 125
- Data through
- 16 APR 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Tiffany Electric, Inc. | $20,550,000 | Low |
| 2 | Daidone Electric, Inc. | $27,878,000 | +36% |
| 3 | HBC Company, Inc. | $32,935,036 | +60% |
| 4 | PKF-Mark III, Inc. | $36,291,900 | +77% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Tiffany Electric, Inc. | 2. Daidone Electric, Inc. | 3. HBC Company, Inc. | 4. PKF-Mark III, Inc. |
|---|---|---|---|---|---|---|---|
| 0001 | Performance bond and payment bond (151006M) | DOL | 1 | $150,000 | $134,924 | $200,000 | $225,010 |
| 0002 | Pollution liability insurance (152015P) | DOL | 1 | $20,000 | $0.01 | $15,000 | $1,000.00 |
| 0003 | Progress schedule (153003P) | LS | 1 | $10,000 | $50,000 | $25,000 | $26,100 |
| 0004 | Progress schedule update (153005M) | U | 8 | $1,200.00 | $0.01 | $5,000.00 | $1,300.00 |
| 0005 | Trainees (153011M) | HR | 2,550 | $0.01 | $0.01 | $1.00 | $79.72 |
| 0006 | Mobilization (154003P) | LS | 1 | $2,294,884 | $2,800,519 | $3,000,000 | $3,629,100 |
| 0007 | Field office type F set UP (155018M) | U | 1 | $20,000 | $25,000 | $75,000 | $48,639 |
| 0008 | Field office type F maintenance (155036M) | MO | 18 | $4,500.00 | $3,000.00 | $5,500.00 | $7,118.00 |
| 0009 | Heavy duty silt fence, orange (158009M) | LF | 44 | $50.00 | $10.00 | $7.00 | $22.59 |
| 0010 | Heavy duty silt fence, black (158012M) | LF | 12,912 | $7.00 | $10.00 | $6.50 | $13.04 |
| 0011 | Inlet filter type 2, 4' X 4' (158033M) | U | 111 | $180.00 | $50.00 | $150.00 | $308.61 |
| 0012 | Oil-water separator (158069M) | U | 2 | $4,000.00 | $0.01 | $4,500.00 | $3,946.35 |
| 0013 | Oil only emergency spill kit, type 1 (158072M) | U | 4 | $1,500.00 | $0.01 | $2,000.00 | $1,313.70 |
| 0014 | Erosion control sediment removal (158084M) | CY | 50 | $60.00 | $0.01 | $120.00 | $10.00 |
| 0015 | Breakaway barricade (159003M) | U | 450 | $0.01 | $0.01 | $195.00 | $157.14 |
| 0016 | Drum (159006M) | U | 1,520 | $0.01 | $0.01 | $110.00 | $30.00 |
| 0017 | Traffic cone (159009M) | U | 1,520 | $15.00 | $0.01 | $30.00 | $13.00 |
| 0018 | Construction signs (159012M) | SF | 9,873 | $17.00 | $0.01 | $60.00 | $15.00 |
| 0019 | Construction barrier curb (159021P) | LF | 5,340 | $0.01 | $100.00 | $120.00 | $83.50 |
| 0020 | Arrow board, 4' X 8' (159027M) | U | 14 | $100.00 | $0.01 | $8,300.00 | $10,350 |
| 0021 | Portable variable message sign (159030M) | U | 24 | $100.00 | $2,500.00 | $18,500 | $7,045.00 |
| 0022 | Temporary crash cushion, inertial barrier system, 14 modules (159054M) | U | 4 | $4,340.00 | $5,600.00 | $25,000 | $12,000 |
| 0023 | Traffic control truck with mounted crash cushion (159108M) | U | 14 | $100.00 | $0.01 | $45,000 | $13,380 |
| 0024 | Traffic director, flagger (159141M) | HR | 200 | $120.00 | $117.00 | $185.00 | $181.13 |
| 0025 | Temporary crash cushion, compressive barrier, type 3, width narrow (159212M) | U | 17 | $100.00 | $10,000 | $12,900 | $18,400 |
| 0026 | Construction identification sign, iija 8' X 5' (159262M) | U | 24 | $1,500.00 | $2,500.00 | $8,500.00 | $800.00 |
| 0027 | Fuel price adjustment (160004M) | DOL | 1 | $600.00 | $600.00 | $600.00 | $600.00 |
| 0028 | Asphalt price adjustment (160007M) | DOL | 1 | $400.00 | $400.00 | $400.00 | $400.00 |
| 0029 | Steel price adjustment (160009M) | DOL | 1 | $219.09 | $219.09 | $219.09 | $219.09 |
| 0030 | Final cleanup (161003P) | LS | 1 | $90,000 | $0.01 | $15,000 | $10,245 |
| 0031 | Clearing site (201003P) | LS | 1 | $200,000 | $3,700.00 | $125,000 | $200,000 |
| 0032 | Excavation, test pit (202006M) | CY | 100 | $200.00 | $100.00 | $1,200.00 | $763.24 |
| 0033 | Excavation, unclassified (202009P) | CY | 113 | $0.01 | $421.00 | $250.00 | $333.47 |
| 0034 | Hot mix asphalt pavement repair (401021M) | SY | 200 | $75.00 | $100.00 | $95.00 | $537.91 |
| 0035 | Set inlet type B, casting (602105M) | U | 3 | $800.00 | $4,500.00 | $2,000.00 | $3,000.45 |
| 0036 | Reconstructed inlet, type B, using new casting (602153M) | U | 5 | $2,200.00 | $5,200.00 | $4,500.00 | $5,818.00 |
| 0037 | Concrete island, 4" thick (606075P) | SY | 9 | $200.00 | $900.00 | $620.00 | $1,087.33 |
| 0038 | Turf pavers (606095P) | SY | 2,071 | $300.00 | $525.00 | $450.00 | $651.92 |
| 0039 | Sawcut vertical curb (607120P) | LF | 3,916 | $74.00 | $97.00 | $65.00 | $38.70 |
| 0040 | Nonvegetative surface, porous hot mix asphalt, 4" thick (608004P) | SY | 3,559 | $65.00 | $176.00 | $125.00 | $80.00 |
| 0041 | Beam guide rail (609003M) | LF | 4,003 | $41.00 | $111.00 | $75.00 | $51.00 |
| 0042 | Beam guide rail, dual-faced (609006M) | LF | 13 | $86.00 | $84.00 | $85.00 | $75.00 |
| 0043 | Tangent guide rail terminal (609027M) | U | 14 | $5,175.00 | $11,300 | $4,500.00 | $3,900.00 |
| 0044 | Telescoping guide rail end terminal (609030M) | U | 1 | $8,000.00 | $16,200 | $15,000 | $4,500.00 |
| 0045 | Beam guide rail anchorage (609039M) | U | 18 | $1,725.00 | $4,900.00 | $2,500.00 | $1,150.00 |
| 0046 | Beam guide rail post (609042M) | U | 66 | $98.00 | $90.00 | $180.00 | $84.00 |
| 0047 | Reset beam guide rail with existing posts (609063M) | LF | 300 | $17.25 | $29.00 | $45.00 | $15.00 |
| 0048 | Removal of beam guide rail (609075M) | LF | 3,065 | $1.15 | $1.00 | $6.00 | $1.00 |
| 0049 | Crash cushion, compressive barrier, type 3, width wide (611318M) | U | 2 | $66,000 | $60,000 | $55,000 | $67,400 |
| 0050 | Fire hydrant (651246M) | U | 1 | $12,000 | $21,000 | $18,000 | $15,900 |
| 0051 | 2" rigid metallic conduit (701015P) | LF | 3,497 | $50.00 | $68.00 | $65.00 | $85.52 |
| 0052 | 2" rigid metallic conduit, PVC coated (701016P) | LF | 44 | $100.00 | $150.00 | $180.00 | $185.04 |
| 0053 | 3" rigid metallic conduit (701021P) | LF | 22,992 | $55.00 | $69.00 | $105.00 | $100.56 |
| 0054 | 2 - 3" flexible nonmetallic conduit (701084P) | LF | 2,213 | $60.00 | $260.00 | $202.00 | $185.28 |
| 0055 | 12" X 10" X 8" metal junction box (701108M) | U | 3 | $1,200.00 | $1,700.00 | $3,500.00 | $4,650.52 |
| 0056 | Junction box modifications (701118P) | LS | 1 | $10,000 | $11,600 | $2,500.00 | $5,987.86 |
| 0057 | Foundation, type STF (701138M) | U | 25 | $6,000.00 | $10,900 | $6,500.00 | $27,078 |
| 0058 | Modify meter cabinet (701187M) | U | 14 | $3,500.00 | $3,500.00 | $35,000 | $16,329 |
| 0059 | Ground wire, no. 6 AWG (701189P) | LF | 4,642 | $2.15 | $4.50 | $5.00 | $1.18 |
| 0060 | Ground wire, no. 4 AWG (701190P) | LF | 9,762 | $2.75 | $5.30 | $5.50 | $1.71 |
| 0061 | Ground wire, no. 8 AWG (701192P) | LF | 8,715 | $1.85 | $4.00 | $4.00 | $0.79 |
| 0062 | Ground wire, no. 10 AWG (701193P) | LF | 3,241 | $1.65 | $3.70 | $3.00 | $0.49 |
| 0063 | Multiple lighting wire, no. 2 AWG (701195P) | LF | 23,817 | $7.00 | $6.60 | $8.00 | $14.48 |
| 0064 | Multiple lighting wire, no. 4 AWG (701196P) | LF | 15,305 | $6.00 | $5.30 | $6.00 | $13.45 |
| 0065 | Multiple lighting wire, no. 6 AWG (701198P) | LF | 16,263 | $4.25 | $4.50 | $4.00 | $12.33 |
| 0066 | Service wire, no. 3/0 AWG (701208P) | LF | 324 | $11.00 | $26.50 | $16.00 | $31.67 |
| 0067 | Service wire, no. 2 AWG (701210P) | LF | 4,375 | $8.00 | $13.60 | $10.00 | $15.35 |
| 0068 | Multiple lighting wire, no. 1/0 AWG (701240P) | LF | 23,313 | $10.00 | $9.20 | $12.00 | $19.87 |
| 0069 | Multiple lighting wire, no. 3/0 AWG (701242P) | LF | 17,103 | $13.00 | $13.00 | $15.00 | $21.60 |
| 0070 | Ground wire, no. 1 AWG (701340P) | LF | 5,701 | $4.25 | $7.50 | $9.00 | $5.49 |
| 0071 | Arc flash studies DMS controller cabinets (701390M) | U | 1 | $6,000.00 | $2,000.00 | $5,000.00 | $10,065 |
| 0072 | Arc flash studies CSS controller cabinets (701390M) | U | 1 | $6,000.00 | $10,000 | $5,000.00 | $150,972 |
| 0073 | Traffic signal standard, aluminum (702012M) | U | 25 | $3,700.00 | $4,500.00 | $5,500.00 | $7,746.27 |
| 0074 | ITS conduit, type A (704002M) | LF | 6,324 | $45.00 | $88.00 | $131.00 | $106.23 |
| 0075 | Junction box ITS type A (704003M) | U | 62 | $3,000.00 | $7,100.00 | $7,100.00 | $7,091.25 |
| 0076 | Junction box ITS type C (704009M) | U | 273 | $1,500.00 | $3,800.00 | $2,200.00 | $4,158.58 |
| 0077 | Meter cabinet ITS (704011M) | U | 30 | $5,900.00 | $4,700.00 | $5,600.00 | $27,143 |
| 0078 | Foundation, ITS (704014M) | U | 26 | $2,500.00 | $4,600.00 | $1,900.00 | $6,202.90 |
| 0079 | Foundation ITS type C (704021M) | U | 49 | $4,000.00 | $6,700.00 | $3,200.00 | $10,753 |
| 0080 | Foundation ITS type C-MC (704022M) | U | 4 | $4,500.00 | $7,900.00 | $6,000.00 | $12,424 |
| 0081 | Communication hub modifications route 3 EB M.P. 6.30 (704029M) | U | 1 | $4,150.00 | $4,500.00 | $6,800.00 | $8,462.38 |
| 0082 | Communication hub modifications 16W toll plaza (704029M) | U | 1 | $4,150.00 | $4,500.00 | $6,800.00 | $6,558.25 |
| 0083 | Communication hub modifications route 3 WB M.P. 8.1 (704029M) | U | 1 | $26,800 | $28,900 | $35,000 | $33,770 |
| 0084 | Communication hub modifications field terminal S2D3FT1 (704029M) | U | 1 | $4,150.00 | $4,500.00 | $6,800.00 | $6,558.25 |
| 0085 | Controller modifications, type ___ camera (704032M) | U | 7 | $8,750.00 | $9,400.00 | $11,000 | $11,675 |
| 0086 | Controller modifications, type ___ DMS (704032M) | U | 2 | $4,450.00 | $4,800.00 | $6,200.00 | $6,879.64 |
| 0087 | Controller modifications, type ___ TTS (704032M) | U | 1 | $16,000 | $17,300 | $21,000 | $21,679 |
| 0088 | Control center system, location no. ___ communications integration (704033P) | LS | 1 | $40,000 | $143,000 | $440,000 | $150,710 |
| 0089 | Foundation CSS (704035M) | U | 29 | $41,500 | $53,000 | $45,000 | $33,811 |
| 0090 | Camera standard type A (704048M) | U | 29 | $69,000 | $100,000 | $109,000 | $84,835 |
| 0091 | Camera standard type B (704051M) | U | 1 | $37,000 | $90,000 | $80,000 | $74,389 |
| 0092 | Camera standard type C (704054M) | U | 1 | $59,000 | $80,000 | $55,000 | $49,945 |
| 0093 | Camera (704060M) | U | 94 | $4,800.00 | $28,000 | $38,000 | $51,807 |
| 0094 | Controller, camera (704063M) | U | 51 | $84,000 | $53,000 | $59,100 | $65,379 |
| 0095 | Fiber optic cable type E (704078P) | LF | 32,705 | $11.00 | $17.00 | $20.00 | $27.23 |
| 0096 | Foundation DMS type A (704147M) | U | 1 | $18,700 | $15,000 | $25,000 | $37,020 |
| 0097 | DMS standard ground mounted (704169M) | U | 1 | $32,000 | $18,000 | $31,000 | $37,371 |
| 0098 | DMS sign (704171M) | U | 2 | $97,000 | $123,000 | $175,000 | $129,663 |
| 0099 | Controller, DMS (704183M) | U | 2 | $65,000 | $66,000 | $71,000 | $34,134 |
| 0100 | ITS roadside unit, type ___ A (704237M) | U | 33 | $17,000 | $21,000 | $22,500 | $21,842 |
| 0101 | System detector, type ___ lidar (704300M) | U | 38 | $41,000 | $46,000 | $52,000 | $48,815 |
| 0102 | ITS systems burn-in period (704257M) | MO | 6 | $3,150.00 | $3,400.00 | $3,100.00 | $24,687 |
| 0103 | Low-voltage transformer (706004M) | U | 1 | $15,000 | $18,000 | $15,000 | $29,113 |
| 0104 | Standby engine generator (MMG153M) | U | 8 | $8,000.00 | $20,000 | $1,500.00 | $22,348 |
| 0105 | Selective clearing (801012M) | SY | 430 | $50.00 | $0.01 | $30.00 | $16.00 |
| 0106 | Topsoil spreading __" thick 4 (804000P) | SY | 691 | $10.00 | $41.00 | $15.00 | $62.00 |
| 0107 | Borrow topsoil (804015P) | CY | 59 | $100.00 | $100.00 | $125.00 | $120.00 |
| 0108 | Fertilizing and seeding, type A (806003P) | SY | 425 | $6.00 | $2.00 | $5.00 | $8.00 |
| 0109 | Fertilizing and seeding, type A-3 (806006P) | SY | 341 | $6.00 | $2.00 | $5.00 | $8.00 |
| 0110 | Fertilizing and seeding, type F (806018P) | SY | 70 | $6.00 | $2.00 | $5.00 | $8.00 |
| 0111 | Straw mulching (809003M) | SY | 761 | $6.00 | $2.00 | $5.00 | $8.00 |
| 0112 | Excavation, unclassified (202009P) | CY | 13 | $825.00 | $600.00 | $995.00 | $789.79 |
| 0113 | Temporary sheeting (501003P) | SF | 305 | $9.00 | $30.00 | $11.00 | $22.97 |
| 0114 | Furnishing drilled shaft equipment (503003P) | LS | 1 | $13,200 | $10,900 | $16,000 | $678,468 |
| 0115 | Crosshole sonic logging (503012M) | U | 1 | $4,400.00 | $6,800.00 | $5,400.00 | $3,532.13 |
| 0116 | Shaft coring (503015M) | LF | 25 | $82.50 | $1,236.00 | $100.00 | $281.04 |
| 0117 | Drilled shaft in soil 60" diameter (503027M) | LF | 25 | $1,980.00 | $2,100.00 | $2,500.00 | $1,462.81 |
| 0118 | Obstruction removal (503048M) | LF | 3 | $1,540.00 | $1,200.00 | $1,800.00 | $4,200.00 |
| 0119 | Reinforcement steel, epoxy- coated (504006P) | LB | 1,560 | $5.50 | $7.00 | $6.50 | $4.76 |
| 0120 | Epoxy waterproofing (504036P) | SY | 3 | $250.00 | $1,300.00 | $300.00 | $572.18 |
| 0121 | Sign support structure cap, HPC (504095P) | CY | 8 | $3,410.00 | $2,200.00 | $4,100.00 | $476.47 |
| 0122 | Cantilever sign support, DMS structure no. ___ 1601-238 (512002M) | U | 1 | $150,000 | $132,000 | $217,000 | $194,668 |
| 0123 | 9" X 14" concrete vertical curb (607034P) | LF | 200 | $60.00 | $105.00 | $82.00 | $430.38 |
| 0124 | 9" X 16" concrete vertical curb (607018P) | LF | 200 | $60.00 | $110.00 | $85.00 | $428.98 |
| 0125 | 9" X 18" concrete vertical curb (607021P) | LF | 200 | $60.00 | $115.00 | $90.00 | $431.25 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NJDOT's tabulation for this contract. NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.
Every contract let that day: NJDOT letting of April 15, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.