Mohegan Associates Inc: NYSDOT bid record
Mohegan Associates Inc submitted 12 bids on New York State DOT contracts in the data, from 07 APR 2022 to 21 NOV 2024, and was the low bidder on 6 of them (50%). When it was not low, its total sat a median +13% above the low bid.
- Owner
- New York State DOT
- Low bid volume
- $26,680,681
- Latest bid
- 21 NOV 2024
- Data through
- 15 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2022 | 5 | 3 | 60% |
| 2023 | 2 | 1 | 50% |
| 2024 | 5 | 2 | 40% |
By region
| Region | Bids | Low bids | Win rate |
|---|---|---|---|
| Region 08 | 7 | 4 | 57% |
| Region 01 | 4 | 1 | 25% |
| Region 08, 10, 11 | 1 | 1 | 100% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Field Change Payment (FCP) | 697.03 | DOL | 10 | 10 (100%) | $1.00 | $1.00 |
| Fuel Price Adjustment | 698.05 | DOL | 10 | 10 (100%) | $1.00 | $1.00 |
| Steel/Iron Price Adjustment | 698.06 | DOL | 10 | 10 (100%) | $1.00 | $1.00 |
| Office Technology and Supplies | 637.34 | DOL | 9 | 9 (100%) | $1.00 | $1.00 |
| Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips | 608.000013 | QUALITY UNIT | 7 | 7 (100%) | $105.00 | $90.00 |
| Removing and Disposing Box Beam Guide Railing | 606.73 | LF | 9 | 6 (67%) | $3.60 | $6.00 |
| Box Beam End Piece | 606.120101 | EACH | 8 | 6 (75%) | $648.00 | $750.00 |
| HPBO (Mod.) Corrugated Beam Guide Railing | 606.2701 | LF | 6 | 6 (100%) | $35.85 | $60.00 |
| Box Beam Guide Railing | 606.10 | LF | 10 | 5 (50%) | $55.44 | $55.00 |
| Asphalt Price Adjustment | 698.04 | DOL | 5 | 5 (100%) | $1.00 | $1.00 |
| Removing and Disposing Box Beam Guide Rail Turned-Down Terminal | 606.7920 | EACH | 9 | 4 (44%) | $101.00 | $200.00 |
| Box Beam Guide Railing End Assembly Type IIA | 606.120201 | EACH | 8 | 4 (50%) | $2,800.19 | $2,345.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Elderlee Inc | 7 | 4 of 7 |
| J Fletcher Creamer & Son Inc | 4 | 0 of 4 |
| Emi Guide Rail LLC | 4 | 3 of 4 |
| Amity Construction Corp. | 2 | 0 of 2 |
| Creamer-Ruberton, A Joint Venture | 2 | 2 of 2 |
| Westmoreland Construction Inc | 1 | 0 of 1 |
Latest bids
| Let | Contract | Region | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 21 NOV 2024 | D265342 | Region 08 | REPAIR OVERHEAD SIGN STRUCTURES | 1 of 3 | $2,665,434 | Low, 18% under the second |
| 26 SEP 2024 | D265318 | Region 01 | Guide Rail Replacement SFY 24 | 3 of 3 | $2,608,766 | +16% |
| 09 MAY 2024 | D265225 | Region 01 | INTERSTATE OVERHEAD SIGN STRUCTURE REPLACEMENT, SFY 24 | 1 of 1 | $4,046,579 | Low |
| 08 FEB 2024 | D265173 | Region 08 | GUIDE RAIL REPLACEMENTS IN ROCKLAND COUNTY | 3 of 3 | $13,983,376 | +10% |
| 25 JAN 2024 | D265183 | Region 08 | RUSTIC GUIDE RAIL REPLACEMENT IN WESTCHESTER | 2 of 2 | $31,429,311 | +12% |
| 14 SEP 2023 | D265079 | Region 08 | Guiderail Replacement: Interstate 84, Orange County | 1 of 5 | $1,686,928 | Low, 13% under the second |
| 15 JUN 2023 | D265038 | Region 01 | GUIDE RAIL REPLACEMENT 2023 | 3 of 3 | $3,279,602 | +34% |
| 04 AUG 2022 | D264785 | Region 08 | RUSTIC GUIDE RAIL REPLACEMENT Parts of R8 NYSDOT | 1 of 3 | $14,153,220 | Low, 9.0% under the second |
| 07 JUL 2022 | D264787 | Region 08 | Rustic Rail Replacement, Varied State highways, NYSDOT R-8 | 2 of 2 | $6,498,752 | +14% |
| 16 JUN 2022 | D264805 | Region 01 | RUSTIC RAIL REPLACEMENT | 2 of 4 | $2,070,825 | +10% |
| 02 JUN 2022 | D264822 | Region 08, 10, 11 | Sign Requirements Contract, Down State, Regions 8, 10 and 11 | 1 of 1 | $1,980,637 | Low |
| 07 APR 2022 | D264773 | Region 08 | GUIDERAIL REHABILITATION AND REPLACEMENT | 1 of 2 | $2,147,884 | Low, 66% under the second |
How this record was read
NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
- Every bid counted here matched its published total to within one dollar; NYSDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.