NYSDOT contract D265474 bid tabulation

Large Culvert Rehabilitation Project. Let by New York State DOT on June 26, 2025, Cortland, Onondaga, Oswego, Seneca, Region 03. 4 bids received; low bid $3,975,954 by Economy Paving Co Inc.

Owner
New York State DOT
Letting
26 JUN 2025
Pay items
58
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Economy Paving Co Inc$3,975,954Low
2Vector Construction Corp$4,725,368+19%
3Slate Hill Constructors Inc$5,516,712+39%
4Sealand Contractors Corp.$6,014,001+51%
NYSDOT contract D265474: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Economy Paving Co Inc2. Vector Construction Corp3. Slate Hill Constructors Inc4. Sealand Contractors Corp.
1Clearing and Grubbing (201.06)LS1$105,000$80,000$200,000$60,000
2Trench and Culvert Excavation (206.0201)CY1,307$2.00$60.00$55.00$60.00
3Mulch – Temporary (209.100101)SY6,524$0.50$1.75$3.50$3.40
4Stabilized Construction Access (209.22)SY2,264$50.00$50.00$26.00$75.00
5 (209.23010009)3,140$6.00$11.00$16.00$14.00
6Subbase Course, Type 2 (304.12)CY4$300.00$270.00$300.00$500.00
7 (520.09000010)6$10.00$22.00$45.00$70.00
8 (520.50000004)4$10.00$30.00$65.00$100.00
9 (553.030001)EACH2$100.00$25,000$1.00$5,000.00
10 (553.030002)EACH1$100.00$25,000$1.00$5,000.00
11 (553.030003)EACH1$100.00$25,000$1.00$5,000.00
12 (553.030004)EACH1$100.00$25,000$1.00$5,000.00
13 (553.030005)EACH1$100.00$40,000$1.00$5,000.00
14 (553.030006)EACH1$100.00$25,000$1.00$5,000.00
15 (553.030007)EACH2$100.00$25,000$1.00$5,000.00
16 (553.030008)EACH1$100.00$25,000$1.00$5,000.00
17Concrete for Structures, Performance (555.0021)CY66$3,000.00$3,500.00$2,850.00$5,000.00
18Performance Concrete Quality Adjustment – Concrete for Structures (555.9902)QUALITY UNIT1$10.00$10.00$10.00$10.00
19Epoxy-Coated Bar Reinforcement for Structures (556.0202)LB4,915$1.00$6.00$2.50$5.50
20Removal of Structural Concrete (580.01)CY3$2,000.00$450.00$1,000.00$4,000.00
21Removal and Replacement of Structural Concrete (582.0051)CY1$10,000$11,500$19,000$50,000
22 (582.99)1$25.00$25.00$25.00$25.00
23Drilling and Grouting Bolts or Reinforcing Bars (586.0201)EACH10$50.00$50.00$120.00$200.00
24 (602.2654)LF206$675.00$935.00$950.00$1,200.00
25 (602.2663)LF452$715.00$900.00$1,000.00$1,350.00
26 (602.2740)LF139$745.00$935.00$700.00$1,200.00
27 (602.90100107)361$1,075.00$1,000.00$1,500.00$1,450.00
28 (602.90100207)170$1,375.00$1,500.00$2,300.00$2,350.00
29 (602.90100307)408$1,225.00$1,300.00$1,750.00$2,000.00
30 (602.90100407)291$1,275.00$1,500.00$1,900.00$2,200.00
31 (604.070301)EACH1$5,000.00$17,500$7,100.00$10,000
32 (604.070302)EACH1$5,000.00$17,500$7,800.00$11,000
33 (604.070303)EACH1$5,000.00$17,500$7,100.00$10,000
34 (604.070304)EACH1$5,000.00$17,500$7,100.00$10,000
35Resetting Box Beam Guide Railing (New Posts) (606.5348)LF144$50.00$85.00$90.00$100.00
36Removing and Storing Box Beam Guide Railing (606.63)LF144$15.00$8.00$12.00$15.00
37 (607.41010010)646$4.50$8.00$10.50$10.00
38Topsoil - Roadside (610.1402)CY1,087$10.00$20.00$100.00$133.00
39Turf Establishment - Roadside (610.1601)SY6,524$0.50$2.00$3.75$3.60
40 (613.04000001)160$10.00$65.00$65.00$325.00
41 (617.10000024)76$50.00$56.00$115.00$170.00
42 (617.11000024)LS1$1,000.00$15,000$2,000.00$500.00
43Basic Work Zone Traffic Control (619.01)LS1$575,000$515,000$925,000$292,439
44Stone Filling (Medium) (620.04)CY371$175.00$165.00$150.00$285.00
45Stone Filling (Heavy) (620.05)CY400$165.00$170.00$180.00$315.00
46Bedding Material, Type 1 (620.0801)CY204$185.00$110.00$150.00$270.00
47 (620.14020009)325$235.00$210.00$220.00$410.00
48 (624.0113)SF150$20.00$50.00$80.00$150.00
49Survey Operations (625.01)LS1$5,000.00$55,000$7,000.00$60,000
50Concrete Cylinder Curing Equipment (637.04)EACH8$100.00$500.00$100.00$3,000.00
51Engineer’s Field Office – Type 2 (637.12)MONTH12$3,000.00$3,000.00$2,400.00$2,500.00
52Office Technology and Supplies (637.34)DOL500$1.00$1.00$1.00$1.00
53Construction Testing supplies – Consumables (637.36)DOL100$1.00$1.00$1.00$1.00
54Field Change Payment (FCP) (697.03)DOL384,000$1.00$1.00$1.00$1.00
55Asphalt Price Adjustment (698.04)DOL100$1.00$1.00$1.00$1.00
56Fuel Price Adjustment (698.05)DOL100$1.00$1.00$1.00$1.00
57Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00$1.00$1.00
58Mobilization (699.040001)LS1$150,314$180,000$150,000$231,000
NYSDOT contract D265474: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of June 26, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy