NYSDOT contract D265474 bid tabulation
Large Culvert Rehabilitation Project. Let by New York State DOT on June 26, 2025, Cortland, Onondaga, Oswego, Seneca, Region 03. 4 bids received; low bid $3,975,954 by Economy Paving Co Inc.
- Owner
- New York State DOT
- Letting
- 26 JUN 2025
- Pay items
- 58
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Economy Paving Co Inc | $3,975,954 | Low |
| 2 | Vector Construction Corp | $4,725,368 | +19% |
| 3 | Slate Hill Constructors Inc | $5,516,712 | +39% |
| 4 | Sealand Contractors Corp. | $6,014,001 | +51% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Economy Paving Co Inc | 2. Vector Construction Corp | 3. Slate Hill Constructors Inc | 4. Sealand Contractors Corp. |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $105,000 | $80,000 | $200,000 | $60,000 |
| 2 | Trench and Culvert Excavation (206.0201) | CY | 1,307 | $2.00 | $60.00 | $55.00 | $60.00 |
| 3 | Mulch – Temporary (209.100101) | SY | 6,524 | $0.50 | $1.75 | $3.50 | $3.40 |
| 4 | Stabilized Construction Access (209.22) | SY | 2,264 | $50.00 | $50.00 | $26.00 | $75.00 |
| 5 | (209.23010009) | 3,140 | $6.00 | $11.00 | $16.00 | $14.00 | |
| 6 | Subbase Course, Type 2 (304.12) | CY | 4 | $300.00 | $270.00 | $300.00 | $500.00 |
| 7 | (520.09000010) | 6 | $10.00 | $22.00 | $45.00 | $70.00 | |
| 8 | (520.50000004) | 4 | $10.00 | $30.00 | $65.00 | $100.00 | |
| 9 | (553.030001) | EACH | 2 | $100.00 | $25,000 | $1.00 | $5,000.00 |
| 10 | (553.030002) | EACH | 1 | $100.00 | $25,000 | $1.00 | $5,000.00 |
| 11 | (553.030003) | EACH | 1 | $100.00 | $25,000 | $1.00 | $5,000.00 |
| 12 | (553.030004) | EACH | 1 | $100.00 | $25,000 | $1.00 | $5,000.00 |
| 13 | (553.030005) | EACH | 1 | $100.00 | $40,000 | $1.00 | $5,000.00 |
| 14 | (553.030006) | EACH | 1 | $100.00 | $25,000 | $1.00 | $5,000.00 |
| 15 | (553.030007) | EACH | 2 | $100.00 | $25,000 | $1.00 | $5,000.00 |
| 16 | (553.030008) | EACH | 1 | $100.00 | $25,000 | $1.00 | $5,000.00 |
| 17 | Concrete for Structures, Performance (555.0021) | CY | 66 | $3,000.00 | $3,500.00 | $2,850.00 | $5,000.00 |
| 18 | Performance Concrete Quality Adjustment – Concrete for Structures (555.9902) | QUALITY UNIT | 1 | $10.00 | $10.00 | $10.00 | $10.00 |
| 19 | Epoxy-Coated Bar Reinforcement for Structures (556.0202) | LB | 4,915 | $1.00 | $6.00 | $2.50 | $5.50 |
| 20 | Removal of Structural Concrete (580.01) | CY | 3 | $2,000.00 | $450.00 | $1,000.00 | $4,000.00 |
| 21 | Removal and Replacement of Structural Concrete (582.0051) | CY | 1 | $10,000 | $11,500 | $19,000 | $50,000 |
| 22 | (582.99) | 1 | $25.00 | $25.00 | $25.00 | $25.00 | |
| 23 | Drilling and Grouting Bolts or Reinforcing Bars (586.0201) | EACH | 10 | $50.00 | $50.00 | $120.00 | $200.00 |
| 24 | (602.2654) | LF | 206 | $675.00 | $935.00 | $950.00 | $1,200.00 |
| 25 | (602.2663) | LF | 452 | $715.00 | $900.00 | $1,000.00 | $1,350.00 |
| 26 | (602.2740) | LF | 139 | $745.00 | $935.00 | $700.00 | $1,200.00 |
| 27 | (602.90100107) | 361 | $1,075.00 | $1,000.00 | $1,500.00 | $1,450.00 | |
| 28 | (602.90100207) | 170 | $1,375.00 | $1,500.00 | $2,300.00 | $2,350.00 | |
| 29 | (602.90100307) | 408 | $1,225.00 | $1,300.00 | $1,750.00 | $2,000.00 | |
| 30 | (602.90100407) | 291 | $1,275.00 | $1,500.00 | $1,900.00 | $2,200.00 | |
| 31 | (604.070301) | EACH | 1 | $5,000.00 | $17,500 | $7,100.00 | $10,000 |
| 32 | (604.070302) | EACH | 1 | $5,000.00 | $17,500 | $7,800.00 | $11,000 |
| 33 | (604.070303) | EACH | 1 | $5,000.00 | $17,500 | $7,100.00 | $10,000 |
| 34 | (604.070304) | EACH | 1 | $5,000.00 | $17,500 | $7,100.00 | $10,000 |
| 35 | Resetting Box Beam Guide Railing (New Posts) (606.5348) | LF | 144 | $50.00 | $85.00 | $90.00 | $100.00 |
| 36 | Removing and Storing Box Beam Guide Railing (606.63) | LF | 144 | $15.00 | $8.00 | $12.00 | $15.00 |
| 37 | (607.41010010) | 646 | $4.50 | $8.00 | $10.50 | $10.00 | |
| 38 | Topsoil - Roadside (610.1402) | CY | 1,087 | $10.00 | $20.00 | $100.00 | $133.00 |
| 39 | Turf Establishment - Roadside (610.1601) | SY | 6,524 | $0.50 | $2.00 | $3.75 | $3.60 |
| 40 | (613.04000001) | 160 | $10.00 | $65.00 | $65.00 | $325.00 | |
| 41 | (617.10000024) | 76 | $50.00 | $56.00 | $115.00 | $170.00 | |
| 42 | (617.11000024) | LS | 1 | $1,000.00 | $15,000 | $2,000.00 | $500.00 |
| 43 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $575,000 | $515,000 | $925,000 | $292,439 |
| 44 | Stone Filling (Medium) (620.04) | CY | 371 | $175.00 | $165.00 | $150.00 | $285.00 |
| 45 | Stone Filling (Heavy) (620.05) | CY | 400 | $165.00 | $170.00 | $180.00 | $315.00 |
| 46 | Bedding Material, Type 1 (620.0801) | CY | 204 | $185.00 | $110.00 | $150.00 | $270.00 |
| 47 | (620.14020009) | 325 | $235.00 | $210.00 | $220.00 | $410.00 | |
| 48 | (624.0113) | SF | 150 | $20.00 | $50.00 | $80.00 | $150.00 |
| 49 | Survey Operations (625.01) | LS | 1 | $5,000.00 | $55,000 | $7,000.00 | $60,000 |
| 50 | Concrete Cylinder Curing Equipment (637.04) | EACH | 8 | $100.00 | $500.00 | $100.00 | $3,000.00 |
| 51 | Engineer’s Field Office – Type 2 (637.12) | MONTH | 12 | $3,000.00 | $3,000.00 | $2,400.00 | $2,500.00 |
| 52 | Office Technology and Supplies (637.34) | DOL | 500 | $1.00 | $1.00 | $1.00 | $1.00 |
| 53 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 54 | Field Change Payment (FCP) (697.03) | DOL | 384,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 55 | Asphalt Price Adjustment (698.04) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 56 | Fuel Price Adjustment (698.05) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 57 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 58 | Mobilization (699.040001) | LS | 1 | $150,314 | $180,000 | $150,000 | $231,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of June 26, 2025. Compiled by Mirage Metrics.