NYSDOT contract D265483 bid tabulation
REPLACEMENT OF OVERHEAD SIGNS & GROUND MOUNTED SIGNS. Let by New York State DOT on May 8, 2025, Cattaraugus, Erie, Niagara, Region 05. 4 bids received; low bid $1,738,634 by Cold Spring Construction Company.
- Owner
- New York State DOT
- Letting
- 08 MAY 2025
- Pay items
- 53
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Cold Spring Construction Company | $1,738,634 | Low |
| 2 | Union Concrete & Construction Corp | $1,796,761 | +3.0% |
| 3 | Hunting Valley Construction Inc | $1,828,611 | +5.0% |
| 4 | Elderlee Inc | $1,916,623 | +10% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Cold Spring Construction Company | 2. Union Concrete & Construction Corp | 3. Hunting Valley Construction Inc | 4. Elderlee Inc |
|---|---|---|---|---|---|---|---|
| 1 | Seed and Mulch – Temporary (209.1003) | SY | 70 | $21.00 | $2.00 | $30.00 | $80.00 |
| 2 | Topsoil – Reuse On-Site Materials (610.1401) | CY | 21 | $65.00 | $180.00 | $250.00 | $190.00 |
| 3 | Turf Establishment - Roadside (610.1601) | SY | 70 | $20.00 | $5.50 | $42.00 | $80.00 |
| 4 | (617.11000024) | LS | 1 | $200.00 | $100.00 | $200.00 | $5,000.00 |
| 5 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $100,000 | $270,000 | $183,000 | $172,691 |
| 6 | (619.2401) | LS | 1 | $6,500.00 | $7,000.00 | $20,000 | $50,000 |
| 7 | Survey Operations (625.01) | LS | 1 | $9,500.00 | $6,000.00 | $30,000 | $21,520 |
| 8 | (625.09010015) | LS | 1 | $1,000.00 | $1.00 | $10.00 | $500.00 |
| 9 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $250.00 | $500.00 | $1,000.00 | $1,000.00 |
| 10 | Engineer’s Field Office – Type 2 (637.12) | MONTH | 12 | $2,400.00 | $1,800.00 | $3,000.00 | $3,700.00 |
| 11 | Office Technology and Supplies (637.34) | DOL | 500 | $1.00 | $1.00 | $1.00 | $1.00 |
| 12 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 13 | Anchor Bolts (644.11) | LB | 1,455 | $12.00 | $15.75 | $12.00 | $9.00 |
| 14 | (644.11010003) | 1 | $250.00 | $750.00 | $2,500.00 | $2,600.00 | |
| 15 | (644.11090003) | LS | 1 | $4,000.00 | $18,000 | $4,000.00 | $8,000.00 |
| 16 | Drilled Shaft for Overhead Sign Structures (644.20) | CY | 60 | $3,800.00 | $2,050.00 | $700.00 | $4,500.00 |
| 17 | (644.432030) | EACH | 1 | $125,000 | $105,000 | $195,000 | $110,000 |
| 18 | (644.435590) | EACH | 1 | $300,000 | $310,000 | $370,000 | $290,000 |
| 19 | Performance Concrete Quality Adjustment (644.99) | QUALITY UNIT | 1 | $10.50 | $10.50 | $10.50 | $10.50 |
| 20 | Ground-Mounted Sign Panels without Z-bars (645.5101) | SF | 85 | $31.00 | $33.00 | $33.00 | $70.00 |
| 21 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 7,075 | $36.00 | $37.50 | $38.00 | $31.00 |
| 22 | Ground-Mounted Sign Panels greater than 32 SF with Z-bars (645.5103) | SF | 248 | $36.00 | $38.50 | $38.00 | $45.00 |
| 23 | Overhead Sign Panels (645.61) | SF | 1,054 | $37.00 | $28.25 | $55.00 | $35.00 |
| 24 | Type A Sign Posts (645.81) | EACH | 1,529 | $174.00 | $183.00 | $175.00 | $185.00 |
| 25 | High-Capacity Type A Sign Posts with Soil Plates Only (645.8106) | EACH | 2 | $910.00 | $990.00 | $950.00 | $1,000.00 |
| 26 | (645.81090003) | 276 | $57.00 | $60.00 | $60.00 | $45.00 | |
| 27 | (645.830402) | EACH | 2 | $5,900.00 | $6,300.00 | $6,000.00 | $5,240.00 |
| 28 | (645.830602) | EACH | 2 | $6,900.00 | $7,250.00 | $7,000.00 | $6,300.00 |
| 29 | Pole-Mounted Sign Support System (Band Mounting) (645.85) | EACH | 2 | $205.00 | $215.00 | $200.00 | $130.00 |
| 30 | Reference Marker Panel (646.21) | EACH | 338 | $34.50 | $36.00 | $35.00 | $35.00 |
| 31 | Steel Post, 2.0 lb/ft (646.32) | EACH | 338 | $68.00 | $72.00 | $70.00 | $80.00 |
| 32 | Removal of Single Span Overhead Sign Panel(s), Structure, and Foundations (647.21) | EACH | 2 | $19,000 | $12,000 | $8,000.00 | $17,000 |
| 33 | Remove and Dispose Overhead Sign Panel, Sign Panel Assembly (647.25) | EACH | 1 | $2,000.00 | $1,500.00 | $2,000.00 | $1,600.00 |
| 34 | Remove and Store Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.41) | EACH | 700 | $34.00 | $35.00 | $35.00 | $75.00 |
| 35 | Remove and Dispose Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.51) | EACH | 1 | $30.00 | $32.00 | $30.00 | $170.00 |
| 36 | Remove and Dispose Sign Panel, Sign Panel Assembly Size III (Over 100 Square Feet) (647.53) | EACH | 3 | $98.00 | $130.00 | $100.00 | $220.00 |
| 37 | Remove and Dispose Type B Ground Mounted Sign Support and Foundation (647.65) | EACH | 9 | $140.00 | $180.00 | $140.00 | $160.00 |
| 38 | (647.83001002) | 338 | $7.25 | $6.50 | $8.00 | $13.00 | |
| 39 | (662.60000315) | LS | 1 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 |
| 40 | (680.510301) | EACH | 2 | $1,750.00 | $3,850.00 | $3,800.00 | $3,500.00 |
| 41 | (680.520105) | LF | 26 | $80.00 | $22.00 | $22.00 | $20.00 |
| 42 | (680.520205) | LF | 80 | $30.00 | $22.00 | $22.00 | $20.00 |
| 43 | (680.730514) | LF | 110 | $10.00 | $5.50 | $6.00 | $5.00 |
| 44 | (680.77000105) | 2 | $5,000.00 | $7,500.00 | $7,000.00 | $6,801.00 | |
| 45 | (680.80620215) | 2 | $12,500 | $2,200.00 | $2,200.00 | $2,000.00 | |
| 46 | Traffic Signal Module - 12-inch, Yellow Ball, LED (680.810103) | EACH | 4 | $325.00 | $275.00 | $300.00 | $250.00 |
| 47 | Traffic Signal Section - Polycarbonate, Type I, 12-inch (680.810601) | EACH | 4 | $650.00 | $330.00 | $320.00 | $300.00 |
| 48 | Traffic Signal Bracket Assembly - 1 Way (680.8111) | EACH | 4 | $300.00 | $265.00 | $250.00 | $240.00 |
| 49 | Field Change Payment (FCP) (697.03) | DOL | 75,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 50 | Asphalt Price Adjustment (698.04) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 51 | Fuel Price Adjustment (698.05) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 52 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 53 | Mobilization (699.040001) | LS | 1 | $66,000 | $69,100 | $70,000 | $73,700 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of May 8, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.