NYSDOT contract D265493 bid tabulation
Route 221 Over Big Brook Bridge Replacement. Let by New York State DOT on August 7, 2025, Cortland, Region 03. 6 bids received; low bid $2,579,310 by Vector Construction Corp.
- Owner
- New York State DOT
- Letting
- 07 AUG 2025
- Pay items
- 117
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Vector Construction Corp | $2,579,310 | Low |
| 2 | R De Vincentis Construction Inc | $2,669,000 | +3.0% |
| 3 | Economy Paving Co Inc | $2,696,697 | +5.0% |
| 4 | Bothar Construction LLC | $2,899,900 | +12% |
| 5 | Slate Hill Constructors Inc | $2,916,772 | +13% |
| 6 | Winn Construction Services Inc | $3,103,583 | +20% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Vector Construction Corp | 2. R De Vincentis Construction Inc | 3. Economy Paving Co Inc | 4. Bothar Construction LLC | 5. Slate Hill Constructors Inc | 6. Winn Construction Services Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $5,000.00 | $6,000.00 | $10,000 | $7,800.00 | $20,000 | $15,000 |
| 2 | (202.120001) | LS | 1 | $95,000 | $78,000 | $125,000 | $61,000 | $115,000 | $75,000 |
| 3 | Removal of Substructures (202.19) | CY | 115 | $120.00 | $240.00 | $105.00 | $390.00 | $260.00 | $100.00 |
| 4 | Unclassified Excavation and Disposal (203.02) | CY | 1,032 | $30.00 | $22.00 | $45.00 | $79.30 | $27.00 | $65.00 |
| 5 | Embankment In Place (203.03) | CY | 2,394 | $25.00 | $12.00 | $35.00 | $49.00 | $55.00 | $71.00 |
| 6 | Select Granular Fill (203.07) | CY | 247 | $65.00 | $96.00 | $55.00 | $76.45 | $100.00 | $58.00 |
| 7 | Select Structural Fill (203.21) | CY | 135 | $70.00 | $89.00 | $90.00 | $96.00 | $100.00 | $86.00 |
| 8 | (203.24010017) | 7 | $155.00 | $440.00 | $10.00 | $91.00 | $180.00 | $72.00 | |
| 9 | Structure Excavation (206.01) | CY | 995 | $40.00 | $17.00 | $35.00 | $21.25 | $30.00 | $30.00 |
| 10 | Trench and Culvert Excavation (206.0201) | CY | 422 | $35.00 | $29.00 | $2.00 | $61.00 | $50.00 | $51.00 |
| 11 | Geotextile Bedding (207.20) | SY | 9 | $90.00 | $110.00 | $10.00 | $119.25 | $25.00 | $175.00 |
| 12 | Prefabricated Composite Integral Abutment Drain (207.27) | SY | 130 | $17.00 | $21.00 | $15.00 | $20.00 | $15.00 | $14.50 |
| 13 | Mulch – Temporary (209.100101) | SY | 5,300 | $1.00 | $2.00 | $0.75 | $2.65 | $1.00 | $2.00 |
| 14 | Seed and Mulch – Temporary (209.1003) | SY | 1,350 | $2.00 | $2.00 | $0.95 | $6.70 | $1.10 | $1.75 |
| 15 | Silt Fence - Temporary (209.13) | LF | 200 | $5.00 | $9.00 | $5.00 | $3.15 | $4.00 | $5.50 |
| 16 | Rolled Erosion Control Product, Class I Type A, Short Term (209.1801) | SY | 200 | $4.00 | $5.00 | $10.00 | $4.65 | $2.50 | $5.50 |
| 17 | Rolled Erosion Control Product, Class II Type C, Intermediate (209.190301) | SY | 1,879 | $3.00 | $3.00 | $5.00 | $5.20 | $5.00 | $3.00 |
| 18 | Soil Stabilizers, Class IV Type A (209.2101) | SY | 200 | $2.25 | $6.50 | $5.00 | $4.60 | $4.00 | $8.75 |
| 19 | (209.23010009) | 1,047 | $6.00 | $7.50 | $7.50 | $15.00 | $11.00 | $7.00 | |
| 20 | Subbase Course, Type 2 (304.12) | CY | 2,437 | $75.00 | $71.00 | $85.00 | $86.65 | $90.00 | $80.00 |
| 21 | (404.0001) | TON | 103 | $80.00 | $80.00 | $80.00 | $80.00 | $80.00 | $80.00 |
| 22 | (404.0189) | TON | 15 | $215.00 | $230.00 | $225.00 | $205.50 | $235.00 | $287.00 |
| 23 | (404.0983) | TON | 480 | $125.00 | $132.00 | $155.00 | $163.00 | $145.00 | $186.00 |
| 24 | (404.2589) | TON | 677 | $125.00 | $130.00 | $145.00 | $140.50 | $125.00 | $160.00 |
| 25 | (404.3789) | TON | 869 | $115.00 | $118.00 | $135.00 | $127.30 | $120.00 | $145.00 |
| 26 | Diluted Tack Coat (407.0102) | GAL | 529 | $12.00 | $13.00 | $3.40 | $4.25 | $6.00 | $6.00 |
| 27 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 1,611 | $1.00 | $1.25 | $0.35 | $1.05 | $1.00 | $1.90 |
| 28 | Production Cold-Mill Surface Planing of Bituminous Concrete (490.15) | SY | 190 | $8.00 | $30.00 | $15.00 | $29.00 | $30.00 | $16.75 |
| 29 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 442 | $21.00 | $25.00 | $15.00 | $23.00 | $20.00 | $10.75 |
| 30 | Steel H-Piles (HP 12x84) (551.012084) | LF | 900 | $1.00 | $1.15 | $65.00 | $96.05 | $1.10 | $87.00 |
| 31 | Splices for Steel H-Piles (551.12) | EACH | 10 | $100.00 | $11.00 | $1.00 | $169.50 | $11.00 | $88.00 |
| 32 | Furnishing Equipment for Driving Piles (551.13) | LS | 1 | $155,500 | $143,000 | $50,000 | $49,155 | $125,000 | $90,000 |
| 33 | Dynamic Pile Load Testing (551.14) | EACH | 2 | $1,000.00 | $1,100.00 | $4,000.00 | $1,695.00 | $1,100.00 | $2,000.00 |
| 34 | (553.020001) | EACH | 1 | $13,000 | $13,000 | $1,000.00 | $1,500.00 | $1.00 | $18,500 |
| 35 | (553.020002) | EACH | 1 | $13,000 | $13,000 | $1,000.00 | $1,500.00 | $1.00 | $18,500 |
| 36 | Concrete for Structures, Performance (555.0021) | CY | 145 | $1,260.00 | $1,550.00 | $1,125.00 | $1,545.00 | $1,800.00 | $1,700.00 |
| 37 | Performance Concrete Quality Adjustment – Concrete for Structures (555.9902) | QUALITY UNIT | 1 | $7.50 | $7.50 | $7.50 | $7.50 | $7.50 | $7.50 |
| 38 | Galvanized Bar Reinforcement for Structures (556.0203) | LB | 27,500 | $2.20 | $2.35 | $2.15 | $2.65 | $2.25 | $2.50 |
| 39 | Stud Shear Connectors for Bridges (556.03) | EACH | 1,350 | $9.25 | $6.50 | $6.00 | $7.00 | $6.00 | $6.00 |
| 40 | (557.1019) | SY | 136 | $465.00 | $460.00 | $525.00 | $542.00 | $550.00 | $475.00 |
| 41 | (557.1119) | SY | 254 | $670.00 | $855.00 | $875.00 | $923.00 | $800.00 | $800.00 |
| 42 | Winter Surface Treatment – Superstructure Slabs and Structural Approach Slabs (557.29) | SY | 390 | $0.01 | $1.00 | $1.00 | $7.00 | $0.10 | $0.20 |
| 43 | (557.60010004) | 370 | $50.00 | $55.00 | $50.00 | $42.00 | $55.00 | $85.00 | |
| 44 | Performance Concrete Quality Adjustment – Superstructure and Approach Slab (557.9901) | QUALITY UNIT | 1 | $12.56 | $12.56 | $12.56 | $12.56 | $12.56 | $12.56 |
| 45 | Longitudinal Sawcut Grooving of Structural Slab Surface (558.02) | SY | 370 | $20.00 | $23.50 | $25.00 | $20.75 | $27.00 | $20.00 |
| 46 | Protective Sealing of Structural Concrete on New Bridge Decks and Bridge Deck Overlays (559.01) | SF | 3,285 | $0.50 | $1.30 | $0.65 | $2.15 | $2.50 | $0.80 |
| 47 | Protective Sealing of New Structural Concrete (559.02) | SF | 2,514 | $0.75 | $3.00 | $0.65 | $2.35 | $3.00 | $0.75 |
| 48 | (564.0501) | LS | 1 | $245,000 | $195,000 | $200,000 | $220,000 | $220,000 | $275,000 |
| 49 | (564.20010008) | 80,475 | $0.60 | $0.52 | $0.50 | $0.55 | $0.70 | $0.90 | |
| 50 | (565.30130101) | 10 | $125.00 | $330.00 | $350.00 | $230.00 | $250.00 | $400.00 | |
| 51 | Transition Bridge Railing (568.70) | LF | 151 | $216.00 | $195.00 | $180.00 | $200.35 | $185.00 | $225.00 |
| 52 | Single Slope (Half-Section) Concrete Bridge Barrier (569.04) | LF | 141 | $350.00 | $390.00 | $315.00 | $437.75 | $400.00 | $525.00 |
| 53 | Performance Concrete Quality Adjustment–Cast-In-Place Concrete Barrier (569.99) | QUALITY UNIT | 1 | $9.09 | $9.09 | $9.09 | $9.09 | $9.09 | $9.09 |
| 54 | (570.10) | LS | 1 | $610.00 | $1,500.00 | $100.00 | $3,700.00 | $200.00 | $1,500.00 |
| 55 | (603.6005) | LF | 62 | $125.00 | $125.00 | $115.00 | $210.00 | $100.00 | $78.00 |
| 56 | (603.6102) | LF | 20 | $122.00 | $140.00 | $105.00 | $200.00 | $100.00 | $77.00 |
| 57 | (603.6103) | LF | 24 | $110.00 | $143.00 | $105.00 | $201.00 | $100.00 | $89.00 |
| 58 | (603.7302) | EACH | 2 | $3,100.00 | $3,500.00 | $3,050.00 | $2,035.00 | $2,000.00 | $2,515.00 |
| 59 | (603.7303) | EACH | 2 | $3,300.00 | $3,500.00 | $3,350.00 | $2,225.00 | $2,200.00 | $2,655.00 |
| 60 | (603.7305) | EACH | 2 | $5,200.00 | $3,600.00 | $4,350.00 | $7,051.50 | $6,500.00 | $4,000.00 |
| 61 | Underdrain Filter, Type I (605.0901) | CY | 46 | $160.00 | $150.00 | $110.00 | $142.50 | $150.00 | $130.00 |
| 62 | (605.1701) | LF | 185 | $12.00 | $7.00 | $25.00 | $1.35 | $4.00 | $22.00 |
| 63 | (605.1702) | LF | 625 | $9.00 | $9.00 | $25.00 | $3.50 | $7.00 | $16.00 |
| 64 | Box Beam Guide Railing (606.10) | LF | 1,218 | $45.00 | $48.00 | $45.00 | $49.15 | $45.00 | $47.00 |
| 65 | Box Beam Guide Railing (Shop Bent or Shop Mitered) (606.100002) | LF | 34 | $55.00 | $59.00 | $55.00 | $59.90 | $58.00 | $57.25 |
| 66 | Box Beam End Piece (606.120101) | EACH | 1 | $600.00 | $630.00 | $600.00 | $644.10 | $600.00 | $615.25 |
| 67 | Box Beam Guide Railing End Assembly Type I (606.120102) | EACH | 2 | $4,000.00 | $3,200.00 | $4,000.00 | $4,214.90 | $4,000.00 | $4,025.00 |
| 68 | Box Beam Guide Railing End Assembly Type IIA (606.120201) | EACH | 7 | $2,000.00 | $2,100.00 | $1,850.00 | $2,067.90 | $2,000.00 | $1,975.00 |
| 69 | Removing and Disposing Box Beam Guide Railing (606.73) | LF | 398 | $10.00 | $17.00 | $10.00 | $3.00 | $5.00 | $6.00 |
| 70 | (607.41010010) | 200 | $4.50 | $9.00 | $5.00 | $8.45 | $8.00 | $6.00 | |
| 71 | Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013) | QUALITY UNIT | 1 | $65.00 | $65.00 | $65.00 | $65.00 | $65.00 | $65.00 |
| 72 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 131 | $250.00 | $246.00 | $195.00 | $222.00 | $185.00 | $235.00 |
| 73 | Stone Curb – Bridge (Type A) (609.0301) | LF | 57 | $192.00 | $220.00 | $200.00 | $167.30 | $150.00 | $153.00 |
| 74 | Compost (610.10) | CY | 12 | $450.00 | $220.00 | $70.00 | $245.00 | $140.00 | $102.00 |
| 75 | (610.15120208) | 137 | $8.00 | $8.00 | $1.00 | $35.00 | $6.00 | $22.00 | |
| 76 | Turf Establishment – Performance (610.1605) | SY | 2,636 | $13.00 | $2.50 | $1.50 | $9.30 | $20.00 | $13.00 |
| 77 | (611.0442) | EACH | 36 | $139.00 | $90.00 | $100.00 | $113.00 | $120.00 | $142.00 |
| 78 | (611.0711) | EACH | 441 | $30.00 | $11.00 | $10.00 | $16.95 | $17.00 | $34.00 |
| 79 | (611.19040024) | 36 | $38.00 | $3.50 | $5.00 | $22.60 | $24.00 | $42.00 | |
| 80 | (611.19070024) | 441 | $8.50 | $1.10 | $1.00 | $5.65 | $6.00 | $10.00 | |
| 81 | (617.01010024) | 200 | $23.00 | $6.00 | $5.00 | $11.30 | $6.00 | $10.00 | |
| 82 | (617.10000024) | 10 | $120.00 | $275.00 | $10.00 | $153.00 | $200.00 | $110.00 | |
| 83 | (617.11000024) | LS | 1 | $888.00 | $2,000.00 | $100.00 | $2,669.00 | $2,200.00 | $6,500.00 |
| 84 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $43,000 | $170,000 | $165,000 | $70,000 | $185,000 | $77,500 |
| 85 | Type III Construction Barricades (619.04) | EACH | 52 | $140.00 | $325.00 | $50.00 | $120.00 | $50.00 | $265.00 |
| 86 | (619.110511) | EACH | 4 | $4,900.00 | $13,000 | $10,000 | $7,900.00 | $6,500.00 | $17,700 |
| 87 | Temporary Positive Barrier – Category 1 (Pinning Prohibited) (619.1711) | LF | 160 | $38.00 | $33.00 | $50.00 | $74.00 | $50.00 | $10.00 |
| 88 | Mailboxes (619.27) | EACH | 1 | $630.00 | $250.00 | $500.00 | $256.00 | $100.00 | $125.00 |
| 89 | (619.99230101) | LS | 1 | $2,000.00 | $2,000.00 | $1,000.00 | $2,000.00 | $100.00 | $2,000.00 |
| 90 | (619.99230201) | 10 | $150.00 | $115.00 | $100.00 | $120.00 | $50.00 | $500.00 | |
| 91 | Stone Filling (Light) (620.03) | CY | 20 | $155.00 | $127.00 | $195.00 | $154.00 | $220.00 | $106.00 |
| 92 | Stone Filling (Medium) (620.04) | CY | 50 | $190.00 | $156.00 | $195.00 | $162.55 | $190.00 | $117.00 |
| 93 | Stone Filling (Heavy) (620.05) | CY | 230 | $190.00 | $176.00 | $175.00 | $178.00 | $175.00 | $131.00 |
| 94 | Bedding Material, Type 1 (620.0801) | CY | 75 | $120.00 | $115.00 | $175.00 | $126.00 | $155.00 | $132.00 |
| 95 | (621.51000015) | 660 | $12.00 | $9.00 | $1.00 | $2.10 | $16.00 | $12.00 | |
| 96 | Survey Operations (625.01) | LS | 1 | $44,000 | $17,000 | $50,000 | $35,000 | $35,000 | $25,000 |
| 97 | (625.09010015) | LS | 1 | $3,100.00 | $8,000.00 | $1,000.00 | $3,100.00 | $100.00 | $5,000.00 |
| 98 | (627.50140008) | 746 | $7.00 | $6.00 | $1.00 | $4.65 | $6.00 | $3.00 | |
| 99 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $5,000.00 | $3,500.00 | $10,000 | $4,300.00 | $500.00 | $4,500.00 |
| 100 | Engineer’s Field Office – Type 1 (637.11) | MONTH | 12 | $2,400.00 | $2,000.00 | $3,000.00 | $2,500.00 | $2,200.00 | $2,500.00 |
| 101 | Rain Gauge (637.26) | EACH | 1 | $250.00 | $250.00 | $100.00 | $250.00 | $100.00 | $100.00 |
| 102 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 103 | (637.41000115) | 12 | $130.00 | $300.00 | $100.00 | $1,900.00 | $250.00 | $150.00 | |
| 104 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 14 | $50.00 | $47.00 | $45.00 | $48.05 | $45.00 | $45.00 |
| 105 | Type A Sign Posts (645.81) | EACH | 2 | $250.00 | $225.00 | $205.00 | $231.65 | $220.00 | $208.00 |
| 106 | Reference Marker Panel (646.21) | EACH | 3 | $43.00 | $38.00 | $35.00 | $39.55 | $38.00 | $38.00 |
| 107 | Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23) | EACH | 32 | $24.00 | $23.00 | $25.00 | $22.60 | $21.00 | $21.00 |
| 108 | Steel Post, 2.0 lb/ft (646.32) | EACH | 35 | $89.00 | $80.00 | $75.00 | $82.50 | $75.00 | $75.00 |
| 109 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 1 | $25.00 | $120.00 | $100.00 | $215.00 | $11.00 | $89.00 |
| 110 | (657.020001) | LS | 1 | $20,000 | $19,000 | $20,000 | $19,281 | $10,000 | $30,000 |
| 111 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 3,650 | $1.30 | $1.25 | $1.50 | $1.45 | $1.50 | $1.00 |
| 112 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 3,650 | $1.30 | $1.25 | $1.50 | $1.45 | $1.50 | $1.00 |
| 113 | Field Change Payment (FCP) (697.03) | DOL | 103,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 114 | Asphalt Price Adjustment (698.04) | DOL | 1,485 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 115 | Fuel Price Adjustment (698.05) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 116 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 117 | Mobilization (699.040001) | LS | 1 | $99,000 | $100,389 | $100,231 | $108,758 | $80,000 | $115,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of August 7, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.