NYSDOT contract D265588 bid tabulation
LARGE CULVERT REPLACEMENT/REHABILITATION. Let by New York State DOT on November 6, 2025, Erie, Niagara, Region 05. 3 bids received; low bid $3,290,418 by McLaughlin Construction Corp/DBA Edbauer Construction.
- Owner
- New York State DOT
- Letting
- 06 NOV 2025
- Pay items
- 106
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | McLaughlin Construction Corp/DBA Edbauer Construction | $3,290,418 | Low |
| 2 | Oakgrove Construction Inc | $3,547,729 | +8.0% |
| 3 | Concrete Applied Technologies Corp/DBA:Catco | $3,574,338 | +9.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. McLaughlin Construction Corp/DBA Edbauer Construction | 2. Oakgrove Construction Inc | 3. Concrete Applied Technologies Corp/DBA:Catco |
|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $75,000 | $15,000 | $6,200.00 |
| 2 | Unclassified Excavation and Disposal (203.02) | CY | 2,780 | $22.00 | $30.00 | $30.00 |
| 3 | Embankment In Place (203.03) | CY | 7,120 | $23.00 | $20.00 | $22.00 |
| 4 | Select Granular Fill (203.07) | CY | 1,120 | $74.00 | $75.00 | $71.00 |
| 5 | Select Structural Fill (203.21) | CY | 230 | $82.00 | $150.00 | $88.00 |
| 6 | (203.24010017) | 11 | $75.00 | $250.00 | $113.00 | |
| 7 | Structure Excavation (206.01) | CY | 8,540 | $16.00 | $15.00 | $23.00 |
| 8 | Trench and Culvert Excavation (206.0201) | CY | 130 | $34.00 | $45.00 | $128.00 |
| 9 | Test Pit Excavation (206.05) | EACH | 2 | $1,600.00 | $2,500.00 | $1,500.00 |
| 10 | Geotextile Bedding (207.20) | SY | 770 | $3.50 | $4.00 | $3.50 |
| 11 | Geotextile Separation (207.21) | SY | 2,520 | $1.73 | $1.00 | $1.50 |
| 12 | Prefabricated Composite Structural Drain (207.26) | SY | 65 | $20.00 | $15.00 | $16.00 |
| 13 | Seed and Mulch – Temporary (209.1003) | SY | 8,880 | $0.35 | $1.00 | $0.50 |
| 14 | Check Dam (Ditch Bottom Width >10′), Gravel Bag – Temporary (209.110204) | EACH | 1 | $850.00 | $2,000.00 | $1,200.00 |
| 15 | Check Dam, Prefabricated – Temporary (209.1105) | LF | 220 | $2.00 | $15.00 | $38.00 |
| 16 | Drainage Structure Inlet Protection, Prefabricated – Temporary (209.1703) | LF | 25 | $3.00 | $40.00 | $38.00 |
| 17 | Sediment Filter Log, 12″ (209.2301) | LF | 1,160 | $2.00 | $5.00 | $6.00 |
| 18 | (304.15010005) | 1,887 | $76.00 | $45.00 | $80.00 | |
| 19 | (404.0001) | TON | 108 | $100.00 | $100.00 | $100.00 |
| 20 | Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003) | QUALITY UNIT | 18 | $100.00 | $100.00 | $100.00 |
| 21 | (404.0189) | TON | 23 | $120.00 | $200.00 | $210.00 |
| 22 | (404.0982) | TON | 333 | $203.00 | $135.00 | $190.00 |
| 23 | (404.1989) | TON | 495 | $182.00 | $100.00 | $120.00 |
| 24 | (404.3789) | TON | 1,316 | $129.00 | $85.00 | $100.00 |
| 25 | (404.4189) | TON | 260 | $182.00 | $125.00 | $150.00 |
| 26 | (404.4389) | TON | 795 | $110.00 | $85.00 | $110.00 |
| 27 | Diluted Tack Coat (407.0102) | GAL | 760 | $10.00 | $8.00 | $8.00 |
| 28 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 2,335 | $0.50 | $0.50 | $1.60 |
| 29 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 930 | $15.00 | $15.00 | $15.00 |
| 30 | (553.020001) | EACH | 2 | $100.00 | $15,000 | $1.00 |
| 31 | (553.030001) | EACH | 1 | $500.00 | $35,000 | $1.00 |
| 32 | (554.3001) | SF | 330 | $63.00 | $40.00 | $48.00 |
| 33 | Footing Concrete, Performance (555.0011) | CY | 40 | $1,280.00 | $1,000.00 | $1,500.00 |
| 34 | Concrete for Structures, Performance (555.0021) | CY | 8 | $4,768.00 | $3,500.00 | $4,300.00 |
| 35 | Performance Concrete Quality Adjustment – Footing Concrete (555.9901) | QUALITY UNIT | 1 | $5.50 | $5.50 | $5.50 |
| 36 | Performance Concrete Quality Adjustment – Concrete for Structures (555.9902) | QUALITY UNIT | 1 | $15.00 | $15.00 | $15.00 |
| 37 | Epoxy-Coated Bar Reinforcement for Structures (556.0202) | LB | 5,000 | $4.70 | $4.00 | $4.70 |
| 38 | Protective Sealing of New Structural Concrete (559.02) | SF | 500 | $4.00 | $4.00 | $5.30 |
| 39 | (562.0101) | SY | 66 | $1,400.00 | $1,750.00 | $1,890.00 |
| 40 | Performance Concrete Quality Adjustment (562.99) | QUALITY UNIT | 1 | $20.00 | $20.00 | $20.00 |
| 41 | Steel Bridge Railing (Four-Rail) (568.51) | LF | 36 | $340.00 | $350.00 | $347.00 |
| 42 | Steel Bridge Railing (Three-Rail) (568.54) | LF | 24 | $270.00 | $300.00 | $274.00 |
| 43 | Transition Bridge Railing (568.70) | LF | 192 | $202.00 | $250.00 | $206.00 |
| 44 | (595.50000018) | 12,100 | $7.00 | $3.00 | $4.40 | |
| 45 | (603.63120915) | 297 | $1,895.00 | $2,100.00 | $1,550.00 | |
| 46 | (603.67000001) | 106 | $1,375.00 | $1,500.00 | $1,410.00 | |
| 47 | (603.9818) | LF | 18 | $100.00 | $65.00 | $146.00 |
| 48 | (604.300611) | LF | 6 | $1,027.00 | $650.00 | $856.00 |
| 49 | Box Beam Guide Railing (606.10) | LF | 457 | $55.00 | $55.00 | $54.00 |
| 50 | Box Beam End Piece (606.120101) | EACH | 1 | $700.00 | $1,000.00 | $702.00 |
| 51 | Box Beam Guide Railing End Assembly Type I (606.120102) | EACH | 3 | $4,500.00 | $4,500.00 | $4,590.00 |
| 52 | Box Beam Guide Railing End Assembly Type IIA (606.120201) | EACH | 3 | $2,175.00 | $2,500.00 | $2,230.00 |
| 53 | Removing and Disposing Box Beam Guide Railing (606.73) | LF | 635 | $4.50 | $6.00 | $7.00 |
| 54 | Removing and Disposing Box Beam Guide Rail Turned-Down Terminal (606.7920) | EACH | 2 | $100.00 | $500.00 | $918.00 |
| 55 | (607.97000008) | 160 | $78.00 | $75.00 | $73.00 | |
| 56 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 55 | $310.00 | $200.00 | $278.00 |
| 57 | Stone Curb – Bridge (Type A) (609.0301) | LF | 53 | $260.00 | $300.00 | $252.00 |
| 58 | Topsoil - Roadside (610.1402) | CY | 985 | $75.00 | $40.00 | $82.00 |
| 59 | Turf Establishment - Roadside (610.1601) | SY | 8,370 | $0.50 | $1.00 | $2.20 |
| 60 | Wildflower Seeding (610.17) | SY | 510 | $1.25 | $6.00 | $4.00 |
| 61 | Watering Vegetation (610.19) | 1,000 GALLONS | 113 | $10.00 | $50.00 | $80.00 |
| 62 | (613.04000001) | 281 | $12.00 | $65.00 | $90.00 | |
| 63 | (614.060204) | EACH | 10 | $320.00 | $1,000.00 | $785.00 |
| 64 | (614.060304) | EACH | 3 | $650.00 | $2,500.00 | $1,310.00 |
| 65 | (614.060404) | EACH | 1 | $4,740.00 | $3,500.00 | $1,960.00 |
| 66 | (617.11000024) | LS | 1 | $200.00 | $1,000.00 | $2,810.00 |
| 67 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $157,239 | $522,000 | $200,000 |
| 68 | Type III Construction Barricades (619.04) | EACH | 35 | $150.00 | $75.00 | $91.00 |
| 69 | Cover Existing Pavement Marking Stripes (Removable Tape) (619.0803) | LF | 11,370 | $1.00 | $2.00 | $7.00 |
| 70 | Cover Existing Pavement Marking Letters or Symbols (Removable Tape) (619.0804) | EACH | 2 | $350.00 | $350.00 | $488.00 |
| 71 | (619.100103) | LF | 16,685 | $1.00 | $2.00 | $6.00 |
| 72 | (619.111113) | EACH | 5 | $6,500.00 | $5,500.00 | $8,200.00 |
| 73 | (619.17060005) | 3,508 | $1.83 | $3.00 | $3.00 | |
| 74 | Temporary Positive Barrier – Category 1 (Pinning Prohibited) (619.1711) | LF | 1,740 | $10.00 | $10.00 | $35.00 |
| 75 | Temporary Positive Barrier – Category 7 (Pinning and Box-Beam-Stiffening Required) (619.1717) | LF | 2,030 | $12.00 | $20.00 | $50.00 |
| 76 | Stone Filling (Light) (620.03) | CY | 15 | $184.00 | $90.00 | $150.00 |
| 77 | Stone Filling (Medium) (620.04) | CY | 121 | $144.00 | $125.00 | $150.00 |
| 78 | Stone Filling (Heavy) (620.05) | CY | 220 | $173.00 | $150.00 | $150.00 |
| 79 | Bedding Material, Type 1 (620.0801) | CY | 71 | $110.00 | $125.00 | $120.00 |
| 80 | Survey Operations (625.01) | LS | 1 | $25,000 | $15,000 | $36,200 |
| 81 | Concrete Right of Way Markers Type L (Low) (625.04) | EACH | 6 | $1,771.00 | $750.00 | $680.00 |
| 82 | Permanent Survey Markers (625.06) | EACH | 2 | $2,412.00 | $750.00 | $2,000.00 |
| 83 | (627.50140008) | 421 | $10.00 | $4.00 | $9.00 | |
| 84 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $250.00 | $2,000.00 | $3,600.00 |
| 85 | Engineer’s Field Office – Type 2 (637.12) | MONTH | 15 | $1,100.00 | $2,000.00 | $2,300.00 |
| 86 | Office Technology and Supplies (637.34) | DOL | 500 | $1.00 | $1.00 | $1.00 |
| 87 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 88 | Reference Marker Panel (646.21) | EACH | 3 | $75.00 | $50.00 | $55.00 |
| 89 | Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels (646.22) | EACH | 12 | $20.00 | $20.00 | $18.00 |
| 90 | Steel Post, 1.1 lb/ft (646.31) | EACH | 1 | $150.00 | $100.00 | $78.00 |
| 91 | Steel Post, 2.0 lb/ft (646.32) | EACH | 15 | $95.00 | $100.00 | $92.00 |
| 92 | Relocate Sign Panel, Sign Panel Assembly Size II (30-100 Square Feet) (647.32) | EACH | 2 | $3,900.00 | $10,000 | $39.00 |
| 93 | Milled-In Audible Roadway Delineators (MIARDs) (649.01) | LF | 930 | $6.00 | $5.00 | $5.00 |
| 94 | Centerline Audible Roadway Delineators (CARDs) (649.11) | LF | 235 | $7.00 | $20.00 | $6.00 |
| 95 | Welded Frame & Rectangular Grate 11 (655.1011) | EACH | 1 | $1,400.00 | $1,500.00 | $1,300.00 |
| 96 | Solar Power System (680.81) | EACH | 2 | $3,000.00 | $6,000.00 | $5,000.00 |
| 97 | Flashing Beacon Sign Assembly (680.8220) | EACH | 2 | $8,500.00 | $5,000.00 | $15,000 |
| 98 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 1,579 | $4.00 | $4.00 | $3.50 |
| 99 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 1,168 | $4.00 | $4.00 | $3.50 |
| 100 | White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404) | EACH | 2 | $400.00 | $350.00 | $330.00 |
| 101 | Field Change Payment (FCP) (697.03) | DOL | 198,000 | $1.00 | $1.00 | $1.00 |
| 102 | Asphalt Price Adjustment (698.04) | DOL | 8,500 | $1.00 | $1.00 | $1.00 |
| 103 | Fuel Price Adjustment (698.05) | DOL | 4,950 | $1.00 | $1.00 | $1.00 |
| 104 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 105 | (698.93940015) | LS | 1 | $21,000 | $21,000 | $21,000 |
| 106 | Mobilization (699.040001) | LS | 1 | $126,000 | $136,100 | $135,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of November 6, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.