NYSDOT contract D265589 bid tabulation
LARGE CULVERT REPLACEMENT/REHABILITATION. Let by New York State DOT on November 20, 2025, Cattaraugus, Erie, Region 05. 3 bids received; low bid $3,815,481 by Legend Excavating LLC.
- Owner
- New York State DOT
- Letting
- 20 NOV 2025
- Pay items
- 115
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Legend Excavating LLC | $3,815,481 | Low |
| 2 | Concrete Applied Technologies Corp/DBA:Catco | $4,439,539 | +16% |
| 3 | McLaughlin Construction Corp/DBA Edbauer Construction | $4,505,565 | +18% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Legend Excavating LLC | 2. Concrete Applied Technologies Corp/DBA:Catco | 3. McLaughlin Construction Corp/DBA Edbauer Construction |
|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $14,000 | $82,000 | $438,000 |
| 2 | Removal of Substructures (202.19) | CY | 136 | $15.00 | $170.00 | $110.00 |
| 3 | Unclassified Excavation and Disposal (203.02) | CY | 4,100 | $22.00 | $30.00 | $24.00 |
| 4 | Embankment In Place (203.03) | CY | 3,440 | $12.00 | $35.00 | $32.00 |
| 5 | Select Granular Fill (203.07) | CY | 421 | $62.00 | $70.00 | $94.00 |
| 6 | Select Structural Fill (203.21) | CY | 11 | $62.00 | $130.00 | $110.00 |
| 7 | (203.24010017) | 9 | $40.00 | $130.00 | $95.00 | |
| 8 | Structure Excavation (206.01) | CY | 4,310 | $15.00 | $30.00 | $26.00 |
| 9 | Trench and Culvert Excavation (206.0201) | CY | 225 | $14.00 | $75.00 | $30.00 |
| 10 | Test Pit Excavation (206.05) | EACH | 3 | $500.00 | $2,500.00 | $3,000.00 |
| 11 | Geotextile Bedding (207.20) | SY | 903 | $5.00 | $4.00 | $3.75 |
| 12 | Geotextile Drainage (207.22) | SY | 138 | $5.00 | $5.00 | $5.30 |
| 13 | Seed and Mulch – Temporary (209.1003) | SY | 3,010 | $2.00 | $0.50 | $0.50 |
| 14 | Check Dam (Ditch Bottom Width >10′), Gravel Bag – Temporary (209.110204) | EACH | 4 | $5,000.00 | $1,200.00 | $550.00 |
| 15 | Sediment Filter Log, 12″ (209.2301) | LF | 2,370 | $5.00 | $6.50 | $1.50 |
| 16 | (304.15200005) | 1,925 | $60.00 | $77.00 | $88.00 | |
| 17 | (404.0001) | TON | 92 | $100.00 | $100.00 | $100.00 |
| 18 | Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003) | QUALITY UNIT | 29 | $100.00 | $100.00 | $100.00 |
| 19 | (404.0189) | TON | 10 | $110.00 | $248.00 | $120.00 |
| 20 | (404.0982) | TON | 385 | $110.00 | $248.00 | $244.00 |
| 21 | (404.1989) | TON | 460 | $110.00 | $208.00 | $230.00 |
| 22 | (404.3789) | TON | 970 | $110.00 | $164.00 | $170.00 |
| 23 | (404.4189) | TON | 35 | $110.00 | $206.00 | $260.00 |
| 24 | (404.4389) | TON | 395 | $110.00 | $175.00 | $180.00 |
| 25 | (404.4589) | TON | 545 | $110.00 | $175.00 | $145.00 |
| 26 | Diluted Tack Coat (407.0102) | GAL | 800 | $7.00 | $10.00 | $10.00 |
| 27 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 3,655 | $3.00 | $1.50 | $0.25 |
| 28 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 1,590 | $4.00 | $22.00 | $18.00 |
| 29 | Temporary Steel Sheeting (552.13) | SF | 6,986 | $40.00 | $5.00 | $1.00 |
| 30 | (552.2001) | LF | 198 | $110.00 | $10.00 | $1.00 |
| 31 | (552.2201) | LF | 198 | $310.00 | $20.00 | $1.00 |
| 32 | (552.230201) | SF | 508 | $40.00 | $5.00 | $1.00 |
| 33 | (553.030001) | EACH | 1 | $5,000.00 | $1,000.00 | $100.00 |
| 34 | (553.030002) | EACH | 1 | $5,000.00 | $1,000.00 | $100.00 |
| 35 | (553.030003) | EACH | 1 | $5,000.00 | $1,000.00 | $100.00 |
| 36 | (553.030004) | EACH | 1 | $5,000.00 | $1,000.00 | $100.00 |
| 37 | Protective Sealing of New Structural Concrete (559.02) | SF | 550 | $3.00 | $5.00 | $4.00 |
| 38 | (560.13200007) | 52 | $350.00 | $120.00 | $74.00 | |
| 39 | Steel Bridge Railing (Four-Rail) (568.51) | LF | 39 | $400.00 | $430.00 | $430.00 |
| 40 | Steel Bridge Railing (Three-Rail) (568.54) | LF | 24 | $290.00 | $300.00 | $298.00 |
| 41 | Transition Bridge Railing (568.70) | LF | 176 | $280.00 | $285.00 | $284.00 |
| 42 | Pedestrian and Bicycle Railing (Four-Rail) (568.83) | LF | 44 | $280.00 | $300.00 | $299.00 |
| 43 | (595.50000018) | 7,040 | $4.00 | $5.50 | $8.00 | |
| 44 | (603.171116) | EACH | 1 | $500.00 | $1,100.00 | $637.00 |
| 45 | (603.171614) | EACH | 1 | $500.00 | $1,300.00 | $957.00 |
| 46 | (603.63080415) | 67 | $2,300.00 | $2,519.00 | $3,200.00 | |
| 47 | (603.63120415) | 95 | $2,400.00 | $2,936.00 | $2,700.00 | |
| 48 | (603.63140615) | 55 | $2,900.00 | $3,290.00 | $4,300.00 | |
| 49 | (603.63150515) | 70 | $3,600.00 | $4,314.00 | $4,600.00 | |
| 50 | (603.67000001) | 113 | $1,400.00 | $1,450.00 | $1,900.00 | |
| 51 | (603.7303) | EACH | 1 | $2,000.00 | $4,300.00 | $5,700.00 |
| 52 | (603.9812) | LF | 14 | $55.00 | $108.00 | $80.00 |
| 53 | (603.9836) | LF | 20 | $120.00 | $320.00 | $137.00 |
| 54 | (604.4048) | LF | 6 | $950.00 | $670.00 | $750.00 |
| 55 | Underdrain Filter, Type II (605.1001) | CY | 17 | $60.00 | $66.00 | $92.00 |
| 56 | (605.1501) | LF | 220 | $22.00 | $9.00 | $17.00 |
| 57 | Box Beam Guide Railing (606.10) | LF | 326 | $70.00 | $70.00 | $70.00 |
| 58 | Box Beam Guide Railing (Shop Bent or Shop Mitered) (606.100002) | LF | 83 | $90.00 | $85.00 | $86.00 |
| 59 | Box Beam End Piece (606.120101) | EACH | 3 | $760.00 | $835.00 | $834.00 |
| 60 | Box Beam Guide Railing End Assembly Type I (606.120102) | EACH | 1 | $5,200.00 | $5,700.00 | $5,655.00 |
| 61 | Box Beam Guide Railing End Assembly Type IIA (606.120201) | EACH | 7 | $2,500.00 | $2,800.00 | $2,736.00 |
| 62 | Removing and Disposing Corrugated Beam Guide Railing (606.71) | LF | 124 | $10.00 | $7.00 | $5.00 |
| 63 | Removing and Disposing Box Beam Guide Railing (606.73) | LF | 429 | $10.00 | $7.00 | $6.00 |
| 64 | Removing and Disposing Anchorage Units for Corrugated Beam Guide Railing and Median Barrier (606.7910) | EACH | 4 | $10.00 | $900.00 | $75.00 |
| 65 | Removing and Disposing Box Beam Guide Rail Turned-Down Terminal (606.7920) | EACH | 7 | $10.00 | $900.00 | $200.00 |
| 66 | Concrete Sidewalks and Driveways (608.0101) | CY | 28 | $1,000.00 | $1,500.00 | $1,328.00 |
| 67 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 59 | $110.00 | $265.00 | $380.00 |
| 68 | Stone Curb – Bridge (Type A) (609.0301) | LF | 57 | $500.00 | $190.00 | $230.00 |
| 69 | Topsoil - Roadside (610.1402) | CY | 620 | $30.00 | $100.00 | $70.00 |
| 70 | Turf Establishment - Roadside (610.1601) | SY | 5,360 | $4.00 | $4.00 | $0.50 |
| 71 | Wildflower Seeding (610.17) | SY | 80 | $30.00 | $8.00 | $1.50 |
| 72 | Watering Vegetation (610.19) | 1,000 GALLONS | 18 | $500.00 | $80.00 | $50.00 |
| 73 | (613.04000001) | 191 | $6.00 | $100.00 | $30.00 | |
| 74 | (614.060204) | EACH | 13 | $1,000.00 | $640.00 | $405.00 |
| 75 | (614.060304) | EACH | 7 | $1,500.00 | $1,100.00 | $1,444.00 |
| 76 | (614.060404) | EACH | 5 | $2,000.00 | $1,700.00 | $2,181.00 |
| 77 | (614.060504) | EACH | 2 | $2,500.00 | $2,300.00 | $4,388.00 |
| 78 | (617.11000024) | LS | 1 | $5,000.00 | $3,600.00 | $100.00 |
| 79 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $80,000 | $361,600 | $189,397 |
| 80 | Type III Construction Barricades (619.04) | EACH | 20 | $75.00 | $90.00 | $150.00 |
| 81 | Cover Existing Pavement Marking Stripes (Removable Tape) (619.0803) | LF | 7,775 | $2.00 | $0.50 | $1.10 |
| 82 | (619.100103) | LF | 10,870 | $3.00 | $0.50 | $1.10 |
| 83 | (619.111113) | EACH | 9 | $2,000.00 | $5,400.00 | $4,000.00 |
| 84 | (619.130101) | EACH | 1 | $115,150 | $36,000 | $70,000 |
| 85 | (619.130102) | EACH | 1 | $46,450 | $21,000 | $22,000 |
| 86 | (619.130103) | EACH | 1 | $69,200 | $36,000 | $35,000 |
| 87 | (619.130104) | EACH | 1 | $69,950 | $21,000 | $18,000 |
| 88 | (619.17060005) | 4,140 | $15.00 | $2.00 | $1.10 | |
| 89 | Temporary Positive Barrier – Category 1 (Pinning Prohibited) (619.1711) | LF | 2,830 | $50.00 | $30.00 | $24.00 |
| 90 | Temporary Positive Barrier – Category 5 (Pinning Prohibited) (619.1715) | LF | 1,610 | $50.00 | $30.00 | $24.00 |
| 91 | Temporary Impact Attenuator - Redirective (Test Level 3) (619.1803) | EACH | 17 | $5,000.00 | $2,500.00 | $3,488.00 |
| 92 | Mailboxes (619.27) | EACH | 3 | $300.00 | $600.00 | $280.00 |
| 93 | Stone Filling (Light) (620.03) | CY | 65 | $100.00 | $150.00 | $119.00 |
| 94 | Stone Filling (Medium) (620.04) | CY | 205 | $150.00 | $175.00 | $125.00 |
| 95 | Stone Filling (Heavy) (620.05) | CY | 505 | $200.00 | $175.00 | $135.00 |
| 96 | Bedding Material, Type 1 (620.0801) | CY | 170 | $60.00 | $95.00 | $96.00 |
| 97 | Bedding Material, Type 2 (620.0802) | CY | 25 | $60.00 | $100.00 | $106.00 |
| 98 | (621.51970008) | 40 | $85.00 | $33.00 | $30.00 | |
| 99 | Crushed Stone (In-Place Measure) (623.12) | CY | 235 | $60.00 | $90.00 | $120.00 |
| 100 | Survey Operations (625.01) | LS | 1 | $10,000 | $200,000 | $85,000 |
| 101 | Concrete Right of Way Markers Type H (High) (625.03) | EACH | 12 | $250.00 | $600.00 | $1,235.00 |
| 102 | Concrete Right of Way Markers Type L (Low) (625.04) | EACH | 3 | $200.00 | $600.00 | $1,407.00 |
| 103 | Permanent Survey Markers (625.06) | EACH | 5 | $2,000.00 | $2,000.00 | $1,730.00 |
| 104 | (627.50140008) | 1,300 | $5.00 | $6.00 | $7.00 | |
| 105 | Engineer’s Field Office – Type 2 (637.12) | MONTH | 15 | $500.00 | $2,500.00 | $1,100.00 |
| 106 | Office Technology and Supplies (637.34) | DOL | 500 | $1.00 | $1.00 | $1.00 |
| 107 | Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels (646.22) | EACH | 12 | $50.00 | $33.00 | $32.00 |
| 108 | Steel Post, 2.0 lb/ft (646.32) | EACH | 12 | $135.00 | $144.00 | $144.00 |
| 109 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 3,551 | $3.00 | $5.00 | $5.50 |
| 110 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 1,676 | $3.00 | $5.00 | $5.50 |
| 111 | Field Change Payment (FCP) (697.03) | DOL | 203,000 | $1.00 | $1.00 | $1.00 |
| 112 | Asphalt Price Adjustment (698.04) | DOL | 8,250 | $1.00 | $1.00 | $1.00 |
| 113 | Fuel Price Adjustment (698.05) | DOL | 4,500 | $1.00 | $1.00 | $1.00 |
| 114 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 115 | Mobilization (699.040001) | LS | 1 | $87,600 | $165,000 | $173,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of November 20, 2025. Compiled by Mirage Metrics.