BRIDGE DECK REPLACEMENT - NYS Route 434 Over Choconut Creek. Let by New York State DOT on January 22, 2026, Broome, Region 09. 5 bids received; low bid $4,367,231 by Bette & Cring LLC.
- Owner
- New York State DOT
- Letting
- 22 JAN 2026
- Pay items
- 114
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Bette & Cring LLC | $4,367,231 | Low |
| 2 | R De Vincentis Construction Inc | $4,624,000 | +6.0% |
| 3 | Vector Construction Corp | $4,641,839 | +6.0% |
| 4 | Bothar Construction LLC | $5,000,000 | +14% |
| 5 | Economy Paving Co Inc | $5,407,754 | +24% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Bette & Cring LLC | 2. R De Vincentis Construction Inc | 3. Vector Construction Corp | 4. Bothar Construction LLC | 5. Economy Paving Co Inc |
|---|---|---|---|---|---|---|---|---|
| 1 | (201.07000004) | 1,102 | $5.00 | $10.00 | $3.00 | $15.00 | $5.00 | |
| 2 | Removal of Steel Supported Structural Slabs (with shear connectors) – Type A (202.2201) | SF | 10,800 | $30.00 | $32.00 | $45.00 | $21.50 | $50.00 |
| 3 | (203.01990006) | 220 | $125.00 | $100.00 | $48.00 | $156.60 | $10.00 | |
| 4 | Unclassified Excavation and Disposal (203.02) | CY | 968 | $35.00 | $27.00 | $34.00 | $38.00 | $50.00 |
| 5 | Embankment In Place (203.03) | CY | 538 | $55.00 | $16.00 | $25.00 | $57.45 | $30.00 |
| 6 | Select Structural Fill (203.21) | CY | 216 | $90.00 | $66.00 | $80.00 | $99.50 | $75.00 |
| 7 | Structure Excavation (206.01) | CY | 589 | $25.00 | $16.00 | $50.00 | $25.00 | $25.00 |
| 8 | Geotextile Separation (207.21) | SY | 213 | $3.25 | $5.00 | $5.00 | $3.25 | $1.00 |
| 9 | Prefabricated Composite Structural Drain (207.26) | SY | 200 | $20.00 | $16.00 | $22.00 | $16.35 | $10.00 |
| 10 | Seed and Mulch – Temporary (209.1003) | SY | 762 | $2.25 | $3.00 | $2.00 | $5.25 | $5.00 |
| 11 | Soil Stabilizers, Class IV Type C (209.2103) | SY | 648 | $7.00 | $5.00 | $1.50 | $5.65 | $1.50 |
| 12 | Stabilized Construction Access (209.22) | SY | 105 | $35.00 | $53.00 | $50.00 | $81.80 | $50.00 |
| 13 | Sediment Filter Log, 12″ (209.2301) | LF | 345 | $9.00 | $28.00 | $9.00 | $9.55 | $8.50 |
| 14 | Subbase Course, Optional Type (304.15) | CY | 698 | $90.00 | $100.00 | $80.00 | $79.00 | $95.00 |
| 15 | (404.0982) | TON | 168 | $190.00 | $230.00 | $245.00 | $190.00 | $195.00 |
| 16 | (404.1989) | TON | 210 | $175.00 | $185.00 | $195.00 | $175.00 | $185.00 |
| 17 | (404.2589) | TON | 263 | $160.00 | $190.00 | $175.00 | $160.00 | $175.00 |
| 18 | (404.4389) | TON | 172 | $160.00 | $184.00 | $175.00 | $160.00 | $165.00 |
| 19 | (407.01040009) | 210 | $12.00 | $17.00 | $12.00 | $12.00 | $3.60 | |
| 20 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 788 | $2.00 | $5.00 | $2.00 | $2.00 | $0.40 |
| 21 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 1,300 | $15.00 | $21.00 | $16.00 | $12.35 | $17.25 |
| 22 | Interim Steel Sheeting (552.15) | SF | 1,224 | $40.00 | $36.00 | $50.00 | $48.40 | $25.00 |
| 23 | (553.030001) | EACH | 1 | $1.00 | $16,000 | $6,500.00 | $1,500.00 | $1,000.00 |
| 24 | (553.030002) | EACH | 1 | $1.00 | $25,000 | $6,500.00 | $30,000 | $1,000.00 |
| 25 | (553.04010109) | LS | 1 | $1.00 | $55,000 | $23,000 | $54,000 | $25,000 |
| 26 | Concrete for Structures, Performance (555.0021) | CY | 179 | $1,600.00 | $1,850.00 | $1,700.00 | $1,582.00 | $1,650.00 |
| 27 | Performance Concrete Quality Adjustment – Concrete for Structures (555.9902) | QUALITY UNIT | 1 | $7.50 | $7.50 | $7.50 | $7.50 | $7.50 |
| 28 | Epoxy-Coated Bar Reinforcement for Structures (556.0202) | LB | 24,771 | $3.00 | $2.50 | $2.00 | $2.25 | $2.00 |
| 29 | Stud Shear Connectors for Bridges (556.03) | EACH | 2,580 | $25.00 | $9.00 | $12.00 | $11.20 | $10.00 |
| 30 | (557.1012) | SY | 273 | $500.00 | $500.00 | $580.00 | $654.00 | $605.00 |
| 31 | (557.1112) | SY | 1,200 | $500.00 | $685.00 | $670.00 | $585.00 | $665.00 |
| 32 | (557.25000016) | 367 | $15.00 | $6.00 | $14.00 | $20.40 | $8.50 | |
| 33 | Winter Surface Treatment – Superstructure Slabs and Structural Approach Slabs (557.29) | SY | 1,391 | $0.01 | $1.00 | $0.01 | $11.70 | $1.00 |
| 34 | (557.60010004) | 1,390 | $15.00 | $23.00 | $22.00 | $16.00 | $21.50 | |
| 35 | Performance Concrete Quality Adjustment – Superstructure and Approach Slab (557.9901) | QUALITY UNIT | 1 | $8.86 | $8.86 | $8.86 | $8.86 | $8.86 |
| 36 | Longitudinal Sawcut Grooving of Structural Slab Surface (558.02) | SY | 1,391 | $10.00 | $12.00 | $14.00 | $7.30 | $11.50 |
| 37 | Protective Sealing of Structural Concrete on New Bridge Decks and Bridge Deck Overlays (559.01) | SF | 18,767 | $0.50 | $1.30 | $0.55 | $1.00 | $0.55 |
| 38 | Protective Sealing of New Structural Concrete (559.02) | SF | 7,181 | $0.55 | $1.30 | $1.50 | $1.40 | $0.55 |
| 39 | Protective Sealing of Existing Structural Concrete and Existing Bridge Decks (559.03) | SF | 7,288 | $0.55 | $1.30 | $1.50 | $1.40 | $1.55 |
| 40 | Type E.B. Fixed Bearing (112 to 168 k) (565.2023) | EACH | 9 | $2,000.00 | $2,500.00 | $3,000.00 | $2,109.00 | $4,935.00 |
| 41 | Type E.B. Expansion Bearing (112 to 168 k) (565.2033) | EACH | 27 | $2,000.00 | $1,800.00 | $3,000.00 | $1,959.00 | $4,045.00 |
| 42 | Armorless Bridge Joint (567.60) | LF | 85 | $240.00 | $350.00 | $360.00 | $304.90 | $305.00 |
| 43 | Transition Bridge Railing (568.70) | LF | 160 | $205.00 | $225.00 | $220.00 | $243.00 | $195.00 |
| 44 | Single Slope (Half-Section) Concrete Bridge Barrier (569.04) | LF | 322 | $225.00 | $250.00 | $240.00 | $273.40 | $225.00 |
| 45 | Performance Concrete Quality Adjustment–Cast-In-Place Concrete Barrier (569.99) | QUALITY UNIT | 1 | $7.61 | $7.61 | $7.61 | $7.61 | $7.61 |
| 46 | Lead-Exposure Control Plan (570.01) | LS | 1 | $3,000.00 | $1,500.00 | $3,000.00 | $3,383.00 | $100.00 |
| 47 | Medical Testing (570.02) | DOL | 3,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 48 | Personal-Exposure-Monitoring Sample Analysis (570.03) | DOL | 3,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 49 | Decontamination Facilities (570.04) | CALENDAR WEEK | 2 | $50.00 | $1,500.00 | $50.00 | $56.40 | $1,000.00 |
| 50 | (570.10) | LS | 1 | $1,200.00 | $2,500.00 | $2,200.00 | $1,494.00 | $100.00 |
| 51 | Disposal of Hazardous Paint Removal Waste Containing Lead (571.03) | LB | 370 | $5.00 | $9.00 | $6.00 | $5.65 | $1.00 |
| 52 | (574.030001) | SF | 2,087 | $40.00 | $20.00 | $65.00 | $45.20 | $10.00 |
| 53 | Scuppers (Type B) (576.02) | EACH | 2 | $3,500.00 | $3,700.00 | $2,500.00 | $5,348.00 | $3,865.00 |
| 54 | Removal of Structural Concrete (580.01) | CY | 146 | $1,500.00 | $1,900.00 | $1,800.00 | $2,474.00 | $3,835.00 |
| 55 | Removal and Replacement of Structural Concrete (582.0051) | CY | 7 | $10,000 | $6,800.00 | $9,200.00 | $6,766.00 | $10,500 |
| 56 | (585.01) | EACH | 18 | $5,000.00 | $4,000.00 | $6,000.00 | $5,603.00 | $9,405.00 |
| 57 | (585.02) | EACH | 18 | $5,000.00 | $4,200.00 | $7,000.00 | $5,888.00 | $14,005 |
| 58 | Drilling and Grouting Bolts or Reinforcing Bars (586.0201) | EACH | 1,009 | $82.00 | $37.00 | $37.00 | $63.10 | $55.00 |
| 59 | Drilling and Grouting Bolts or Reinforcing Bars with Pullout Test (586.0301) | EACH | 776 | $110.00 | $83.00 | $43.00 | $69.55 | $65.00 |
| 60 | (589.010001) | LB | 15 | $300.00 | $275.00 | $250.00 | $476.10 | $10.00 |
| 61 | (589.010002) | LB | 15,888 | $10.00 | $1.00 | $2.00 | $0.95 | $1.50 |
| 62 | (589.520001) | EACH | 36 | $1,000.00 | $600.00 | $600.00 | $338.90 | $750.00 |
| 63 | Box Beam Guide Railing (606.10) | LF | 125 | $50.00 | $55.00 | $60.00 | $56.50 | $55.00 |
| 64 | Box Beam Guide Railing (Shop Bent or Shop Mitered) (606.100002) | LF | 93 | $60.00 | $66.00 | $70.00 | $67.80 | $65.00 |
| 65 | Box Beam Median Barrier (606.11) | LF | 301 | $70.00 | $72.00 | $80.00 | $73.45 | $75.00 |
| 66 | (606.11000016) | 190 | $160.00 | $100.00 | $145.00 | $101.70 | $115.00 | |
| 67 | Box Beam End Piece (606.120101) | EACH | 2 | $750.00 | $1,000.00 | $800.00 | $1,017.00 | $695.00 |
| 68 | Box Beam Median Barrier End Assembly, Type C (606.1403) | EACH | 2 | $8,750.00 | $9,100.00 | $8,000.00 | $9,266.00 | $6,655.00 |
| 69 | Removing and Disposing Box Beam Guide Railing (606.73) | LF | 352 | $6.00 | $10.00 | $6.00 | $3.00 | $10.00 |
| 70 | Removing and Disposing Box Beam Median Barrier (606.74) | LF | 320 | $6.00 | $11.00 | $6.00 | $32.00 | $10.00 |
| 71 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 17 | $240.00 | $305.00 | $250.00 | $240.00 | $195.00 |
| 72 | Stone Curb – Bridge (Type A) (609.0301) | LF | 60 | $230.00 | $200.00 | $260.00 | $307.00 | $305.00 |
| 73 | Optional Curb (Precast Concrete Type PM4 or Cast-In-Place Concrete Type M4 or Stone Type MT) (609.0902) | LF | 570 | $50.00 | $40.00 | $40.00 | $96.00 | $45.00 |
| 74 | Weed Removal (610.13) | SY | 1,769 | $0.50 | $0.65 | $6.00 | $0.60 | $1.00 |
| 75 | Topsoil – Reuse On-Site Materials (610.1401) | CY | 125 | $35.00 | $95.00 | $24.00 | $53.70 | $10.00 |
| 76 | Topsoil - Roadside (610.1402) | CY | 162 | $85.00 | $110.00 | $64.00 | $151.20 | $15.00 |
| 77 | (610.16090824) | 1,121 | $2.00 | $2.50 | $2.60 | $2.30 | $2.50 | |
| 78 | (610.16092124) | 648 | $3.00 | $3.50 | $4.20 | $3.40 | $4.00 | |
| 79 | Watering Vegetation (610.19) | 1,000 GALLONS | 81 | $10.00 | $12.00 | $50.00 | $11.30 | $50.00 |
| 80 | (611.0132) | EACH | 3 | $750.00 | $850.00 | $600.00 | $847.50 | $600.00 |
| 81 | (611.0711) | EACH | 50 | $50.00 | $60.00 | $20.00 | $56.50 | $20.00 |
| 82 | (611.19010024) | 3 | $20.00 | $25.00 | $100.00 | $22.60 | $100.00 | |
| 83 | (616.08000024) | 249 | $20.00 | $25.00 | $15.00 | $22.60 | $15.00 | |
| 84 | (617.01010024) | 524 | $2.00 | $3.00 | $3.00 | $2.30 | $5.00 | |
| 85 | (617.10000024) | 392 | $25.00 | $120.00 | $50.00 | $55.55 | $1.00 | |
| 86 | (617.11000024) | LS | 1 | $5,000.00 | $4,000.00 | $3,000.00 | $2,858.00 | $100.00 |
| 87 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $250,000 | $250,000 | $120,000 | $500,000 | $450,000 |
| 88 | Type III Construction Barricades (619.04) | EACH | 69 | $350.00 | $195.00 | $180.00 | $69.00 | $150.00 |
| 89 | Cover Existing Pavement Marking Stripes (Removable Tape) (619.0803) | LF | 8,706 | $6.00 | $4.25 | $4.00 | $4.25 | $4.00 |
| 90 | (619.100102) | LF | 27,163 | $0.10 | $0.85 | $0.90 | $1.00 | $0.75 |
| 91 | (619.110511) | EACH | 2 | $10,000 | $18,000 | $15,000 | $13,000 | $20,000 |
| 92 | Temporary Positive Barrier – Category 5 (Pinning Prohibited) (619.1715) | LF | 3,160 | $25.00 | $41.00 | $30.00 | $45.50 | $35.00 |
| 93 | Temporary Positive Barrier – Category 6 (Pinning Required) (619.1716) | LF | 2,260 | $40.00 | $39.00 | $34.00 | $70.25 | $35.00 |
| 94 | Temporary Impact Attenuator - Redirective (Test Level 3) (619.1803) | EACH | 4 | $10,000 | $16,000 | $6,500.00 | $8,000.00 | $2,755.00 |
| 95 | Interim Tubular Markers (619.20) | EACH | 14 | $50.00 | $120.00 | $140.00 | $90.00 | $75.00 |
| 96 | Stone Filling (Light) (620.03) | CY | 21 | $115.00 | $175.00 | $130.00 | $188.00 | $115.00 |
| 97 | Bedding Material, Type 1 (620.0801) | CY | 21 | $105.00 | $160.00 | $120.00 | $111.00 | $135.00 |
| 98 | Survey Operations (625.01) | LS | 1 | $25,000 | $25,000 | $45,000 | $80,000 | $50,000 |
| 99 | Permanent Survey Markers (625.06) | EACH | 2 | $3,000.00 | $750.00 | $2,400.00 | $3,590.00 | $3,500.00 |
| 100 | (627.50140008) | 1,616 | $10.00 | $4.00 | $6.00 | $6.50 | $1.00 | |
| 101 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $2,500.00 | $4,000.00 | $5,000.00 | $4,500.00 | $10,000 |
| 102 | Engineer’s Field Office – Type 2 (637.12) | MONTH | 18 | $2,500.00 | $2,200.00 | $2,400.00 | $2,500.00 | $4,000.00 |
| 103 | Office Technology and Supplies (637.34) | DOL | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 104 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 53 | $45.00 | $65.00 | $55.00 | $62.15 | $45.00 |
| 105 | Type A Sign Posts (645.81) | EACH | 17 | $200.00 | $300.00 | $280.00 | $293.80 | $205.00 |
| 106 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 13 | $50.00 | $70.00 | $51.00 | $67.80 | $100.00 |
| 107 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 8,131 | $1.25 | $1.50 | $1.40 | $1.45 | $1.25 |
| 108 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 3,450 | $1.25 | $1.50 | $1.40 | $1.45 | $1.25 |
| 109 | (691.04000020) | 40,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 110 | Field Change Payment (FCP) (697.03) | DOL | 194,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 111 | Asphalt Price Adjustment (698.04) | DOL | 1,132 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 112 | Fuel Price Adjustment (698.05) | DOL | 2,097 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 113 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 114 | Mobilization (699.040001) | LS | 1 | $165,001 | $175,163 | $176,000 | $190,018 | $200,030 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of January 22, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.