NYSDOT contract D265704 bid tabulation
PAVEMENT RESURFACING - Route I-87 - Mohawk River to Exit 11. Let by New York State DOT on February 5, 2026, Saratoga, Region 01. 4 bids received; low bid $18,707,797 by Kubricky-Jointa Lime LLC.
- Owner
- New York State DOT
- Letting
- 05 FEB 2026
- Pay items
- 89
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Kubricky-Jointa Lime LLC | $18,707,797 | Low |
| 2 | Rifenburg Construction Inc | $20,669,115 | +10% |
| 3 | Callanan Industries Inc | $22,867,178 | +22% |
| 4 | Peckham Road Corp | $23,157,461 | +24% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Kubricky-Jointa Lime LLC | 2. Rifenburg Construction Inc | 3. Callanan Industries Inc | 4. Peckham Road Corp |
|---|---|---|---|---|---|---|---|
| 1 | (203.24010017) | 4,460 | $31.46 | $31.00 | $60.00 | $10.00 | |
| 2 | (206.03120010) | 880 | $39.97 | $38.00 | $38.00 | $38.00 | |
| 3 | Pavement Density Quality Adjustment to Asphalt Items (404.0002) | QUALITY UNIT | 4,927 | $95.00 | $95.00 | $95.00 | $95.00 |
| 4 | Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003) | QUALITY UNIT | 1,797 | $95.00 | $95.00 | $95.00 | $95.00 |
| 5 | (404.0589) | TON | 111 | $716.20 | $248.00 | $800.00 | $585.00 |
| 6 | (404.0952) | TON | 98,530 | $98.48 | $95.00 | $112.00 | $127.50 |
| 7 | Straight Tack Coat (407.0103) | GAL | 49,420 | $3.37 | $3.00 | $7.00 | $2.20 |
| 8 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 386,263 | $0.36 | $0.70 | $0.60 | $0.78 |
| 9 | (490.17011018) | 823,651 | $1.53 | $2.40 | $3.00 | $3.28 | |
| 10 | Box Beam Guide Railing (606.10) | LF | 2,700 | $52.60 | $50.00 | $50.00 | $50.00 |
| 11 | Box Beam Guide Railing (Shop Bent or Shop Mitered) (606.100002) | LF | 252 | $68.38 | $65.00 | $65.00 | $65.00 |
| 12 | Box Beam Median Barrier (606.11) | LF | 714 | $73.64 | $70.00 | $70.00 | $70.00 |
| 13 | Box Beam Median Barrier (Shop Bent or Shop Mitered) (606.110002) | LF | 474 | $89.42 | $85.00 | $85.00 | $85.00 |
| 14 | Box Beam End Piece (606.120101) | EACH | 5 | $894.16 | $850.00 | $850.00 | $850.00 |
| 15 | Box Beam Guide Railing End Assembly Type I with 18 ft Extension (606.120103) | EACH | 2 | $5,680.53 | $5,400.00 | $5,400.00 | $5,400.00 |
| 16 | Box Beam Median Barrier End Assembly, Type A (606.1401) | EACH | 1 | $4,628.58 | $4,400.00 | $4,400.00 | $4,400.00 |
| 17 | Box Beam Median Barrier End Assembly, Type B (606.1402) | EACH | 1 | $3,997.41 | $3,800.00 | $3,800.00 | $3,800.00 |
| 18 | Box Beam Median Barrier End Assembly, Type C (606.1403) | EACH | 2 | $9,046.77 | $8,600.00 | $8,600.00 | $8,600.00 |
| 19 | Removing and Disposing Cable Guide Railing (606.70) | LF | 2,408 | $3.16 | $3.00 | $3.00 | $3.00 |
| 20 | Removing and Disposing Corrugated Beam Guide Railing (606.71) | LF | 996 | $3.16 | $3.00 | $3.00 | $3.00 |
| 21 | Removing and Disposing Corrugated Beam Median Barrier (606.72) | LF | 372 | $6.31 | $6.00 | $6.00 | $6.00 |
| 22 | Removing and Disposing Box Beam Median Barrier (606.74) | LF | 144 | $10.52 | $10.00 | $10.00 | $10.00 |
| 23 | Removing and Disposing Anchorage Units for Cable Guide railing or Median Barrier (606.79) | EACH | 10 | $315.59 | $300.00 | $300.00 | $300.00 |
| 24 | Removing and Disposing Anchorage Units for Corrugated Beam Guide Railing and Median Barrier (606.7910) | EACH | 2 | $315.59 | $300.00 | $300.00 | $300.00 |
| 25 | Removing and Disposing Box Beam Guide Rail Turned-Down Terminal (606.7920) | EACH | 4 | $84.16 | $80.00 | $80.00 | $80.00 |
| 26 | Removing and Disposing Box Beam Median Barrier End Assembly-Type C (606.7932) | EACH | 1 | $178.83 | $170.00 | $170.00 | $170.00 |
| 27 | (606.85020001) | 3 | $231.43 | $220.00 | $220.00 | $220.00 | |
| 28 | (608.01070415) | 216 | $50.68 | $99.00 | $100.00 | $150.55 | |
| 29 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $1,001,865 | $1,635,197 | $2,440,000 | $1,057,070 |
| 30 | Type III Construction Barricades (619.04) | EACH | 126 | $27.55 | $86.00 | $50.00 | $157.75 |
| 31 | (619.0901) | LF | 688,291 | $0.32 | $1.00 | $0.30 | $0.30 |
| 32 | (619.111213) | WEEK | 68 | $1,187.16 | $1,600.00 | $550.00 | $553.15 |
| 33 | Interim Tubular Markers (619.20) | EACH | 12 | $29.54 | $130.00 | $100.00 | $25.00 |
| 34 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $961,712 | $925,000 | $450,000 | $1,066,550 |
| 35 | Pavement Patching (Force Acount) (619.2601) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 36 | Pavement Patching (Tonnage) (619.2602) | TON | 88 | $480.45 | $498.00 | $389.58 | $177.75 |
| 37 | Survey Operations (625.01) | LS | 1 | $6,857.62 | $31,000 | $15,000 | $21,100 |
| 38 | (627.50140008) | 2,760 | $20.75 | $47.50 | $25.00 | $14.35 | |
| 39 | Removal and Repair of Deteriorated Asphalt Pavement - Less than or equal to 4 Square Yards (633.1401) | SY | 636 | $57.82 | $139.00 | $100.00 | $146.85 |
| 40 | Removal and Repair of Deteriorated Asphalt Pavement – Greater than 4 Square Yards and less than 20 Square Yards (633.1402) | SY | 348 | $53.85 | $111.50 | $90.00 | $135.30 |
| 41 | Removal and Repair of Deteriorated Asphalt Pavement – 20 Square Yards or Greater (633.1403) | SY | 116 | $74.68 | $111.50 | $90.00 | $135.30 |
| 42 | Removal and Repair of Loose, Broken, or Spalled PCC Pavement (633.15) | SY | 116 | $74.68 | $85.00 | $25.00 | $318.15 |
| 43 | Engineer’s Field Office – Type 2 (637.12) | MONTH | 19 | $1,900.00 | $4,500.00 | $3,500.00 | $2,850.00 |
| 44 | Office Technology and Supplies (637.34) | DOL | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 45 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 46 | (637.41000115) | 19 | $50.00 | $400.00 | $150.00 | $100.00 | |
| 47 | (637.41000215) | 19 | $50.00 | $400.00 | $150.00 | $100.00 | |
| 48 | (637.41000315) | 19 | $50.00 | $400.00 | $150.00 | $100.00 | |
| 49 | (637.41000415) | 19 | $50.00 | $400.00 | $150.00 | $100.00 | |
| 50 | (637.41000515) | 19 | $50.00 | $400.00 | $150.00 | $100.00 | |
| 51 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 267 | $38.92 | $37.00 | $37.00 | $37.00 |
| 52 | Ground-Mounted Sign Panels greater than 32 SF with Z-bars (645.5103) | SF | 4,952 | $36.82 | $35.00 | $35.00 | $35.00 |
| 53 | Type A Sign Posts (645.81) | EACH | 42 | $216.70 | $206.00 | $206.00 | $206.00 |
| 54 | (645.830302) | EACH | 4 | $3,366.24 | $3,200.00 | $3,200.00 | $3,200.00 |
| 55 | (645.830402) | EACH | 12 | $3,787.02 | $3,600.00 | $3,600.00 | $3,600.00 |
| 56 | (645.830502) | EACH | 10 | $4,523.39 | $4,300.00 | $4,300.00 | $4,300.00 |
| 57 | (645.830602) | EACH | 14 | $5,470.14 | $5,200.00 | $5,200.00 | $5,200.00 |
| 58 | (645.830702) | EACH | 15 | $7,363.65 | $7,000.00 | $7,000.00 | $7,000.00 |
| 59 | (645.830802) | EACH | 2 | $8,520.80 | $8,100.00 | $8,100.00 | $8,100.00 |
| 60 | Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23) | EACH | 46 | $28.40 | $27.00 | $27.00 | $27.00 |
| 61 | Steel Post, 2.0 lb/ft (646.32) | EACH | 17 | $68.38 | $65.00 | $65.00 | $65.00 |
| 62 | Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31) | EACH | 4 | $210.39 | $200.00 | $200.00 | $200.00 |
| 63 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 18 | $63.12 | $60.00 | $60.00 | $60.00 |
| 64 | Remove and Dispose Type B Ground Mounted Sign Support and Foundation (647.65) | EACH | 30 | $357.66 | $340.00 | $340.00 | $340.00 |
| 65 | (647.83001002) | 25 | $21.04 | $20.00 | $20.00 | $20.00 | |
| 66 | Milled-In Audible Roadway Delineators (MIARDs) (649.01) | LF | 236,934 | $0.13 | $0.35 | $0.20 | $0.14 |
| 67 | Pavement Ride Quality Adjustment to Asphalt Level 1 (653.1010) | QUALITY UNIT | 5,385 | $95.00 | $95.00 | $95.00 | $95.00 |
| 68 | (662.18200108) | LS | 1 | $4,944.17 | $4,700.00 | $4,700.00 | $4,700.00 |
| 69 | (680.05010007) | 2 | $27,982 | $26,600 | $26,600 | $26,600 | |
| 70 | (680.05020007) | 1 | $5,338.65 | $5,075.00 | $5,075.00 | $5,075.00 | |
| 71 | (680.51100010) | 5 | $289.29 | $275.00 | $275.00 | $275.00 | |
| 72 | (680.51300008) | 1 | $6,732.48 | $6,400.00 | $6,400.00 | $6,400.00 | |
| 73 | (680.520408) | LF | 880 | $90.47 | $86.00 | $86.00 | $86.00 |
| 74 | (680.77000105) | 1 | $946.76 | $900.00 | $900.00 | $900.00 | |
| 75 | (680.77000205) | 1 | $946.76 | $900.00 | $900.00 | $900.00 | |
| 76 | (680.77000305) | 1 | $946.76 | $900.00 | $900.00 | $900.00 | |
| 77 | (680.80324515) | 1 | $4,102.61 | $3,900.00 | $3,900.00 | $3,900.00 | |
| 78 | (680.80620103) | 2 | $4,602.28 | $4,375.00 | $4,375.00 | $4,375.00 | |
| 79 | (685.16010014) | 346,373 | $1.46 | $1.35 | $1.39 | $1.39 | |
| 80 | (685.17010014) | 205,306 | $1.46 | $1.35 | $1.39 | $1.39 | |
| 81 | White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104) | LF | 36,045 | $3.16 | $2.65 | $3.00 | $3.00 |
| 82 | White Epoxy Reflectorized Pavement Letters - 20 mil Portable/Hand Application (685.3304) | EACH | 108 | $78.90 | $75.00 | $75.00 | $75.00 |
| 83 | White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404) | EACH | 47 | $236.69 | $230.00 | $225.00 | $225.00 |
| 84 | (691.04000020) | 84,000 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 85 | Field Change Payment (FCP) (697.03) | DOL | 789,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 86 | Asphalt Price Adjustment (698.04) | DOL | 94,307 | $1.00 | $1.00 | $1.00 | $1.00 |
| 87 | Fuel Price Adjustment (698.05) | DOL | 20,862 | $1.00 | $1.00 | $1.00 | $1.00 |
| 88 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 89 | Mobilization (699.040001) | LS | 1 | $557,523 | $794,500 | $875,000 | $553,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of February 5, 2026. Compiled by Mirage Metrics.