NYSDOT contract D265793 bid tabulation
Replacement of Overhead Sign & Ground Mounted Signs. Let by New York State DOT on June 4, 2026, Cattaraugus, Erie, Niagara, Region 05. 3 bids received; low bid $1,254,756 by Elderlee Inc.
- Owner
- New York State DOT
- Letting
- 04 JUN 2026
- Pay items
- 41
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Elderlee Inc | $1,254,756 | Low |
| 2 | Cold Spring Construction Company | $1,350,127 | +8.0% |
| 3 | Union Concrete & Construction Corp | $1,405,918 | +12% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Elderlee Inc | 2. Cold Spring Construction Company | 3. Union Concrete & Construction Corp |
|---|---|---|---|---|---|---|
| 1 | Seed and Mulch – Temporary (209.1003) | SY | 50 | $18.00 | $13.00 | $3.00 |
| 2 | Resetting Box Beam Guide Railing (606.53) | LF | 60 | $12.00 | $100.00 | $35.00 |
| 3 | Removing and Storing Box Beam Guide Railing (606.63) | LF | 60 | $6.00 | $100.00 | $33.00 |
| 4 | Topsoil – Reuse On-Site Materials (610.1401) | CY | 15 | $50.00 | $85.00 | $175.00 |
| 5 | Turf Establishment - Roadside (610.1601) | SY | 50 | $18.00 | $13.00 | $5.00 |
| 6 | (617.11000024) | LS | 1 | $500.00 | $250.00 | $500.00 |
| 7 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $138,429 | $140,000 | $108,000 |
| 8 | (619.2401) | LS | 1 | $20,000 | $14,000 | $5,100.00 |
| 9 | Survey Operations (625.01) | LS | 1 | $16,330 | $10,000 | $25,000 |
| 10 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $1,500.00 | $300.00 | $2,700.00 |
| 11 | Engineer’s Field Office – Type 2 (637.12) | MONTH | 12 | $3,400.00 | $2,500.00 | $2,500.00 |
| 12 | Office Technology and Supplies (637.34) | DOL | 500 | $1.00 | $1.00 | $1.00 |
| 13 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 14 | Anchor Bolts (644.11) | LB | 1,474 | $9.50 | $12.00 | $14.00 |
| 15 | Drilled Shaft for Overhead Sign Structures (644.20) | CY | 43 | $4,000.00 | $3,250.00 | $5,600.00 |
| 16 | (644.421130) | EACH | 1 | $100,000 | $125,000 | $116,000 |
| 17 | (644.432560) | EACH | 1 | $160,000 | $175,000 | $159,000 |
| 18 | Performance Concrete Quality Adjustment (644.99) | QUALITY UNIT | 1 | $21.00 | $21.00 | $21.00 |
| 19 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 5,101 | $30.00 | $37.00 | $40.00 |
| 20 | Ground-Mounted Sign Panels greater than 32 SF with Z-bars (645.5103) | SF | 154 | $29.00 | $37.00 | $40.00 |
| 21 | Overhead Sign Panels (645.61) | SF | 697 | $31.00 | $62.00 | $40.00 |
| 22 | Type A Sign Posts (645.81) | EACH | 959 | $145.00 | $190.00 | $200.00 |
| 23 | (645.81090003) | 110 | $40.00 | $67.00 | $70.00 | |
| 24 | (645.830502) | EACH | 2 | $5,800.00 | $7,700.00 | $7,325.00 |
| 25 | Pole-Mounted Sign Support System (Band Mounting) (645.85) | EACH | 9 | $200.00 | $185.00 | $194.00 |
| 26 | Reference Marker Panel (646.21) | EACH | 208 | $30.00 | $38.00 | $40.00 |
| 27 | Steel Post, 2.0 lb/ft (646.32) | EACH | 208 | $60.00 | $78.00 | $81.00 |
| 28 | Removal of Cantilever Overhead Sign Panel(s), Structure, and Foundations (647.20) | EACH | 3 | $13,000 | $7,500.00 | $8,425.00 |
| 29 | Removal of Single Span Overhead Sign Panel(s), Structure, and Foundations (647.21) | EACH | 1 | $20,000 | $15,000 | $9,775.00 |
| 30 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 492 | $40.00 | $35.00 | $36.00 |
| 31 | (647.83001002) | 208 | $10.00 | $9.50 | $10.00 | |
| 32 | (670.75010005) | 1 | $978.00 | $260.00 | $275.00 | |
| 33 | Pole Excavation and Concrete Foundation (680.5001) | CY | 2 | $5,166.00 | $6,500.00 | $3,875.00 |
| 34 | (680.622041) | EACH | 1 | $26,820 | $25,000 | $28,000 |
| 35 | (680.8207) | EACH | 3 | $1,020.00 | $1,750.00 | $1,210.00 |
| 36 | Performance Concrete Quality Adjustment (680.99) | QUALITY UNIT | 1 | $14.50 | $14.50 | $14.50 |
| 37 | Field Change Payment (FCP) (697.03) | DOL | 63,000 | $1.00 | $1.00 | $1.00 |
| 38 | Asphalt Price Adjustment (698.04) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 39 | Fuel Price Adjustment (698.05) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 40 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 41 | Mobilization (699.040001) | LS | 1 | $47,000 | $51,000 | $53,500 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of June 4, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.