NYSDOT contract D265810 bid tabulation

NY 201 Pavement Resurfacing, Flyover to Harry L. Drive. Let by New York State DOT on August 27, 2026, Broome, Region 09. 3 bids received; low bid $9,897,897 by Bothar Construction LLC.

Owner
New York State DOT
Letting
27 AUG 2026
Pay items
91
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Bothar Construction LLC$9,897,897Low
2Barrett Paving Materials Inc$10,117,768+2.0%
3Lancaster Development and Tully Construction Co LLC$13,434,308+36%
NYSDOT contract D265810: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Bothar Construction LLC2. Barrett Paving Materials Inc3. Lancaster Development and Tully Construction Co LLC
1Unclassified Excavation and Disposal (203.02)CY1,610$64.00$180.00$117.00
2 (203.24010017)258$57.70$78.00$64.90
3Conduit Excavation and Backfill including Surface Restoration (206.03)LF48$70.15$61.00$85.40
4 (209.11010024)27$539.20$222.00$753.00
5 (304.00010018)56,647$1.55$0.85$1.15
6Pavement Density Quality Adjustment to Asphalt Items (404.0002)QUALITY UNIT1,682$100.00$100.00$100.00
7Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003)QUALITY UNIT1,682$100.00$100.00$100.00
8 (404.0589)TON1,331$173.90$232.00$295.00
9 (404.1989)TON1,063$193.70$229.00$283.00
10 (404.2589)TON1,771$159.70$183.00$229.00
11 (407.01040009)7,152$4.85$4.35$2.90
12Asphalt Pavement Joint Adhesive (418.7603)LF27,149$0.70$1.30$1.55
13 (421.09520109)4,183$207.20$191.50$268.00
14Miscellaneous Cold Milling of Bituminous Concrete (490.30)SY4,132$9.30$23.00$18.80
15Epoxy-Coated Bar Reinforcement for Structures (556.0202)LB234$24.05$14.00$9.85
16 (557.05013011)2,236$244.00$260.00$399.00
17Bridge Joint Seal (567.63)LF99$200.40$95.00$187.00
18 (568.75010001)5,872$88.90$77.32$112.00
19Reinforcing Bar Exposure (579.02)SF4,422$44.05$65.00$86.20
20Removal of Structural Concrete (580.01)CY23$8,072.00$2,600.00$13,000
21Drilling and Grouting Bolts or Reinforcing Bars (586.0201)EACH138$86.45$96.00$123.00
22 (604.070901)EACH27$1,792.00$2,600.00$5,790.00
23 (604.070902)EACH6$2,152.00$2,500.00$3,780.00
24Box Beam Guide Railing (606.10)LF881$68.95$59.93$86.10
25Box Beam Guide Railing with Extra Long Posts (Shop Bent or Shop Mitered) (606.100102)LF210$82.25$71.50$98.00
26Box Beam Median Barrier (606.11)LF1,582$98.55$85.69$119.00
27Box Beam Median Barrier (Shop Bent or Shop Mitered) (606.110002)LF115$113.65$98.83$136.00
28Box Beam End Piece (606.120101)EACH3$910.25$791.51$1,150.00
29Box Beam Guide Railing End Assembly Type I (606.120102)EACH1$6,142.80$5,341.56$8,080.00
30Box Beam Median Barrier End Assembly, Type B (606.1402)EACH2$2,999.85$2,608.54$2,800.00
31Removing and Disposing Box Beam Guide Railing (606.73)LF1,016$7.55$5.00$7.00
32Removing and Disposing Box Beam Median Barrier (606.74)LF1,721$8.90$6.00$8.40
33Removing and Disposing Box Beam Guide Rail Turned-Down Terminal (606.7920)EACH4$1,911.00$100.00$140.00
34Removing and Disposing Box Beam Median Barrier End Assembly-Type A (606.7930)EACH2$1,911.00$775.00$1,080.00
35Transition from Box Beam Guide Rail to Full-Section Single-Slope Concrete Barrier (One- or Two-Way Operation) (606.8806)EACH2$21,033$19,800$20,500
36 (607.06410016)665$122.55$110.00$149.00
37 (607.96000008)665$18.00$15.40$21.70
38 (608.01030009)4$3,500.00$3,500.00$4,200.00
39 (608.01040009)80,000$1.00$1.00$1.00
40Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102)TON115$359.00$580.00$550.00
41Turf Establishment – Performance (610.1605)SY860$30.90$28.00$55.80
42 (617.01010024)100$92.00$83.00$4.25
43 (617.10000024)1$643.70$2,300.00$676.00
44 (617.11000024)LS1$2,500.00$530.00$210.00
45Basic Work Zone Traffic Control (619.01)LS1$700,000$1,010,000$1,500,000
46 (619.0901)LF114,400$0.35$0.56$0.42
47 (619.111112)EACH12$12,245$9,400.00$20,400
48Nighttime Operations (Entire Project) (619.24)LS1$802,603$300,000$402,000
49Survey Operations (625.01)LS1$31,670$45,000$117,055
50 (627.50140008)2,401$7.75$9.50$15.70
51Cleaning Existing Pavement and/or Shoulder (633.11)SY49,516$0.65$1.00$0.93
52Removal and Repair of Loose, Broken, or Spalled PCC Pavement (633.15)SY4,716$90.40$107.00$105.00
53Stress Relieving Pavement Repairs (633.16)SY12,657$186.60$197.00$252.00
54Engineer’s Field Office – Type 2 (637.12)MONTH8$2,575.00$4,125.00$12,000
55Office Technology and Supplies (637.34)DOL1,000$1.00$1.00$1.00
56Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102)SF239$48.30$42.00$78.00
57Type A Sign Posts (645.81)EACH30$281.75$411.00$490.00
58High-Capacity Type A Sign Posts with Soil Plates Only (645.8106)EACH2$1,897.50$1,650.00$2,240.00
59 (645.81090003)4$97.75$85.00$112.00
60Reference Marker Panel (646.21)EACH20$46.00$40.00$70.00
61Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23)EACH28$20.70$18.00$42.00
62Steel Post, 2.0 lb/ft (646.32)EACH21$86.25$75.00$161.00
63Brackets for Barrier and Multidirectional Mounting (646.50)EACH14$120.75$105.00$175.00
64Remove and Dispose Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.51)EACH16$28.75$25.00$70.00
65Remove and Dispose Sign Panel, Sign Panel Assembly Size II (30-100 Square Feet) (647.52)EACH2$34.50$30.00$84.00
66 (647.83001002)32$23.00$20.00$14.00
67Pavement Ride Quality Adjustment to Asphalt Level 2 (653.1020)QUALITY UNIT160$125.00$125.00$125.00
68Telescoping Manhole Frame & Cover (655.1302)EACH4$1,773.00$3,200.00$2,960.00
69 (680.51010009)7$598.00$520.00$728.00
70 (680.51100010)7$525.55$457.00$640.00
71 (680.520203)LF48$18.40$16.00$22.40
72Inductance Loop Installation (680.54)LF1,158$23.30$20.25$28.30
73Shielded Lead-in Cable (680.71)LF370$4.00$3.45$4.85
74Inductance Loop Wire (680.72)LF3,058$1.15$1.00$1.40
75 (680.79300010)19$169.05$147.00$206.00
76Install Ball/Arrow LED Traffic Signal Module (680.810308)EACH21$54.05$47.00$65.80
77Traffic Signal Section - Polycarbonate, Type I, 12-inch (680.810601)EACH21$254.15$221.00$309.00
78Traffic Signal Bracket Assembly - 3 Way (680.8113)EACH1$2,725.50$2,370.00$3,320.00
79Traffic Signal Bracket Assembly - 4 Way (680.8114)EACH1$2,741.60$2,384.00$3,340.00
80 (680.83010005)370$8.85$7.70$10.80
81White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102)LF38,000$0.70$0.59$0.83
82Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202)LF19,200$0.70$0.59$0.83
83White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104)LF8,890$4.15$3.50$5.00
84White Epoxy Reflectorized Pavement Letters - 20 mil Portable/Hand Application (685.3304)EACH56$86.25$75.00$105.00
85White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404)EACH28$258.75$275.00$315.00
86 (691.04000020)37,000$1.00$1.00$1.00
87Field Change Payment (FCP) (697.03)DOL300,000$1.00$1.00$1.00
88Asphalt Price Adjustment (698.04)DOL1,345$1.00$1.00$1.00
89Fuel Price Adjustment (698.05)DOL100$1.00$1.00$1.00
90Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00$1.00
91Mobilization (699.040001)LS1$380,000$350,692$515,462
NYSDOT contract D265810: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of August 27, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy