NCDOT contract C205146 bid tabulation
MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 1 SECTION OF US-176, 2 SECTIONS OF US-25, 1 SECTION OF US-64, 1 SECTION OF NC-191 AND 13 SECTIONS OF SECONDARY ROADS. Let by North Carolina DOT on November 18, 2025, Henderson. 2 bids received; low bid $9,975,887 by Apac Atlantic Inc Asheville Division.
- Owner
- North Carolina DOT
- Letting
- 18 NOV 2025
- Pay items
- 42
- Data through
- 20 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Apac Atlantic Inc Asheville Division | $9,975,887 | Low |
| 2 | Rogers Group, Inc. | $13,140,532 | +32% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Apac Atlantic Inc Asheville Division | 2. Rogers Group, Inc. |
|---|---|---|---|---|---|
| 0001 | Mobilization (0000100000-N) | LS | 1 | $498,000 | $635,000 |
| 0002 | Shoulder reconstruction (1245000000-E) | SMI | 53.43 | $3,550.00 | $5,100.00 |
| 0003 | Aggregate shoulder borrow (1260000000-E) | TON | 8,036 | $31.50 | $38.00 |
| 0004 | Mill asp PVMT *****" DTH - (1-1/2") (1297000000-E) | SY | 172,709 | $2.50 | $2.50 |
| 0005 | Incidental milling (1330000000-E) | SY | 17,729 | $8.00 | $12.75 |
| 0006 | Asphalt conc surface course, type S9.5B (1519000000-E) | TON | 21,275 | $84.00 | $133.00 |
| 0007 | Asphalt conc surface course, type S9.5B (leveling course) (1520000000-E) | TON | 3,642 | $82.00 | $146.00 |
| 0008 | Asphalt conc surface course, type S9.5C (1523000000-E) | TON | 24,765 | $81.00 | $117.00 |
| 0009 | Asphalt binder for plant mix (1575000000-E) | TON | 3,297 | $775.00 | $650.00 |
| 0010 | Patching existing pavement (1704000000-E) | TON | 4,474 | $139.00 | $257.00 |
| 0011 | Generic paving item (LF) - centerline milled rumble strips (asphalt concrete), (18") (1881000000-E) | LF | 345 | $4.75 | $0.40 |
| 0012 | Generic paving item (LF) - sinusoidal milled rumble strips, (18") (1881000000-E) | LF | 8,340 | $0.19 | $0.40 |
| 0013 | Generic paving item (LF) - sinusoidal milled rumble strips, (8") (1881000000-E) | LF | 60,192 | $0.18 | $0.40 |
| 0014 | Remove and replace concrete curb ramps (2612500000-N) | EACH | 8 | $6,925.00 | $10,600 |
| 0015 | Adjustment of manholes (2830000000-N) | EACH | 29 | $1,500.00 | $1,630.00 |
| 0016 | Adjustment of meter boxes or valve boxes (2845000000-N) | EACH | 46 | $1,300.00 | $1,415.00 |
| 0017 | Work zone advance/general warning signing (4413000000-E) | SF | 2,869 | $7.50 | $7.00 |
| 0018 | Temporary traffic control (4457000000-N) | LS | 1 | $307,000 | $710,000 |
| 0019 | Tubular markers (fixed) (4520000000-N) | EACH | 30 | $75.00 | $250.00 |
| 0020 | Thermoplastic pavement marking lines (4", 90 mils) (4685000000-E) | LF | 83,764 | $0.42 | $0.50 |
| 0021 | Thermoplastic pavement marking lines (6", 90 mils) (4688000000-E) | LF | 148,504 | $0.60 | $0.75 |
| 0022 | Thermoplastic pavement marking lines (8", 90 mils) (4695000000-E) | LF | 750 | $5.00 | $3.30 |
| 0023 | Thermoplastic pavement marking lines (12", 90 mils) (4700000000-E) | LF | 50 | $10.37 | $5.30 |
| 0024 | Thermoplastic pavement marking lines (16", 90 mils) (4704000000-E) | LF | 100 | $15.00 | $6.95 |
| 0025 | Thermoplastic pavement marking lines (24", 90 mils) (4709000000-E) | LF | 1,994 | $9.00 | $10.00 |
| 0026 | Thermoplastic pavement marking character (90 mils) (4720000000-E) | EACH | 28 | $100.00 | $53.00 |
| 0027 | Thermoplastic pavement marking symbol (90 mils) (4725000000-E) | EACH | 241 | $125.00 | $107.00 |
| 0028 | Paint pavement marking lines (4") (4810000000-E) | LF | 27,521 | $0.15 | $0.30 |
| 0029 | Paint pavement marking lines (6") (4815000000-E) | LF | 32,744 | $0.21 | $0.40 |
| 0030 | Paint pavement marking lines (24") (4835000000-E) | LF | 1,477 | $8.50 | $1.60 |
| 0031 | Paint pavement marking symbol (4845000000-N) | EACH | 199 | $70.00 | $16.00 |
| 0032 | Generic pavement marking item (LF) - hot spray thermoplastic pavement marking lines, (24", 60 mils) (4890000000-E) | LF | 300 | $10.00 | $10.15 |
| 0033 | Generic pavement marking item (LF) - hot spray thermoplastic pavement marking lines, (4", 60 mils) (4890000000-E) | LF | 611,903 | $0.32 | $0.35 |
| 0034 | Generic pavement marking item (LF) - hot spray thermoplastic pavement marking lines, (8", 60 mils) (4890000000-E) | LF | 100 | $5.00 | $3.35 |
| 0035 | Generic pavement marking item (EA) - polycarbonate H-shaped markers (4895000000-N) | EACH | 2,566 | $50.00 | $58.75 |
| 0036 | Temporary silt fence (6000000000-E) | LF | 50 | $6.25 | $10.55 |
| 0037 | Safety fence (6029000000-E) | LF | 50 | $7.50 | $4.25 |
| 0038 | 1/4" hardware cloth (6042000000-E) | LF | 50 | $8.85 | $8.45 |
| 0039 | Seeding and mulching (6084000000-E) | ACRE | 0.25 | $6,300.00 | $19,000 |
| 0040 | Response for erosion control (6117000000-N) | EACH | 3 | $285.00 | $106.00 |
| 0041 | Inductive loop sawcut (7444000000-E) | LF | 6,432 | $19.00 | $20.50 |
| 0042 | Lead-in cable (14-2) (7456100000-E) | LF | 3,250 | $5.35 | $5.75 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NCDOT's tabulation for this contract. NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
Every contract let that day: NCDOT letting of November 18, 2025. Compiled by Mirage Metrics.