Thermoplastic pavement marking symbol (90 mils), NCDOT 4725000000-E

Low bidders on NCDOT contracts carried a median of $145.00 per EACH for this item, over the 24 months to 20 OCT 2026, across 150 low bids. Half of all 598 bids fell between $120.00 and $172.50.

Owner
North Carolina DOT
Item
4725000000-E
Unit
EACH
Data through
20 OCT 2026

NCDOT prints this item as “THERMO PVT SYMBOL 90MILS”.

$145.00Low bidder's median, per EACH
$145.00Median of all bids, per EACH
150Contracts in the window

By year of letting

Thermoplastic pavement marking symbol (90 mils), NCDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20139999$100.00389$100.00
20147979$110.00339$115.00
20158282$112.50307$125.00
20168989$120.00263$125.00
20175454$125.00189$150.00
20189898$135.65309$140.00
20194141$150.00137$165.00
20202929$130.00116$130.00
20217777$145.00254$145.00
20227070$175.00225$175.00
20236363$175.00238$175.00
20247069$140.00270$141.50
20257575$145.00275$147.33
20265858$125.00254$130.00

Bid prices as published, not adjusted for inflation.

By county

CountyLow bidsLow-bid medianAll bidsMedian, all bids
Wake16$115.2581$120.00
Mecklenburg8$114.2547$130.00
Randolph6$145.5038$150.00
Chatham5$125.0034$130.00
Forsyth6$168.0032$170.50
Wayne4$150.5026$150.50
Brunswick4$143.5017$140.00
Alamance4$145.1913$140.00
Moore3$172.5012$173.75
Cumberland3$130.0012$132.66
Guilford3$172.0012$168.50
Lee3$125.0011$125.00
Thermoplastic pavement marking symbol (90 mils), NCDOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Quantity (EACH)Low bidsLow-bid median
2 to 2837$168.00
29 to 6838$145.10
69 to 12937$140.00
133 to 47938$130.00
Thermoplastic pavement marking symbol (90 mils), NCDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

Thermoplastic pavement marking symbol (90 mils), NCDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
20 OCT 2026C205216Martin33$133.00$133.004Barnhill Contracting CompanyNCDOT
20 OCT 2026C204338Wake77$120.00$120.008Blythe Construction IncNCDOT
20 OCT 2026C205247Rowan197$105.00$105.002NJR Group IncNCDOT
20 OCT 2026C205236Union73$135.00$135.003Truerock Construction LLCNCDOT
20 OCT 2026C205246Polk6$650.00$655.264Rogers Group, Inc.NCDOT
15 SEP 2026C205206Onslow51$115.00$130.003Barnhill Contracting CompanyNCDOT
15 SEP 2026C205203Wayne4$500.00$950.006Legion Asphalt IncNCDOT
15 SEP 2026C205233Wake188$95.00$95.004Blythe Construction IncNCDOT
15 SEP 2026C204349Wake, Durham191$150.00$150.004Blythe Construction IncNCDOT
15 SEP 2026C205234Rockingham285$120.00$101.653Apac - Atlantic, Inc. Thompson Arthur DivisionNCDOT
15 SEP 2026C204990Randolph34$161.00$161.009Apac - Atlantic, Inc. Thompson Arthur DivisionNCDOT
15 SEP 2026C204947Caldwell81$167.00$174.003Branch Civil IncNCDOT
18 AUG 2026C205195Catawba42$199.41$155.754Blythe Development Co.NCDOT
18 AUG 2026C205219Rutherford119$225.00$225.001Wright Brothers Civil Construction LLCNCDOT
16 JUN 2026C205182Carteret69$150.00$150.002Barnhill Contracting CompanyNCDOT
Latest NCDOT contracts carrying Thermoplastic pavement marking symbol (90 mils)

Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.

How these prices were read

NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the NCDOT letting of 20 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy