NCDOT contract C205216 bid tabulation
GRADING, DRAINAGE, AND PAVING. US-17 FROM SR-1521 (MILL INN RD) TO SR-1119 (RALPH TAYLOR RD). Let by North Carolina DOT on October 20, 2026, Martin. 4 bids received; low bid $7,495,824 by Barnhill Contracting Company.
- Owner
- North Carolina DOT
- Letting
- 20 OCT 2026
- Pay items
- 154
- Data through
- 20 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Barnhill Contracting Company | $7,495,824 | Low |
| 2 | S T Wooten Corporation | $8,119,538 | +8.0% |
| 3 | FSC II LLC DBA Fred Smith Company | $8,282,828 | +10% |
| 4 | Branch Civil Inc | $9,485,000 | +27% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Barnhill Contracting Company | 2. S T Wooten Corporation | 3. FSC II LLC DBA Fred Smith Company | 4. Branch Civil Inc |
|---|---|---|---|---|---|---|---|
| 0001 | Mobilization (0000100000-N) | LS | 1 | $374,000 | $405,500 | $414,035 | $257,636 |
| 0002 | Construction surveying (0000400000-N) | LS | 1 | $300,000 | $150,000 | $78,172 | $88,847 |
| 0003 | Clearing & grubbing (0001000000-E) | LS | 1 | $150,000 | $100,000 | $545,545 | $42,537 |
| 0004 | Supplementary clearing & grubbing (0008000000-E) | ACRE | 1 | $1,000.00 | $1.00 | $1.00 | $27,775 |
| 0005 | Unclassified excavation (0022000000-E) | CY | 2,750 | $20.00 | $36.00 | $55.00 | $44.50 |
| 0006 | Undercut excavation (0036000000-E) | CY | 300 | $26.00 | $25.00 | $33.00 | $38.75 |
| 0007 | Borrow excavation (0106000000-E) | CY | 2,330 | $40.00 | $37.00 | $33.00 | $30.25 |
| 0008 | Drainage ditch excavation (0134000000-E) | CY | 380 | $20.00 | $15.00 | $35.00 | $29.75 |
| 0009 | Removal of existing asphalt pavement (0156000000-E) | SY | 710 | $15.00 | $22.60 | $40.00 | $27.50 |
| 0010 | Select granular material (0195000000-E) | CY | 300 | $40.00 | $37.00 | $33.00 | $49.50 |
| 0011 | Geotextile for soil stabilization (0196000000-E) | SY | 300 | $4.50 | $4.00 | $6.00 | $15.50 |
| 0012 | Temporary shoring (0199000000-E) | SF | 600 | $105.00 | $118.00 | $98.00 | $51.75 |
| 0013 | Foundation conditioning material, minor structures (0318000000-E) | TON | 650 | $70.00 | $60.00 | $62.00 | $112.75 |
| 0014 | FND condit geotextile (4A) (0321000000-E) | SY | 2,045 | $6.00 | $3.75 | $5.00 | $6.65 |
| 0015 | 15" side drain pipe (0343000000-E) | LF | 64 | $95.00 | $65.00 | $80.00 | $143.25 |
| 0016 | 18" side drain pipe (0344000000-E) | LF | 28 | $100.00 | $80.00 | $88.00 | $224.00 |
| 0017 | 15" RC pipe culverts, class III (0366000000-E) | LF | 24 | $90.00 | $85.00 | $76.00 | $194.75 |
| 0018 | 18" RC pipe culverts, class III (0372000000-E) | LF | 292 | $100.00 | $100.00 | $84.00 | $152.50 |
| 0019 | 42" RC pipe culverts, class III (0396000000-E) | LF | 36 | $295.00 | $265.00 | $230.00 | $485.50 |
| 0020 | 15" RC pipe culverts, class IV (0448200000-E) | LF | 188 | $95.00 | $90.00 | $82.00 | $198.25 |
| 0021 | 18" RC pipe culverts, class IV (0448300000-E) | LF | 2,352 | $105.00 | $110.00 | $90.00 | $172.00 |
| 0022 | 24" RC pipe culverts, class IV (0448400000-E) | LF | 492 | $145.00 | $145.00 | $115.00 | $247.00 |
| 0023 | 30" RC pipe culverts, class IV (0448500000-E) | LF | 1,328 | $185.00 | $185.00 | $190.00 | $361.75 |
| 0024 | 36" RC pipe culverts, class IV (0448600000-E) | LF | 1,120 | $245.00 | $240.00 | $240.00 | $372.75 |
| 0025 | 42" RC pipe culverts, class IV (0448700000-E) | LF | 204 | $310.00 | $295.00 | $275.00 | $747.75 |
| 0026 | **"WLD STL pipe grad B in soil - (36", 0.500") (0973100000-E) | LF | 72 | $655.00 | $1,380.00 | $1,850.00 | $2,044.00 |
| 0027 | **"WLD STL pipe grad B not in soil - (36", 0.500") (0973300000-E) | LF | 72 | $655.00 | $1.00 | $1.00 | $210.50 |
| 0028 | Pipe removal (0995000000-E) | LF | 3,646 | $55.00 | $35.00 | $20.00 | $91.50 |
| 0029 | Pipe clean out (0996000000-N) | EACH | 10 | $2,500.00 | $4,000.00 | $2,500.00 | $12,455 |
| 0030 | Fine grading (1011000000-N) | LS | 1 | $452,850 | $1,055,965 | $982,928 | $79,720 |
| 0031 | Aggregate base course (1121000000-E) | TON | 1,425 | $35.00 | $0.01 | $25.00 | $80.50 |
| 0032 | Incidental stone base (1220000000-E) | TON | 10 | $100.00 | $250.00 | $125.00 | $181.75 |
| 0033 | Mill asp PVMT *****" DTH - (1-1/2") (1297000000-E) | SY | 66,000 | $1.50 | $1.40 | $0.80 | $1.10 |
| 0034 | Incidental milling (1330000000-E) | SY | 6,500 | $6.50 | $4.95 | $9.00 | $5.85 |
| 0035 | Asphalt conc base course, type B25.0C (1491000000-E) | TON | 3,280 | $65.00 | $98.00 | $100.00 | $105.50 |
| 0036 | Asphalt conc intermediate course, type I19.0C (1503000000-E) | TON | 2,730 | $65.00 | $93.00 | $115.00 | $100.00 |
| 0037 | Asphalt conc surface course, type S9.5C (1523000000-E) | TON | 13,400 | $56.50 | $80.00 | $73.00 | $86.00 |
| 0038 | Asphalt binder for plant mix (1575000000-E) | TON | 1,070 | $800.00 | $550.00 | $800.00 | $590.00 |
| 0039 | Asphalt plant mix, pavement repair (1693000000-E) | TON | 551 | $120.00 | $205.00 | $205.00 | $527.50 |
| 0040 | Subdrain excavation (2022000000-E) | CY | 67 | $15.00 | $40.00 | $40.00 | $58.25 |
| 0041 | Geotextile for subsurface drains (2026000000-E) | SY | 200 | $3.00 | $12.00 | $12.00 | $17.25 |
| 0042 | Subdrain coarse aggregate (2036000000-E) | CY | 34 | $50.00 | $90.00 | $90.00 | $131.00 |
| 0043 | 6" perforated subdrain pipe (2044000000-E) | LF | 200 | $7.00 | $17.00 | $17.00 | $24.50 |
| 0044 | Subdrain pipe outlet (2070000000-N) | EACH | 1 | $250.00 | $400.00 | $400.00 | $583.50 |
| 0045 | 6" outlet pipe (2077000000-E) | LF | 6 | $15.00 | $40.00 | $40.00 | $58.25 |
| 0046 | Temporary steel plate covers for masonry drainage structure (2190000000-N) | EACH | 7 | $1,600.00 | $1,500.00 | $2,500.00 | $3,325.00 |
| 0047 | Endwalls (2209000000-E) | CY | 3.40 | $1,650.00 | $1,650.00 | $1,750.00 | $3,529.00 |
| 0048 | Pipe collars (2253000000-E) | CY | 0.45 | $9,900.00 | $2,000.00 | $5,500.00 | $10,535 |
| 0049 | Pipe plugs (2264000000-E) | CY | 1.58 | $5,200.00 | $2,000.00 | $2,250.00 | $10,075 |
| 0050 | Flowable fill (2275000000-E) | CY | 76 | $1,100.00 | $500.00 | $900.00 | $542.00 |
| 0051 | Masonry drainage structures (2286000000-N) | EACH | 68 | $4,500.00 | $4,000.00 | $4,000.00 | $9,307.00 |
| 0052 | Masonry drainage structures (2308000000-E) | LF | 40.80 | $500.00 | $525.00 | $500.00 | $698.00 |
| 0053 | Frame with two grates, STD 840.24 (2366000000-N) | EACH | 27 | $1,875.00 | $2,500.00 | $1,225.00 | $1,955.00 |
| 0054 | Frame with two grates, STD 840.29 (2367000000-N) | EACH | 36 | $1,905.00 | $1,150.00 | $1,240.00 | $1,998.00 |
| 0055 | Frame with cover, STD 840.54 (2396000000-N) | EACH | 3 | $1,135.00 | $1,000.00 | $1,075.00 | $1,795.00 |
| 0056 | Concrete transitional section for drop inlet (2451000000-N) | EACH | 33 | $2,520.00 | $2,520.00 | $1,550.00 | $1,198.00 |
| 0057 | Generic drainage item (EA) - masonary drainage structure repair (2473000000-N) | EACH | 2 | $1,500.00 | $2,500.00 | $2,750.00 | $10,758 |
| 0058 | 6" concrete driveway (2612000000-E) | SY | 50 | $164.00 | $164.00 | $100.00 | $110.75 |
| 0059 | 5" monolithic concrete islands (keyed in) (2655000000-E) | SY | 2,750 | $88.00 | $88.00 | $97.00 | $115.00 |
| 0060 | Adjustment of drop inlets (2815000000-N) | EACH | 1 | $2,265.00 | $1,500.00 | $1,000.00 | $1,825.80 |
| 0061 | Adjustment of manholes (2830000000-N) | EACH | 1 | $1,200.00 | $1,500.00 | $1,000.00 | $2,765.00 |
| 0062 | Impact attenuator units, type TL-3 (3001000000-N) | EACH | 1 | $28,465 | $28,465 | $32,500 | $32,762 |
| 0063 | Steel beam guardrail (3030000000-E) | LF | 1,275 | $27.41 | $27.41 | $27.41 | $31.50 |
| 0064 | Additional guardrail posts (3150000000-N) | EACH | 10 | $66.00 | $66.00 | $66.00 | $76.00 |
| 0065 | Guardrail end units, type cat-1 (3210000000-N) | EACH | 3 | $1,000.00 | $1,000.00 | $1,000.00 | $1,151.00 |
| 0066 | Guardrail end units, type TL-3 (3287000000-N) | EACH | 4 | $3,200.00 | $3,200.00 | $3,200.00 | $3,683.00 |
| 0067 | Guardrail anchor units, type B-77 (3317000000-N) | EACH | 4 | $2,630.00 | $2,630.00 | $2,630.00 | $3,027.00 |
| 0068 | Remove existing guardrail (3360000000-E) | LF | 1,364 | $1.00 | $1.00 | $1.00 | $1.25 |
| 0069 | Woven wire fence, 47" fabric (3503000000-E) | LF | 1,740 | $6.05 | $6.05 | $6.05 | $6.95 |
| 0070 | 4" timber fence posts, 7'-6" long (3509000000-E) | EACH | 102 | $44.00 | $44.00 | $44.00 | $50.75 |
| 0071 | 5" timber fence posts, 8'-0" long (3515000000-E) | EACH | 41 | $46.00 | $46.00 | $46.00 | $53.00 |
| 0072 | Rip rap, class I (3628000000-E) | TON | 75 | $92.00 | $110.00 | $110.00 | $164.75 |
| 0073 | Rip rap, class B (3649000000-E) | TON | 10 | $91.00 | $100.00 | $115.00 | $219.00 |
| 0074 | Geotextile for drainage (3656000000-E) | SY | 1,370 | $3.00 | $5.00 | $4.00 | $5.50 |
| 0075 | Contr furn, type ***sign - (D) (4025000000-E) | SF | 16 | $21.00 | $24.00 | $22.00 | $28.25 |
| 0076 | Contr furn, type ***sign - (E) (4025000000-E) | SF | 229 | $21.00 | $24.00 | $22.00 | $20.50 |
| 0077 | Contr furn, type ***sign - (F) (4025000000-E) | SF | 76 | $22.00 | $24.00 | $22.00 | $22.75 |
| 0078 | Supports, 3-LB steel U-channel (4072000000-E) | LF | 892 | $7.00 | $10.00 | $9.00 | $17.25 |
| 0079 | Sign erection, type D (4096000000-N) | EACH | 2 | $135.00 | $215.00 | $200.00 | $157.75 |
| 0080 | Sign erection, type E (4102000000-N) | EACH | 36 | $74.00 | $215.00 | $200.00 | $149.75 |
| 0081 | Sign erection, type F (4108000000-N) | EACH | 10 | $200.00 | $215.00 | $200.00 | $134.00 |
| 0082 | Disposal of sign system, U-channel (4155000000-N) | EACH | 46 | $5.00 | $55.00 | $50.00 | $47.25 |
| 0083 | Work zone signs (stationary) (4400000000-E) | SF | 80 | $80.00 | $8.75 | $30.00 | $11.75 |
| 0084 | Work zone signs (portable) (4405000000-E) | SF | 288 | $37.00 | $13.00 | $20.00 | $101.25 |
| 0085 | Work zone signs (barricade mounted) (4410000000-E) | SF | 216 | $24.00 | $8.70 | $8.15 | $76.75 |
| 0086 | Flashing arrow board (4415000000-N) | EACH | 1 | $10,000 | $15,000 | $12,500 | $12,530 |
| 0087 | Portable changeable message sign (4420000000-N) | EACH | 1 | $25,000 | $30,000 | $45,000 | $25,695 |
| 0088 | Drums (4430000000-N) | EACH | 650 | $80.00 | $60.00 | $20.00 | $5.15 |
| 0089 | Barricades (type III) (4445000000-E) | LF | 1,296 | $25.00 | $20.00 | $18.00 | $143.50 |
| 0090 | Flagger (4455000000-N) | DAY | 40 | $400.00 | $360.00 | $975.00 | $576.25 |
| 0091 | Temporary crash cushions (4465000000-N) | EACH | 3 | $8,000.00 | $8,000.00 | $5,950.00 | $9,979.00 |
| 0092 | TMA (4480000000-N) | EACH | 1 | $40,000 | $60,000 | $24,000 | $34,861 |
| 0093 | Portable concrete barrier (4485000000-E) | LF | 695 | $40.00 | $40.00 | $78.00 | $66.50 |
| 0094 | Portable concrete barrier (anchored) (4490000000-E) | LF | 240 | $65.00 | $65.00 | $75.00 | $113.00 |
| 0095 | Law enforcement (4510000000-N) | HR | 160 | $50.00 | $75.00 | $75.00 | $57.50 |
| 0096 | Temporary raised pavement markers (4650000000-N) | EACH | 506 | $10.00 | $10.00 | $10.00 | $12.25 |
| 0097 | Thermoplastic pavement marking lines (4", 90 mils) (4685000000-E) | LF | 3,056 | $0.80 | $0.80 | $0.80 | $1.00 |
| 0098 | Thermoplastic pavement marking lines (6", 90 mils) (4688000000-E) | LF | 44,083 | $0.85 | $0.85 | $0.85 | $1.05 |
| 0099 | Thermoplastic pavement marking lines (12", 90 mils) (4700000000-E) | LF | 5,015 | $4.00 | $4.00 | $4.00 | $4.95 |
| 0100 | Thermoplastic pavement marking lines (24", 90 mils) (4709000000-E) | LF | 83 | $12.00 | $12.00 | $12.00 | $14.75 |
| 0101 | Thermoplastic pavement marking symbol (90 mils) (4725000000-E) | EACH | 33 | $133.00 | $133.00 | $133.00 | $164.00 |
| 0102 | Paint pavement marking lines (4") (4810000000-E) | LF | 6,210 | $0.23 | $0.23 | $0.23 | $0.30 |
| 0103 | Paint pavement marking lines (6") (4815000000-E) | LF | 97,554 | $0.23 | $0.23 | $0.23 | $0.30 |
| 0104 | Paint pavement marking lines (12") (4825000000-E) | LF | 9,660 | $0.75 | $0.75 | $0.75 | $0.95 |
| 0105 | Paint pavement marking lines (24") (4835000000-E) | LF | 110 | $8.00 | $8.00 | $8.00 | $9.85 |
| 0106 | Paint pavement marking symbol (4845000000-N) | EACH | 70 | $73.00 | $73.00 | $73.00 | $90.00 |
| 0107 | Polyurea lines (**", *** mils) - (6", 30 mils) (4846000000-E) | LF | 704 | $5.00 | $5.00 | $5.00 | $6.15 |
| 0108 | Removal of pavement marking lines (4") (4850000000-E) | LF | 510 | $0.50 | $0.50 | $0.50 | $0.65 |
| 0109 | Removal of pavement marking lines (6") (4855000000-E) | LF | 8,485 | $0.50 | $0.50 | $0.50 | $0.65 |
| 0110 | Removal of pavement marking symbols & characters (4875000000-N) | EACH | 3 | $100.00 | $100.00 | $150.00 | $123.25 |
| 0111 | Generic pavement marking item (LF) - yield line thermoplastic pavement marking (24", 90 mils) (4890000000-E) | LF | 20 | $15.00 | $15.00 | $30.00 | $18.50 |
| 0112 | Generic pavement marking item (EA) - polycarbonate H-shaped markers (4895000000-N) | EACH | 498 | $49.00 | $49.00 | $49.00 | $60.50 |
| 0113 | Permanent raised pavement markers (4900000000-N) | EACH | 4 | $10.00 | $10.00 | $15.00 | $12.25 |
| 0114 | 6" water line (5325600000-E) | LF | 160 | $240.00 | $155.00 | $70.00 | $269.00 |
| 0115 | 8" water line (5325800000-E) | LF | 998 | $170.00 | $180.00 | $90.00 | $213.00 |
| 0116 | DI H2O pipe fittings (5329000000-E) | LB | 2,895 | $14.00 | $16.00 | $13.00 | $27.50 |
| 0117 | 6" valve (5540000000-E) | EACH | 1 | $3,025.00 | $2,600.00 | $3,250.00 | $3,980.00 |
| 0118 | 6" tapping sleeve & valve (5571600000-E) | EACH | 2 | $8,500.00 | $8,000.00 | $8,000.00 | $11,625 |
| 0119 | 8" tapping sleeve & valve (5571800000-E) | EACH | 8 | $9,850.00 | $10,000 | $10,000 | $13,502 |
| 0120 | 6" line stop (5678400000-E) | EACH | 2 | $13,500 | $20,000 | $9,000.00 | $14,096 |
| 0121 | 8" line stop (5678600000-E) | EACH | 8 | $14,750 | $22,000 | $10,000 | $16,283 |
| 0122 | Abandon 6" utility pipe (5800000000-E) | LF | 75 | $11.00 | $10.00 | $47.00 | $56.50 |
| 0123 | Abandon 8" utility pipe (5801000000-E) | LF | 822 | $12.00 | $15.00 | $33.00 | $31.50 |
| 0124 | Generic utility item (EA) - concrete cradle protection (5882000000-N) | EACH | 2 | $3,475.00 | $1,500.00 | $1,850.00 | $4,450.00 |
| 0125 | Temporary silt fence (6000000000-E) | LF | 4,760 | $2.99 | $2.99 | $3.00 | $3.20 |
| 0126 | Stone for erosion control, class A (6006000000-E) | TON | 1,220 | $50.00 | $55.00 | $15.00 | $69.75 |
| 0127 | Stone for erosion control, class B (6009000000-E) | TON | 505 | $50.00 | $55.00 | $50.00 | $78.25 |
| 0128 | Sediment control stone (6012000000-E) | TON | 1,480 | $40.00 | $50.00 | $25.00 | $78.25 |
| 0129 | Temporary mulching (6015000000-E) | ACRE | 5.50 | $1,275.00 | $1,275.00 | $1,700.00 | $2,310.00 |
| 0130 | Seed for temporary seeding (6018000000-E) | LB | 300 | $7.95 | $7.95 | $2.00 | $2.50 |
| 0131 | Fertilizer for temporary seeding (6021000000-E) | TON | 1.50 | $1,800.00 | $1,800.00 | $1,000.00 | $1,364.00 |
| 0132 | Temporary slope drains (6024000000-E) | LF | 200 | $40.00 | $25.00 | $25.00 | $58.75 |
| 0133 | Safety fence (6029000000-E) | LF | 320 | $3.50 | $3.50 | $3.00 | $2.45 |
| 0134 | Silt excavation (6030000000-E) | CY | 1,410 | $10.00 | $15.00 | $0.50 | $6.00 |
| 0135 | Matting for erosion control (6036000000-E) | SY | 6,325 | $1.79 | $1.79 | $1.70 | $2.50 |
| 0136 | Coir fiber mat (6037000000-E) | SY | 100 | $6.95 | $6.95 | $6.00 | $5.45 |
| 0137 | 1/4" hardware cloth (6042000000-E) | LF | 3,560 | $5.79 | $5.79 | $6.00 | $4.65 |
| 0138 | Flocculant (6071002000-E) | LB | 2,370 | $2.00 | $1.00 | $1.00 | $29.50 |
| 0139 | Coir fiber wattle (6071012000-E) | LF | 3,900 | $8.69 | $8.69 | $8.50 | $18.00 |
| 0140 | Seeding and mulching (6084000000-E) | ACRE | 6 | $2,675.00 | $2,675.00 | $2,800.00 | $6,182.00 |
| 0141 | Mowing (6087000000-E) | ACRE | 6 | $400.00 | $400.00 | $300.00 | $368.50 |
| 0142 | Seed for repair seeding (6090000000-E) | LB | 50 | $25.00 | $25.00 | $4.75 | $5.20 |
| 0143 | Fertilizer for repair seeding (6093000000-E) | TON | 0.25 | $1.00 | $1.00 | $1,100.00 | $1,364.00 |
| 0144 | Seed for supplemental seeding (6096000000-E) | LB | 100 | $7.00 | $7.00 | $4.75 | $6.20 |
| 0145 | Fertilizer topdressing (6108000000-E) | TON | 2.50 | $1,100.00 | $1,100.00 | $950.00 | $1,364.00 |
| 0146 | Specialized hand mowing (6114500000-N) | MHR | 10 | $95.00 | $95.00 | $200.00 | $93.75 |
| 0147 | Manual litter removal (6114800000-N) | MHR | 4 | $95.00 | $95.00 | $200.00 | $155.75 |
| 0148 | Litter disposal (6114900000-E) | TON | 3 | $100.00 | $100.00 | $200.00 | $996.50 |
| 0149 | Response for erosion control (6117000000-N) | EACH | 100 | $1.00 | $1.00 | $1.00 | $124.50 |
| 0150 | Concrete washout structure (6117500000-N) | EACH | 2 | $2,950.00 | $1,500.00 | $2,000.00 | $2,255.00 |
| 0151 | Generic erosion control item (EA) - fabric insert inlet protection cleanout (6132000000-N) | EACH | 408 | $100.00 | $75.00 | $45.00 | $110.75 |
| 0152 | Generic erosion control item (EA) - fabric insert inlet protection, type 1 (6132000000-N) | EACH | 136 | $100.00 | $150.00 | $45.00 | $255.25 |
| 0153 | Generic erosion control item (EA) - prefabricated concrete washout (6132000000-N) | EACH | 12 | $3,000.00 | $1,500.00 | $450.00 | $575.50 |
| 0154 | Generic erosion control item (SY) - permanent soil reinforcement mat, type 2 (6141000000-E) | SY | 80 | $6.75 | $6.75 | $10.00 | $8.80 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NCDOT's tabulation for this contract. NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
Every contract let that day: NCDOT letting of October 20, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.