6" perforated subdrain pipe, NCDOT 2044000000-E

Low bidders on NCDOT contracts carried a median of $17.00 per LF for this item, over the 24 months to 20 OCT 2026, across 108 low bids. Half of all 576 bids fell between $13.80 and $24.23.

Owner
North Carolina DOT
Item
2044000000-E
Unit
LF
Data through
20 OCT 2026

NCDOT prints this item as “6" PERF SUBDRN PIPE”.

$17.00Low bidder's median, per LF
$17.00Median of all bids, per LF
111Contracts in the window

By year of letting

6" perforated subdrain pipe, NCDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20136060$8.00306$8.00
20144646$8.88259$9.25
20153333$12.00211$11.30
20162928$8.00152$8.47
20172725$13.00158$11.00
20184342$11.00210$14.00
20192222$9.38107$11.00
2020108$8.5071$6.00
20215251$8.00272$7.28
20224846$13.46200$15.00
20234039$12.00183$17.60
20244140$16.00215$16.00
20255554$16.00288$17.05
20264644$17.00236$17.00

Bid prices as published, not adjusted for inflation.

By county

CountyLow bidsLow-bid medianAll bidsMedian, all bids
Mecklenburg6$18.6241$21.25
Wake6$13.2536$15.50
Forsyth6$15.6235$17.00
Wayne4$14.3826$17.00
Rockingham5$6.2524$17.00
Guilford4$15.5019$17.26
Cumberland4$16.0016$16.00
Henderson4$27.8012$27.72
Polk3$18.8411$20.32
6" perforated subdrain pipe, NCDOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Quantity (LF)Low bidsLow-bid median
50 to 20027$15.00
200 to 50027$17.00
500 to 1,20027$17.00
1,225 to 18,21027$17.00
6" perforated subdrain pipe, NCDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
Smith-Rowe, LLC13863 (46%)
FSC II LLC DBA Fred Smith Company11055 (50%)
Dane Construction, Inc.16837 (22%)
S T Wooten Corporation13232 (24%)
Barnhill Contracting Company8632 (37%)
Blythe Construction Inc11920 (17%)
6" perforated subdrain pipe, NCDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
20 OCT 2026C205216Martin200$7.00$17.004Barnhill Contracting CompanyNCDOT
20 OCT 2026C205207Pender200$5.00$5.005S T Wooten CorporationNCDOT
20 OCT 2026C204338Wake200$17.00$17.008Blythe Construction IncNCDOT
24 SEP 2026C205140New Hanover200$21.36$21.361Balfour Beatty Infrastructure IncNCDOT
15 SEP 2026C205206Onslow2,300$10.50$15.003Barnhill Contracting CompanyNCDOT
15 SEP 2026C205203Wayne200$17.00$17.626Legion Asphalt IncNCDOT
15 SEP 2026C204990Randolph500$34.77$21.259Apac - Atlantic, Inc. Thompson Arthur DivisionNCDOT
15 SEP 2026C205214Wilkes200$17.00$10.005James R Vannoy & Sons Construction Company IncNCDOT
15 SEP 2026C204947Caldwell900$13.00$17.003Branch Civil IncNCDOT
18 AUG 2026C205195Catawba1,000$15.00$16.124Blythe Development Co.NCDOT
18 AUG 2026C205205Robeson200$12.00$12.001Bmco Construction, Inc.NCDOT
18 AUG 2026C204504Watauga2,700$18.00$18.003Branch Civil IncNCDOT
18 AUG 2026C204877Rutherford200n/a$11.007R.E. Burns & Sons Co., Inc.NCDOT
18 AUG 2026C205219Rutherford500$16.05$16.051Wright Brothers Civil Construction LLCNCDOT
18 AUG 2026C205070Rutherford200n/a$20.328United Infrastructure Group IncNCDOT
Latest NCDOT contracts carrying 6" perforated subdrain pipe

Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.

How these prices were read

NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the NCDOT letting of 20 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy