NCDOT contract C205214 bid tabulation
GRADING, DRAINAGE, PAVING, AND STRUCTURE., GRADING, DRAINAGE, PAVING, SIGNALS, AND STRUCTURE. BRIDGE #960029 OVER CUB CREEK ON SR-1001 (OAKWOODS RD). Let by North Carolina DOT on September 15, 2026, Wilkes. 5 bids received; low bid $6,489,104 by James R Vannoy & Sons Construction Company Inc.
- Owner
- North Carolina DOT
- Letting
- 15 SEP 2026
- Pay items
- 202
- Data through
- 20 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | James R Vannoy & Sons Construction Company Inc | $6,489,104 | Low |
| 2 | Kemp Sigmon Construction Co Inc | $6,801,641 | +5.0% |
| 3 | Smith-Rowe, LLC | $6,814,189 | +5.0% |
| 4 | Tri-County Paving Inc | $7,709,179 | +19% |
| 5 | Caton Construction Group Inc | $8,512,074 | +31% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. James R Vannoy & Sons Construction Company Inc | 2. Kemp Sigmon Construction Co Inc | 3. Smith-Rowe, LLC | 4. Tri-County Paving Inc | 5. Caton Construction Group Inc |
|---|---|---|---|---|---|---|---|---|
| 0001 | Mobilization (0000100000-N) | LS | 1 | $375,000 | $345,000 | $340,700 | $450,000 | $425,000 |
| 0002 | Construction surveying (0000400000-N) | LS | 1 | $80,900 | $50,000 | $35,300 | $54,000 | $40,255 |
| 0003 | Sealing abandoned wells (0015000000-N) | EACH | 1 | $5,200.00 | $5,000.00 | $4,025.00 | $2,500.00 | $2,628.60 |
| 0004 | Supplementary clearing & grubbing (0050000000-E) | ACRE | 1 | $21,600 | $100.00 | $1.00 | $1.00 | $22,000 |
| 0005 | Undercut excavation (0057000000-E) | CY | 450 | $22.50 | $10.00 | $26.40 | $10.00 | $50.48 |
| 0006 | Grading (0063000000-N) | LS | 1 | $430,000 | $1,050,000 | $944,091 | $900,000 | $342,477 |
| 0007 | Borrow excavation (0106000000-E) | CY | 16,000 | $0.01 | $22.00 | $0.01 | $25.00 | $27.25 |
| 0008 | Drainage ditch excavation (0134000000-E) | CY | 145 | $8.50 | $20.00 | $19.40 | $8.00 | $7.40 |
| 0009 | Select granular material (0195000000-E) | CY | 400 | $69.00 | $10.00 | $0.01 | $80.00 | $148.46 |
| 0010 | Geotextile for soil stabilization (0196000000-E) | SY | 600 | $3.25 | $4.00 | $5.40 | $5.00 | $10.58 |
| 0011 | Temporary shoring (0199000000-E) | SF | 1,403 | $55.00 | $75.00 | $48.21 | $45.00 | $51.06 |
| 0012 | Generic grading item (LS) - type 1 bridge approach fill, station 20+60.00 -L- (0248000000-N) | LS | 1 | $32,200 | $30,000 | $35,830 | $40,000 | $77,026 |
| 0013 | Foundation conditioning material, minor structures (0318000000-E) | TON | 360 | $58.00 | $20.00 | $30.00 | $60.00 | $96.25 |
| 0014 | FND condit geotextile (4A) (0321000000-E) | SY | 1,135 | $5.00 | $2.00 | $2.00 | $5.00 | $11.34 |
| 0015 | 15" drainage pipe (0335200000-E) | LF | 76 | $65.00 | $95.00 | $92.86 | $35.00 | $130.06 |
| 0016 | 18" drainage pipe (0335300000-E) | LF | 120 | $62.00 | $100.00 | $103.18 | $38.00 | $152.35 |
| 0017 | 30" drainage pipe (0335500000-E) | LF | 44 | $102.00 | $175.00 | $165.16 | $45.00 | $279.12 |
| 0018 | **" drainage pipe elbow - (15") (0335850000-E) | EACH | 4 | $430.00 | $750.00 | $100.00 | $150.00 | $1,898.07 |
| 0019 | 15" RC pipe culverts, class IV (0448200000-E) | LF | 780 | $77.00 | $95.00 | $110.22 | $84.74 | $154.80 |
| 0020 | 18" RC pipe culverts, class IV (0448300000-E) | LF | 700 | $82.00 | $110.00 | $109.38 | $111.07 | $180.44 |
| 0021 | 24" RC pipe culverts, class IV (0448400000-E) | LF | 52 | $111.00 | $135.00 | $309.16 | $155.00 | $261.53 |
| 0022 | Pipe removal (0995000000-E) | LF | 659 | $46.00 | $10.00 | $31.26 | $10.00 | $101.00 |
| 0023 | Shallow undercut (1099500000-E) | CY | 100 | $35.50 | $20.00 | $26.90 | $10.00 | $37.00 |
| 0024 | Class IV subgrade stabilization (1099700000-E) | TON | 200 | $46.50 | $35.00 | $50.70 | $55.00 | $128.46 |
| 0025 | Geotextile for subgrade stabilization (1112000000-E) | SY | 300 | $3.75 | $4.00 | $6.50 | $5.00 | $18.54 |
| 0026 | Aggregate base course (1121000000-E) | TON | 220 | $48.50 | $50.00 | $52.80 | $45.00 | $140.30 |
| 0027 | Incidental stone base (1220000000-E) | TON | 100 | $51.00 | $125.00 | $86.70 | $53.50 | $140.32 |
| 0028 | Mill asp PVMT *****" DTH - (1-1/2") (1297000000-E) | SY | 1,550 | $9.50 | $9.00 | $9.00 | $10.00 | $9.09 |
| 0029 | Incidental milling (1330000000-E) | SY | 950 | $9.50 | $9.00 | $9.00 | $10.00 | $9.09 |
| 0030 | Asphalt conc base course, type B25.0C (1491000000-E) | TON | 1,400 | $92.00 | $85.50 | $85.50 | $95.00 | $86.36 |
| 0031 | Asphalt conc intermediate course, type I19.0C (1503000000-E) | TON | 1,150 | $92.00 | $85.50 | $85.50 | $95.00 | $86.36 |
| 0032 | Asphalt conc surface course, type S9.5C (1523000000-E) | TON | 1,350 | $92.00 | $85.50 | $85.50 | $91.06 | $86.36 |
| 0033 | Asphalt binder for plant mix (1575000000-E) | TON | 200 | $970.00 | $900.00 | $900.00 | $965.63 | $909.09 |
| 0034 | Asphalt plant mix, pavement repair (1693000000-E) | TON | 170 | $243.00 | $225.00 | $255.00 | $250.00 | $252.53 |
| 0035 | Right-of-way markers (2000000000-N) | EACH | 24 | $270.00 | $300.00 | $275.00 | $302.50 | $275.00 |
| 0036 | Subdrain excavation (2022000000-E) | CY | 44.80 | $34.50 | $20.00 | $28.25 | $10.00 | $133.33 |
| 0037 | Geotextile for subsurface drains (2026000000-E) | SY | 200 | $6.00 | $2.00 | $4.40 | $5.00 | $18.54 |
| 0038 | Subdrain coarse aggregate (2036000000-E) | CY | 33.60 | $34.50 | $85.00 | $103.75 | $90.00 | $247.88 |
| 0039 | 6" perforated subdrain pipe (2044000000-E) | LF | 200 | $17.00 | $10.00 | $6.30 | $10.00 | $76.87 |
| 0040 | Subdrain pipe outlet (2070000000-N) | EACH | 1 | $350.00 | $500.00 | $555.00 | $471.29 | $4,198.40 |
| 0041 | 6" outlet pipe (2077000000-E) | LF | 6 | $20.00 | $60.00 | $65.80 | $50.00 | $193.20 |
| 0042 | Masonry drainage structures (2286000000-N) | EACH | 29 | $2,490.00 | $2,500.00 | $4,240.09 | $2,800.00 | $5,497.00 |
| 0043 | Masonry drainage structures (2308000000-E) | LF | 6 | $368.00 | $300.00 | $619.52 | $300.00 | $1,255.98 |
| 0044 | Frame with two grates, STD 840.16 (2364000000-N) | EACH | 2 | $1,050.00 | $900.00 | $2,914.06 | $1,200.00 | $2,255.45 |
| 0045 | Frame with two grates, STD 840.24 (2366000000-N) | EACH | 7 | $1,000.00 | $900.00 | $2,800.12 | $1,200.00 | $2,137.50 |
| 0046 | Frame-GRT-HD 840.03 ** - (E) (2374000000-N) | EACH | 5 | $1,100.00 | $1,250.00 | $1,382.43 | $1,200.00 | $2,140.10 |
| 0047 | Frame-GRT-HD 840.03 ** - (F) (2374000000-N) | EACH | 8 | $1,140.00 | $1,250.00 | $1,382.43 | $1,200.00 | $2,430.59 |
| 0048 | Frame-GRT-HD 840.03 ** - (G) (2374000000-N) | EACH | 6 | $1,140.00 | $1,250.00 | $1,382.43 | $1,200.00 | $2,430.59 |
| 0049 | Frame with cover, STD 840.54 (2396000000-N) | EACH | 1 | $840.00 | $750.00 | $1,088.53 | $1,200.00 | $2,467.85 |
| 0050 | 2'-6" concrete curb & gutter (2549000000-E) | LF | 2,870 | $46.50 | $37.00 | $38.50 | $41.82 | $28.79 |
| 0051 | Modified concrete flume (2570000000-N) | EACH | 2 | $2,990.00 | $5,568.00 | $3,000.00 | $1,650.00 | $1,629.44 |
| 0052 | 4" concrete sidewalk (2591000000-E) | SY | 50 | $69.00 | $65.00 | $113.00 | $71.27 | $53.77 |
| 0053 | Concrete curb ramps (2605000000-N) | EACH | 6 | $4,150.00 | $2,650.00 | $4,203.20 | $3,500.00 | $2,715.74 |
| 0054 | 6" concrete driveway (2612000000-E) | SY | 120 | $111.00 | $107.00 | $156.85 | $89.10 | $83.10 |
| 0055 | Generic paving item (SY) - 4" concrete greenway (2738000000-E) | SY | 150 | $105.00 | $105.00 | $93.41 | $71.27 | $64.09 |
| 0056 | Generic paving item (SY) - 4" concrete multi-use path (2738000000-E) | SY | 1,510 | $78.00 | $88.00 | $93.41 | $71.27 | $53.77 |
| 0057 | Generic paving item (SY) - temporary concrete sidewalk (2738000000-E) | SY | 185 | $69.00 | $65.00 | $108.14 | $71.27 | $53.77 |
| 0058 | Adjustment of manholes (2830000000-N) | EACH | 5 | $1,300.00 | $1,200.00 | $2,972.15 | $1,485.00 | $3,110.82 |
| 0059 | Steel beam guardrail (3030000000-E) | LF | 250 | $30.00 | $26.00 | $25.50 | $28.60 | $28.04 |
| 0060 | Steel beam guardrail, shop curved (3045000000-E) | LF | 75 | $33.50 | $30.00 | $26.50 | $33.00 | $29.03 |
| 0061 | Additional guardrail posts (3150000000-N) | EACH | 5 | $61.00 | $11.00 | $1.00 | $11.10 | $83.53 |
| 0062 | Guardrail end units, type at-1 (3195000000-N) | EACH | 1 | $1,620.00 | $1,250.00 | $900.00 | $1,375.00 | $996.72 |
| 0063 | Guardrail anchor units, type III (3215000000-N) | EACH | 4 | $3,050.00 | $2,450.00 | $2,400.00 | $2,695.00 | $2,208.79 |
| 0064 | Guardrail end units, type TL-2 (3288000000-N) | EACH | 3 | $3,580.00 | $3,400.00 | $3,100.00 | $3,740.00 | $2,911.06 |
| 0065 | Generic guardrail item (LF) - wood rub rail (3420000000-E) | LF | 200 | $44.50 | $21.50 | $18.00 | $23.10 | $37.84 |
| 0066 | Generic fencing item (LF) - bicycle/pedestrian safety rail (3575000000-E) | LF | 610 | $268.00 | $240.00 | $285.00 | $264.00 | $252.93 |
| 0067 | Rip rap, class I (3628000000-E) | TON | 22 | $73.00 | $75.00 | $72.05 | $90.00 | $128.93 |
| 0068 | Rip rap, class II (3635000000-E) | TON | 366 | $92.00 | $75.00 | $75.85 | $80.00 | $109.80 |
| 0069 | Rip rap, class B (3649000000-E) | TON | 252 | $69.00 | $75.00 | $74.05 | $70.00 | $99.24 |
| 0070 | Geotextile for drainage (3656000000-E) | SY | 2,049 | $4.00 | $3.50 | $5.25 | $5.00 | $10.24 |
| 0071 | Supports, 3-LB steel U-channel (4072000000-E) | LF | 276 | $11.00 | $9.00 | $10.00 | $9.20 | $9.18 |
| 0072 | Sign erection, type D (4096000000-N) | EACH | 3 | $139.00 | $215.00 | $125.00 | $275.00 | $219.39 |
| 0073 | Sign erection, type E (4102000000-N) | EACH | 7 | $84.00 | $215.00 | $75.00 | $170.50 | $219.39 |
| 0074 | Sign erection, type F (4108000000-N) | EACH | 2 | $139.00 | $215.00 | $125.00 | $99.00 | $219.39 |
| 0075 | Sign erect, reloc ** GRD MTD - (E) (4116100000-N) | EACH | 2 | $84.00 | $250.00 | $75.00 | $203.50 | $255.10 |
| 0076 | Disposal of sign system, U-channel (4155000000-N) | EACH | 15 | $2.25 | $50.00 | $2.00 | $27.50 | $51.02 |
| 0077 | Disposal of support, U-channel (4192000000-N) | EACH | 3 | $2.25 | $50.00 | $2.00 | $27.50 | $51.02 |
| 0078 | Generic signing item (EA) - sign erection, relocate, logo trailblazer (4360000000-N) | EACH | 1 | $84.00 | $350.00 | $75.00 | $275.00 | $357.14 |
| 0079 | Work zone signs (stationary) (4400000000-E) | SF | 434 | $10.00 | $8.25 | $9.00 | $8.80 | $8.42 |
| 0080 | Work zone signs (portable) (4405000000-E) | SF | 96 | $35.50 | $10.00 | $38.91 | $26.40 | $10.20 |
| 0081 | Work zone signs (barricade mounted) (4410000000-E) | SF | 158 | $9.00 | $8.25 | $8.00 | $8.80 | $8.42 |
| 0082 | Portable changeable message sign (4420000000-N) | EACH | 4 | $11,600 | $3,750.00 | $9,050.00 | $16,170 | $3,826.53 |
| 0083 | Drums (4430000000-N) | EACH | 49 | $53.00 | $125.00 | $69.00 | $55.00 | $46.94 |
| 0084 | Cones (4435000000-N) | EACH | 35 | $46.50 | $30.00 | $60.00 | $50.00 | $26.53 |
| 0085 | Barricades (type III) (4445000000-E) | LF | 176 | $28.00 | $20.00 | $25.00 | $30.00 | $20.41 |
| 0086 | Pedestrian channelizing devices (4447000000-E) | LF | 1,473 | $122.00 | $23.50 | $25.00 | $41.80 | $23.98 |
| 0087 | Flagger (4455000000-N) | DAY | 72 | $301.00 | $350.00 | $675.00 | $500.00 | $790.82 |
| 0088 | Temporary crash cushions (4465000000-N) | EACH | 2 | $10,300 | $10,500 | $7,795.00 | $6,842.50 | $6,071.43 |
| 0089 | Portable concrete barrier (4485000000-E) | LF | 367 | $56.00 | $55.00 | $44.05 | $44.00 | $70.00 |
| 0090 | Water filled barrier (4507000000-E) | LF | 200 | $80.00 | $85.00 | $80.00 | $75.00 | $33.67 |
| 0091 | Law enforcement (4510000000-N) | HR | 40 | $86.00 | $100.00 | $96.45 | $80.00 | $100.00 |
| 0092 | Skinny drum (4516000000-N) | EACH | 15 | $46.50 | $89.93 | $1.00 | $100.00 | $70.00 |
| 0093 | Generic traffic control item (EA) - audible warning devices (4600000000-N) | EACH | 4 | $406.00 | $350.00 | $500.00 | $275.00 | $357.14 |
| 0094 | Generic traffic control item (EA) - pedestrian transport service (4600000000-N) | EACH | 30 | $108.00 | $300.00 | $105.00 | $10.00 | $500.00 |
| 0095 | Generic traffic control item (EA) - temporary curb ramps (4600000000-N) | EACH | 2 | $319.00 | $1,500.00 | $4,735.00 | $1,500.00 | $280.61 |
| 0096 | Temporary raised pavement markers (4650000000-N) | EACH | 39 | $17.00 | $14.50 | $15.00 | $15.95 | $15.00 |
| 0097 | 4" cold appl plstic lines type ** - (IV) (4770000000-E) | LF | 432 | $3.50 | $8.75 | $3.00 | $9.63 | $3.00 |
| 0098 | Paint pavement marking lines (4") (4810000000-E) | LF | 6,702 | $1.00 | $0.80 | $0.90 | $0.88 | $0.90 |
| 0099 | Paint pavement marking lines (8") (4820000000-E) | LF | 270 | $1.75 | $1.75 | $1.50 | $1.93 | $1.50 |
| 0100 | Paint pavement marking lines (24") (4835000000-E) | LF | 1,196 | $4.50 | $6.75 | $4.00 | $7.43 | $4.00 |
| 0101 | Paint pavement marking symbol (4845000000-N) | EACH | 8 | $97.00 | $115.00 | $85.00 | $126.50 | $85.00 |
| 0102 | Removal of pavement marking lines (4") (4850000000-E) | LF | 600 | $2.00 | $1.50 | $1.80 | $1.65 | $1.80 |
| 0103 | Generic PVMT marking item (LF) 1205 - integrated multipolymer pavement marking lines (24", 90 mils) (4891000000-E) | LF | 394 | $20.50 | $22.00 | $18.00 | $24.20 | $18.00 |
| 0104 | Generic PVMT marking item (LF) 1205 - integrated multipolymer pavement marking lines (4", 90 mils) (4891000000-E) | LF | 3,845 | $4.00 | $4.50 | $3.45 | $4.95 | $3.45 |
| 0105 | Generic PVMT marking item (EA) 1205 - integrated multipolymer pavement marking symbols (90 mils) (4892000000-N) | EACH | 4 | $229.00 | $500.00 | $200.00 | $550.00 | $200.00 |
| 0106 | Generic pavement marking item (EA) - polycarbonate H-shaped markers (4895000000-N) | EACH | 67 | $183.00 | $85.00 | $160.00 | $93.50 | $160.00 |
| 0107 | Permanent raised pavement markers (4900000000-N) | EACH | 4 | $115.00 | $50.00 | $100.00 | $55.00 | $100.00 |
| 0108 | 12" water line (5326200000-E) | LF | 632 | $140.00 | $175.00 | $242.58 | $140.80 | $255.00 |
| 0109 | DI H2O pipe fittings (5329000000-E) | LB | 2,335 | $11.00 | $18.00 | $18.33 | $11.00 | $16.54 |
| 0110 | 6" valve (5540000000-E) | EACH | 1 | $5,200.00 | $3,000.00 | $4,569.73 | $5,225.00 | $4,757.29 |
| 0111 | 12" valve (5558000000-E) | EACH | 6 | $10,500 | $7,000.00 | $9,304.69 | $10,500 | $11,567 |
| 0112 | Relocate fire hydrant (5672000000-N) | EACH | 1 | $3,840.00 | $3,000.00 | $4,863.64 | $3,850.00 | $11,716 |
| 0113 | Fire hydrant leg (5673000000-E) | LF | 17 | $252.00 | $120.00 | $90.46 | $253.00 | $302.82 |
| 0114 | 8" sanitary gravity sewer (5691300000-E) | LF | 957 | $95.00 | $120.00 | $299.69 | $95.70 | $101.00 |
| 0115 | Sanitary sewer clean-out (5768000000-N) | EACH | 3 | $1,370.00 | $2,500.00 | $2,250.75 | $1,375.00 | $1,151.57 |
| 0116 | Sewer service line (5768500000-E) | LF | 34 | $82.00 | $75.00 | $122.92 | $82.50 | $102.60 |
| 0117 | 4' dia utility manhole (5775000000-E) | EACH | 6 | $8,200.00 | $5,000.00 | $6,158.25 | $8,200.50 | $11,304 |
| 0118 | 5' dia utility manhole (5776000000-E) | EACH | 1 | $12,700 | $7,000.00 | $8,631.78 | $12,738 | $10,446 |
| 0119 | Utility manhole wall 4' dia (5781000000-E) | LF | 10.10 | $850.00 | $350.00 | $713.09 | $858.00 | $8,551.74 |
| 0120 | Utility manhole wall 5' dia (5782000000-E) | LF | 1.20 | $1,730.00 | $500.00 | $1,061.87 | $1,738.00 | $8,562.69 |
| 0121 | Abandon 8" utility pipe (5801000000-E) | LF | 941 | $25.00 | $15.00 | $27.22 | $25.30 | $30.13 |
| 0122 | Abandon 12" utility pipe (5804000000-E) | LF | 623 | $28.50 | $20.00 | $23.82 | $28.68 | $33.85 |
| 0123 | Abandon utility manhole (5816000000-N) | EACH | 3 | $2,740.00 | $4,000.00 | $2,148.82 | $2,750.00 | $4,908.32 |
| 0124 | Direct drill **" - (12") (5872600000-E) | LF | 190 | $1,640.00 | $350.00 | $1,081.59 | $1,815.00 | $441.00 |
| 0125 | Temporary silt fence (6000000000-E) | LF | 3,810 | $3.50 | $2.90 | $3.00 | $3.30 | $2.63 |
| 0126 | Stone for erosion control, class A (6006000000-E) | TON | 480 | $70.00 | $20.00 | $0.01 | $90.00 | $125.28 |
| 0127 | Stone for erosion control, class B (6009000000-E) | TON | 730 | $70.00 | $20.00 | $0.01 | $90.00 | $125.28 |
| 0128 | Sediment control stone (6012000000-E) | TON | 750 | $60.00 | $20.00 | $0.01 | $80.00 | $95.00 |
| 0129 | Temporary mulching (6015000000-E) | ACRE | 5 | $1,080.00 | $2,200.00 | $950.00 | $1,045.00 | $1,907.22 |
| 0130 | Seed for temporary seeding (6018000000-E) | LB | 400 | $2.25 | $2.00 | $2.00 | $2.20 | $2.06 |
| 0131 | Fertilizer for temporary seeding (6021000000-E) | TON | 2.50 | $1,140.00 | $400.00 | $1,000.00 | $1,100.00 | $1,125.77 |
| 0132 | Temporary slope drains (6024000000-E) | LF | 270 | $14.00 | $10.00 | $22.00 | $28.33 | $30.00 |
| 0133 | Safety fence (6029000000-E) | LF | 720 | $3.50 | $1.90 | $4.00 | $3.30 | $2.99 |
| 0134 | Silt excavation (6030000000-E) | CY | 2,290 | $19.00 | $1.00 | $0.01 | $10.00 | $10.00 |
| 0135 | Matting for erosion control (6036000000-E) | SY | 9,500 | $2.00 | $1.75 | $1.81 | $1.98 | $2.06 |
| 0136 | Coir fiber mat (6037000000-E) | SY | 250 | $5.50 | $6.25 | $5.00 | $5.50 | $4.49 |
| 0137 | 1/4" hardware cloth (6042000000-E) | LF | 1,040 | $4.00 | $6.00 | $3.25 | $3.50 | $3.87 |
| 0138 | Low permeability geotextile (6043000000-E) | SY | 100 | $4.25 | $10.00 | $18.50 | $3.00 | $17.08 |
| 0139 | Floating turbidity curtain (6048000000-E) | SY | 55 | $15.00 | $25.00 | $73.25 | $60.00 | $124.25 |
| 0140 | Special stilling basins (6070000000-N) | EACH | 6 | $455.00 | $500.00 | $710.00 | $150.00 | $1,833.98 |
| 0141 | Flocculant (6071002000-E) | LB | 135 | $1.25 | $8.00 | $1.00 | $2.00 | $24.48 |
| 0142 | Coir fiber wattle (6071012000-E) | LF | 90 | $18.00 | $14.00 | $25.00 | $16.50 | $14.95 |
| 0143 | Coir fiber baffle (6071030000-E) | LF | 260 | $18.00 | $6.50 | $15.00 | $16.50 | $8.81 |
| 0144 | **" skimmer - (1-1/2") (6071050000-E) | EACH | 1 | $990.00 | $2,000.00 | $1,435.00 | $1,200.00 | $4,512.52 |
| 0145 | **" skimmer - (2") (6071050000-E) | EACH | 1 | $1,010.00 | $2,500.00 | $1,605.00 | $1,400.00 | $4,914.33 |
| 0146 | Seeding and mulching (6084000000-E) | ACRE | 5 | $3,410.00 | $3,200.00 | $3,000.00 | $3,300.00 | $5,103.09 |
| 0147 | Mowing (6087000000-E) | ACRE | 2.50 | $114.00 | $175.00 | $100.00 | $110.00 | $304.12 |
| 0148 | Seed for repair seeding (6090000000-E) | LB | 50 | $2.25 | $6.00 | $2.00 | $2.20 | $4.28 |
| 0149 | Fertilizer for repair seeding (6093000000-E) | TON | 0.25 | $1,135.56 | $600.00 | $1,000.00 | $1,100.00 | $1,125.76 |
| 0150 | Seed for supplemental seeding (6096000000-E) | LB | 125 | $2.25 | $6.00 | $2.00 | $2.20 | $5.15 |
| 0151 | Fertilizer topdressing (6108000000-E) | TON | 3.75 | $1,140.00 | $600.00 | $1,000.00 | $1,100.00 | $1,125.77 |
| 0152 | Impervious dike (6111000000-E) | LF | 71 | $116.00 | $85.00 | $124.00 | $30.00 | $19.77 |
| 0153 | Specialized hand mowing (6114500000-N) | MHR | 10 | $142.00 | $55.00 | $125.00 | $137.50 | $77.32 |
| 0154 | Response for erosion control (6117000000-N) | EACH | 25 | $17.50 | $400.00 | $10.00 | $11.00 | $103.09 |
| 0155 | Concrete washout structure (6117500000-N) | EACH | 2 | $461.00 | $1,500.00 | $500.00 | $2,500.00 | $750.00 |
| 0156 | Reforestation (6123000000-E) | ACRE | 0.25 | $4,542.28 | $7,200.00 | $4,000.00 | $4,400.00 | $2,500.00 |
| 0157 | Generic erosion control item (EA) - fabric insert inlet protection cleanout (6132000000-N) | EACH | 105 | $378.00 | $150.00 | $25.00 | $126.18 | $100.00 |
| 0158 | Generic erosion control item (EA) - fabric insert inlet protection, type 1 (6132000000-N) | EACH | 35 | $378.00 | $250.00 | $100.00 | $203.39 | $250.00 |
| 0159 | Generic erosion control item (EA) - prefabricated concrete washout (6132000000-N) | EACH | 9 | $442.00 | $1,000.00 | $650.00 | $938.80 | $250.00 |
| 0160 | Pedestrian signal head (16", 1 section W/countdown) (7048500000-E) | EACH | 6 | $178.00 | $1,100.00 | $3,500.00 | $1,595.00 | $1,254.36 |
| 0161 | Signal cable (7060000000-E) | LF | 2,475 | $9.00 | $5.75 | $6.75 | $7.70 | $6.56 |
| 0162 | Vehicle signal head (12", 3 section) (7120000000-E) | EACH | 11 | $1,670.00 | $1,300.00 | $1,825.00 | $1,650.00 | $1,482.42 |
| 0163 | Vehicle signal head (12", 4 section) (7132000000-E) | EACH | 3 | $2,230.00 | $1,400.00 | $2,000.00 | $1,870.00 | $1,596.45 |
| 0164 | Messenger cable (3/8") (7264000000-E) | LF | 300 | $5.50 | $5.00 | $8.50 | $11.00 | $5.70 |
| 0165 | Unpaved trench (***********) - (2, 2") (7300000000-E) | LF | 50 | $56.00 | $22.00 | $175.00 | $55.00 | $25.09 |
| 0166 | Unpaved trench (***********) - (4, 2") (7300000000-E) | LF | 25 | $111.00 | $26.00 | $225.00 | $66.00 | $29.65 |
| 0167 | Junction box (standard size) (7324000000-N) | EACH | 3 | $1,220.00 | $650.00 | $1,000.00 | $1,100.00 | $741.21 |
| 0168 | Junction box (over-sized, heavy duty) (7348000000-N) | EACH | 1 | $1,890.00 | $1,300.00 | $2,500.00 | $1,650.00 | $1,482.42 |
| 0169 | Wood pole (7360000000-N) | EACH | 2 | $3,560.00 | $2,200.00 | $3,100.00 | $1,650.00 | $2,508.71 |
| 0170 | Guy assembly (7372000000-N) | EACH | 6 | $1,220.00 | $950.00 | $900.00 | $1,100.00 | $1,083.31 |
| 0171 | 2" riser with weatherhead (7420000000-E) | EACH | 5 | $1,450.00 | $975.00 | $1,200.00 | $1,375.00 | $1,111.81 |
| 0172 | Lead-in cable (14-2) (7456100000-E) | LF | 1,025 | $5.50 | $5.00 | $6.50 | $6.60 | $5.70 |
| 0173 | Sign for signals (7636000000-N) | EACH | 2 | $1,110.00 | $625.00 | $1,000.00 | $1,100.00 | $712.70 |
| 0174 | Type II pedestal with foundation (7642200000-N) | EACH | 4 | $5,600.00 | $5,800.00 | $3,200.00 | $5,500.00 | $6,613.87 |
| 0175 | Signal cabinet foundation (7684000000-N) | EACH | 1 | $3,900.00 | $2,500.00 | $2,100.00 | $2,750.00 | $2,850.81 |
| 0176 | Contlrs with CBNT (**************) - (2070LX, base mounted) (7696000000-N) | EACH | 1 | $46,000 | $27,950 | $23,000 | $33,000 | $31,872 |
| 0177 | Cabinet base extender (7901000000-N) | EACH | 1 | $970.00 | $800.00 | $1,100.00 | $880.00 | $912.26 |
| 0178 | Generic signal item (EA) - microwave vehicle detectors - multiple zones (approach) (7980000000-N) | EACH | 2 | $15,700 | $4,500.00 | $6,500.00 | $20,900 | $5,131.45 |
| 0179 | Generic signal item (EA) - microwave vehicle detectors - multiple zones (presence) (7980000000-N) | EACH | 2 | $17,100 | $4,500.00 | $6,500.00 | $20,900 | $5,131.45 |
| 0180 | Remv exist STRS ***** BRG (402) - (20+60.00 -L-) (8042000000-N) | LS | 1 | $98,500 | $150,000 | $96,155 | $105,771 | $90,457 |
| 0181 | Asbestos assessment (8065000000-N) | LS | 1 | $1,510.00 | $1,500.00 | $2,250.00 | $2,475.00 | $1,400.00 |
| 0182 | **'-**" dia drilld piers - (3'-6") (8108000000-E) | LF | 184 | $1,010.00 | $1,750.00 | $1,098.57 | $1,938.07 | $1,632.92 |
| 0183 | Permanent steel casing for 3'-6" dia drilled pier (8111400000-E) | LF | 44 | $287.00 | $285.00 | $371.59 | $432.28 | $266.00 |
| 0184 | Sid inspections (8113000000-N) | EACH | 4 | $1,080.00 | $1,500.00 | $1.00 | $1.00 | $1,000.00 |
| 0185 | SPT testing (8114000000-N) | EACH | 4 | $1,080.00 | $1,000.00 | $1.00 | $1.00 | $1,000.00 |
| 0186 | CSL testing (8115000000-N) | EACH | 1 | $2,700.00 | $1,500.00 | $3,400.00 | $2,502.50 | $22,389 |
| 0187 | Concrete wearing surface (8156000000-E) | SF | 7,845 | $23.50 | $30.00 | $22.69 | $24.96 | $27.98 |
| 0188 | Grooving bridge floors (8161000000-E) | SF | 6,825 | $1.25 | $1.25 | $1.56 | $1.72 | $1.04 |
| 0189 | Class A concrete (bridge) (8182000000-E) | CY | 127 | $1,450.00 | $1,500.00 | $1,985.15 | $1,642.28 | $2,226.58 |
| 0190 | BRG appr slab *********** - (20+60.00 -L-) (8210000000-N) | LS | 1 | $87,900 | $120,000 | $87,800 | $96,580 | $89,759 |
| 0191 | Reinforcing steel (bridge) (8217000000-E) | LB | 34,645 | $1.50 | $2.00 | $1.61 | $1.77 | $2.82 |
| 0192 | Spiral column reinforcing steel (bridge) (8238000000-E) | LB | 5,006 | $2.75 | $3.00 | $3.94 | $4.33 | $4.75 |
| 0193 | Pile DRV equip setup ** steel piles - (HP 12 X 53) (8328200000-E) | EACH | 18 | $1,350.00 | $1,500.00 | $978.05 | $1,075.86 | $1,136.10 |
| 0194 | HP 12 X 53 steel piles (8364000000-E) | LF | 570 | $71.00 | $65.00 | $72.06 | $79.27 | $269.41 |
| 0195 | Steel pile points (8391000000-N) | EACH | 18 | $168.00 | $200.00 | $183.12 | $201.43 | $329.64 |
| 0196 | Two bar metal rail (8475000000-E) | LF | 315.30 | $244.00 | $195.00 | $266.98 | $293.68 | $195.00 |
| 0197 | Vertical concrete barrier rail (8505000000-E) | LF | 215 | $209.00 | $175.00 | $229.91 | $252.90 | $176.38 |
| 0198 | 1'-**"X*****"conc parapet - (1'-2" X 2'-9 1/2") (8517000000-E) | LF | 331 | $225.00 | $200.00 | $222.44 | $244.68 | $180.14 |
| 0199 | Rip rap class II (2'-0" thick) (8608000000-E) | TON | 635 | $74.00 | $75.00 | $75.38 | $75.00 | $118.61 |
| 0200 | Geotextile for drainage (8622000000-E) | SY | 705 | $3.50 | $3.00 | $4.80 | $5.00 | $21.59 |
| 0201 | Elastomeric bearings (8657000000-N) | LS | 1 | $9,300.00 | $10,000 | $9,750.00 | $10,725 | $31,369 |
| 0202 | 3'-0" X 2'-9" prestressed conc box beams (8753100000-E) | LF | 2,805 | $364.00 | $325.00 | $367.10 | $417.67 | $711.65 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NCDOT's tabulation for this contract. NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
Every contract let that day: NCDOT letting of September 15, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.