Floating turbidity curtain, NCDOT 6048000000-E
Low bidders on NCDOT contracts carried a median of $39.00 per SY for this item, over the 24 months to 20 OCT 2026, across 29 low bids. Half of all 172 bids fell between $29.81 and $75.00.
- Owner
- North Carolina DOT
- Item
- 6048000000-E
- Unit
- SY
- Data through
- 20 OCT 2026
NCDOT prints this item as “FLOAT TURBIDITY CURTAIN”.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2013 | 30 | 28 | $29.00 | 144 | $30.00 |
| 2014 | 20 | 19 | $25.00 | 126 | $30.00 |
| 2015 | 16 | 16 | $24.54 | 117 | $29.00 |
| 2016 | 6 | 6 | $30.00 | 31 | $27.00 |
| 2017 | 13 | 13 | $22.00 | 80 | $28.50 |
| 2018 | 10 | 9 | $29.55 | 54 | $29.77 |
| 2019 | 9 | 9 | $28.00 | 43 | $33.00 |
| 2020 | 6 | 6 | $13.50 | 49 | $32.00 |
| 2021 | 25 | 24 | $29.00 | 147 | $32.00 |
| 2022 | 15 | 14 | $44.50 | 72 | $45.00 |
| 2023 | 14 | 12 | $46.73 | 74 | $49.90 |
| 2024 | 12 | 9 | $42.00 | 75 | $45.00 |
| 2025 | 17 | 14 | $55.00 | 88 | $55.36 |
| 2026 | 12 | 11 | $30.00 | 58 | $43.50 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 15 to 100 | 7 | $60.67 |
| 100 to 185 | 7 | $39.00 |
| 200 to 255 | 7 | $41.00 |
| 315 to 16,550 | 8 | $27.77 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Smith-Rowe, LLC | 51 | 25 (49%) |
| FSC II LLC DBA Fred Smith Company | 56 | 19 (34%) |
| Sanford Contractors Inc | 37 | 17 (46%) |
| T. A. Loving Company | 32 | 17 (53%) |
| Dane Construction, Inc. | 98 | 14 (14%) |
| Dellinger, Inc. | 46 | 11 (24%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 20 OCT 2026 | C205207 | Pender | 100 | $55.00 | $55.00 | 5 | S T Wooten Corporation | NCDOT |
| 24 SEP 2026 | C205140 | New Hanover | 111 | $16.59 | $16.59 | 1 | Balfour Beatty Infrastructure Inc | NCDOT |
| 15 SEP 2026 | C205214 | Wilkes | 55 | $15.00 | $60.00 | 5 | James R Vannoy & Sons Construction Company Inc | NCDOT |
| 16 JUN 2026 | C205182 | Carteret | 100 | $39.00 | $39.00 | 2 | Barnhill Contracting Company | NCDOT |
| 16 JUN 2026 | C204742 | Pamlico | 1,670 | $12.84 | $12.84 | 1 | Sanford Contractors Inc | NCDOT |
| 19 MAY 2026 | C205106 | Hyde, Beaufort | 5,950 | $32.00 | $40.00 | 5 | S T Wooten Corporation | NCDOT |
| 19 MAY 2026 | C204773 | Gaston, Mecklenburg | 16,550 | $15.11 | $20.20 | 10 | Zachry Construction Corporation | NCDOT |
| 17 FEB 2026 | C204936 | Alamance | 80 | $75.00 | $65.10 | 7 | Kemp Sigmon Construction Co Inc | NCDOT |
| 17 FEB 2026 | C205095 | Mecklenburg | 15 | $23.50 | $73.50 | 10 | Blythe Development Co. | NCDOT |
| 20 JAN 2026 | C205129 | Pamlico | 1,225 | n/a | $95.00 | 1 | Smith-Rowe, LLC | NCDOT |
| 20 JAN 2026 | C205117 | Cabarrus | 160 | $85.00 | $42.00 | 5 | NJR Group Inc | NCDOT |
| 20 JAN 2026 | C205132 | Cleveland | 230 | $30.00 | $27.50 | 6 | Blythe Construction Inc | NCDOT |
| 18 NOV 2025 | C205069 | Robeson | 160 | $28.00 | $38.45 | 6 | S & C Construction LLC | NCDOT |
| 18 NOV 2025 | C205044 | Surry, Yadkin | 735 | n/a | $66.95 | 5 | Smith-Rowe, LLC | NCDOT |
| 21 OCT 2025 | C205092 | Pitt | 100 | $170.00 | $57.89 | 3 | Barnhill Contracting Company | NCDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.
How these prices were read
NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the NCDOT letting of 20 OCT 2026 and was rebuilt on 26 NOV 2026.