NCDOT contract C205129 bid tabulation
GRADING, DRAINAGE, PAVING AND STRUCTURE. BRIDGE #680078 OVER NEUSE RIVER ON NC-306. Let by North Carolina DOT on January 20, 2026, Pamlico. 2 bids received; low bid $4,333,322 by Smith-Rowe, LLC.
- Owner
- North Carolina DOT
- Letting
- 20 JAN 2026
- Pay items
- 101
- Data through
- 20 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Smith-Rowe, LLC | $4,333,322 | Low |
| 2 | United Infrastructure Group Inc | $5,157,507 | +19% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Smith-Rowe, LLC | 2. United Infrastructure Group Inc |
|---|---|---|---|---|---|
| 0001 | Mobilization (0000100000-N) | LS | 1 | $216,650 | $257,875 |
| 0002 | Construction surveying (0000400000-N) | LS | 1 | $12,182 | $20,000 |
| 0003 | Grading (0043000000-N) | LS | 1 | $220,000 | $25,000 |
| 0004 | Undercut excavation (0057000000-E) | CY | 300 | $0.02 | $21.00 |
| 0005 | Drainage ditch excavation (0134000000-E) | CY | 5 | $235.00 | $205.00 |
| 0006 | Select granular material (0195000000-E) | CY | 300 | $0.01 | $47.00 |
| 0007 | Geotextile for soil stabilization (0196000000-E) | SY | 300 | $7.15 | $4.00 |
| 0008 | Foundation conditioning material, minor structures (0318000000-E) | TON | 10 | $83.65 | $65.00 |
| 0009 | FND condit geotextile (4A) (0321000000-E) | SY | 10 | $36.25 | $15.00 |
| 0010 | 18" RC pipe culverts, class IV (0448300000-E) | LF | 24 | $299.50 | $200.00 |
| 0011 | Pipe clean out (0996000000-N) | EACH | 1 | $6,824.01 | $300.00 |
| 0012 | Class IV aggregate stabilization (1111000000-E) | TON | 30 | $145.00 | $65.00 |
| 0013 | Aggregate base course (1121000000-E) | TON | 60 | $120.00 | $58.00 |
| 0014 | Milln asphalt PVMT ***** - ***** - (0" to 1-1/2") (1308000000-E) | SY | 50 | $240.00 | $178.00 |
| 0015 | Asphalt conc base course, type B25.0C (1491000000-E) | TON | 10 | $1,191.10 | $300.00 |
| 0016 | Asphalt conc surface course, type S9.5B (1519000000-E) | TON | 10 | $1,191.10 | $300.00 |
| 0017 | Asphalt binder for plant mix (1575000000-E) | TON | 5 | $1,042.21 | $1,000.00 |
| 0018 | Subdrain excavation (2022000000-E) | CY | 44.80 | $36.85 | $35.00 |
| 0019 | Geotextile for subsurface drains (2026000000-E) | SY | 200 | $6.00 | $4.00 |
| 0020 | Subdrain coarse aggregate (2036000000-E) | CY | 34 | $126.00 | $75.00 |
| 0021 | 6" perforated subdrain pipe (2044000000-E) | LF | 200 | $10.00 | $16.00 |
| 0022 | Subdrain pipe outlet (2070000000-N) | EACH | 1 | $940.00 | $700.00 |
| 0023 | 6" outlet pipe (2077000000-E) | LF | 6 | $66.75 | $40.00 |
| 0024 | Pipe collars (2253000000-E) | CY | 0.45 | $6,255.83 | $1,200.00 |
| 0025 | Masonry drainage structures (2286000000-N) | EACH | 1 | $7,153.52 | $5,000.00 |
| 0026 | Frame with two grates, STD 840.24 (2366000000-N) | EACH | 1 | $2,923.59 | $900.00 |
| 0027 | CHN LK fence **" fabric - (72") (3533000000-E) | LF | 9 | $335.07 | $225.00 |
| 0028 | Met line PST **" CL fen - (72") (3539000000-E) | EACH | 1 | $967.77 | $650.00 |
| 0029 | Met term PST **" CL fen - (72") (3545000000-E) | EACH | 4 | $1,265.54 | $200.00 |
| 0030 | Generic fencing item (EA) - gate replacement (3578000000-N) | EACH | 1 | $14,665 | $1,500.00 |
| 0031 | Rip rap, class B (3649000000-E) | TON | 3 | $365.00 | $120.00 |
| 0032 | Geotextile for drainage (3656000000-E) | SY | 220 | $6.55 | $4.00 |
| 0033 | Work zone signs (stationary) (4400000000-E) | SF | 112 | $29.78 | $7.75 |
| 0034 | Work zone signs (portable) (4405000000-E) | SF | 96 | $32.15 | $8.55 |
| 0035 | Work zone signs (barricade mounted) (4410000000-E) | SF | 46 | $10.45 | $8.95 |
| 0036 | Drums (4430000000-N) | EACH | 40 | $175.00 | $46.00 |
| 0037 | Barricades (type III) (4445000000-E) | LF | 36 | $52.11 | $25.00 |
| 0038 | Flagger (4455000000-N) | DAY | 8 | $800.00 | $1,850.00 |
| 0039 | Tubular markers (fixed) (4520000000-N) | EACH | 18 | $300.00 | $55.00 |
| 0040 | Thermoplastic pavement marking lines (4", 90 mils) (4685000000-E) | LF | 1,076 | $4.47 | $3.00 |
| 0041 | Thermoplastic pavement marking lines (8", 90 mils) (4695000000-E) | LF | 927 | $5.96 | $4.00 |
| 0042 | Thermoplastic pavement marking lines (24", 90 mils) (4709000000-E) | LF | 160 | $44.67 | $30.00 |
| 0043 | Thermoplastic pavement marking character (90 mils) (4720000000-E) | EACH | 18 | $260.55 | $175.00 |
| 0044 | Thermoplastic pavement marking symbol (90 mils) (4725000000-E) | EACH | 5 | $260.69 | $175.00 |
| 0045 | Paint pavement marking lines (4") (4810000000-E) | LF | 1,944 | $1.49 | $1.00 |
| 0046 | Paint pavement marking lines (24") (4835000000-E) | LF | 80 | $7.44 | $5.00 |
| 0047 | Paint pavement marking character (4840000000-N) | EACH | 24 | $74.44 | $50.00 |
| 0048 | Paint pavement marking symbol (4845000000-N) | EACH | 28 | $74.44 | $50.00 |
| 0049 | Removal of pavement marking lines (4") (4850000000-E) | LF | 1,578 | $2.23 | $1.50 |
| 0050 | Removal of pavement marking lines (8") (4860000000-E) | LF | 86 | $4.47 | $3.00 |
| 0051 | Removal of pavement marking lines (24") (4870000000-E) | LF | 160 | $14.89 | $10.00 |
| 0052 | Removal of pavement marking symbols & characters (4875000000-N) | EACH | 23 | $96.81 | $65.00 |
| 0053 | Portable lighting (5255000000-N) | LS | 1 | $34,380 | $30,000 |
| 0054 | Temporary silt fence (6000000000-E) | LF | 100 | $10.10 | $5.00 |
| 0055 | Stone for erosion control, class A (6006000000-E) | TON | 35 | $1.00 | $100.00 |
| 0056 | Stone for erosion control, class B (6009000000-E) | TON | 40 | $1.00 | $100.00 |
| 0057 | Sediment control stone (6012000000-E) | TON | 55 | $1.00 | $75.00 |
| 0058 | Temporary mulching (6015000000-E) | ACRE | 1.20 | $2,084.42 | $2,300.00 |
| 0059 | Seed for temporary seeding (6018000000-E) | LB | 100 | $7.44 | $3.00 |
| 0060 | Fertilizer for temporary seeding (6021000000-E) | TON | 0.50 | $4,095.75 | $700.00 |
| 0061 | Temporary slope drains (6024000000-E) | LF | 200 | $1.00 | $20.00 |
| 0062 | Safety fence (6029000000-E) | LF | 460 | $4.47 | $2.25 |
| 0063 | Silt excavation (6030000000-E) | CY | 60 | $1.00 | $25.00 |
| 0064 | Matting for erosion control (6036000000-E) | SY | 250 | $6.33 | $2.00 |
| 0065 | Coir fiber mat (6037000000-E) | SY | 100 | $11.91 | $7.00 |
| 0066 | 1/4" hardware cloth (6042000000-E) | LF | 25 | $10.45 | $6.00 |
| 0067 | Floating turbidity curtain (6048000000-E) | SY | 1,225 | $0.01 | $95.00 |
| 0068 | Special stilling basins (6070000000-N) | EACH | 2 | $725.00 | $1,500.00 |
| 0069 | Flocculant (6071002000-E) | LB | 10 | $32.76 | $10.00 |
| 0070 | Coir fiber wattle (6071012000-E) | LF | 40 | $22.89 | $15.00 |
| 0071 | Seeding and mulching (6084000000-E) | ACRE | 1.20 | $4,429.40 | $3,800.00 |
| 0072 | Mowing (6087000000-E) | ACRE | 0.60 | $261.68 | $200.00 |
| 0073 | Seed for repair seeding (6090000000-E) | LB | 50 | $17.87 | $5.00 |
| 0074 | Fertilizer for repair seeding (6093000000-E) | TON | 0.25 | $8,191.51 | $500.00 |
| 0075 | Seed for supplemental seeding (6096000000-E) | LB | 50 | $17.87 | $5.00 |
| 0076 | Fertilizer topdressing (6108000000-E) | TON | 0.75 | $4,610.99 | $500.00 |
| 0077 | Specialized hand mowing (6114500000-N) | MHR | 10 | $111.67 | $55.00 |
| 0078 | Manual litter removal (6114800000-N) | MHR | 2 | $125.00 | $150.00 |
| 0079 | Litter disposal (6114900000-E) | TON | 1 | $655.00 | $150.00 |
| 0080 | Response for erosion control (6117000000-N) | EACH | 13 | $57.26 | $500.00 |
| 0081 | Concrete washout structure (6117500000-N) | EACH | 1 | $1,000.00 | $1,200.00 |
| 0082 | Reforestation (6123000000-E) | ACRE | 0.10 | $8,933.24 | $8,900.00 |
| 0083 | Generic erosion control item (EA) - prefabricated concrete washout (6132000000-N) | EACH | 2 | $650.00 | $1,200.00 |
| 0084 | Remv exist STR ****** BRG (SP) - (10+23.61 -ramp-) (8021000000-N) | LS | 1 | $491,509 | $996,919 |
| 0085 | Asbestos assessment (8065000000-N) | LS | 1 | $1,488.88 | $10,000 |
| 0086 | Structural steel (8280000000-E) | LS | 1 | $748,455 | $1,100,000 |
| 0087 | Pollution control (8296000000-N) | LS | 1 | $22,333 | $30,000 |
| 0088 | Pile DRV equip setup ** steel piles - (HP 14 X 73) (8328200000-E) | EACH | 6 | $2,931.24 | $50,000 |
| 0089 | HP 14 X 73 steel piles (8384000000-E) | LF | 540 | $0.01 | $90.00 |
| 0090 | Pile redrives (8393000000-N) | EACH | 6 | $314.06 | $1,500.00 |
| 0091 | Dynamic pile testing (8394000000-N) | EACH | 2 | $3,387.18 | $2,200.00 |
| 0092 | Generic structure item (LS) - painting bulkhead sheet piling (8860000000-N) | LS | 1 | $323,562 | $550,000 |
| 0093 | Generic structure item (LS) - painting containment for bulkhead (8860000000-N) | LS | 1 | $250,402 | $200,000 |
| 0094 | Generic structure item (LS) - painting steel piles (8860000000-N) | LS | 1 | $164,520 | $100,000 |
| 0095 | Generic structure item (LS) - ramp electrical system (8860000000-N) | LS | 1 | $383,027 | $300,000 |
| 0096 | Generic structure item (LS) - ramp mechanical system (8860000000-N) | LS | 1 | $965,800 | $500,000 |
| 0097 | Generic structure item (LF) - 1-1/4" dia steel pipe rail (8867000000-E) | LF | 69 | $162.27 | $150.00 |
| 0098 | Generic structure item (CY) - class AA concrete (bridge) (8881000000-E) | CY | 7 | $7,466.99 | $2,000.00 |
| 0099 | Generic structure item (LB) - epoxy coated reinforcing steel (bridge) (8889000000-E) | LB | 383 | $12.09 | $1.50 |
| 0100 | Generic structure item (SF) - ultra high molecular weight polyethylene fender (1-1/4") (8892000000-E) | SF | 223 | $474.18 | $1,000.00 |
| 0101 | Generic structure item (SF) - ultra high molecular weight polyethylene fender (3-1/2") (8892000000-E) | SF | 120 | $650.35 | $1,200.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NCDOT's tabulation for this contract. NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
Every contract let that day: NCDOT letting of January 20, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.