Matting for erosion control, NCDOT 6036000000-E

Low bidders on NCDOT contracts carried a median of $1.75 per SY for this item, over the 24 months to 20 OCT 2026, across 136 low bids. Half of all 676 bids fell between $1.60 and $2.00.

Owner
North Carolina DOT
Item
6036000000-E
Unit
SY
Data through
20 OCT 2026

NCDOT prints this item as “MATTING FOR EROS CONTROL”.

$1.75Low bidder's median, per SY
$1.75Median of all bids, per SY
136Contracts in the window

By year of letting

Matting for erosion control, NCDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
2013114114$1.55567$1.50
20146867$1.50381$1.45
20155857$1.70355$1.60
20165252$1.79264$1.80
20174442$1.75236$1.74
20186260$1.75271$1.75
20193534$1.73159$1.75
20202020$2.05114$2.00
20216161$1.75316$1.90
20226060$2.00245$2.00
20234949$2.00223$2.00
20245352$1.99270$1.90
20256767$1.70339$1.75
20265858$1.80279$1.79

Bid prices as published, not adjusted for inflation.

By county

CountyLow bidsLow-bid medianAll bidsMedian, all bids
Wake7$1.7042$1.75
Mecklenburg6$1.5641$1.65
Forsyth6$1.7335$1.65
Rockingham7$1.7531$1.79
Chatham3$1.5027$1.50
Wayne4$1.8526$1.81
Guilford5$1.6925$1.65
Rutherford4$1.7324$1.77
Brunswick4$2.9217$2.00
Cumberland4$1.4516$1.50
Haywood3$1.7913$1.95
Pender3$3.0013$2.50
Matting for erosion control, NCDOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Quantity (SY)Low bidsLow-bid median
140 to 5,75034$2.25
6,250 to 12,00034$1.69
12,500 to 24,56034$1.70
24,600 to 417,55034$1.73
Matting for erosion control, NCDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
Smith-Rowe, LLC212113 (53%)
S T Wooten Corporation22693 (41%)
Dane Construction, Inc.26690 (34%)
FSC II LLC DBA Fred Smith Company18389 (49%)
Barnhill Contracting Company14188 (62%)
Blythe Construction Inc16859 (35%)
Matting for erosion control, NCDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
20 OCT 2026C205216Martin6,325$1.79$1.794Barnhill Contracting CompanyNCDOT
20 OCT 2026C205207Pender11,700$3.00$1.905S T Wooten CorporationNCDOT
20 OCT 2026C204338Wake49,725$1.70$1.718Blythe Construction IncNCDOT
24 SEP 2026C205140New Hanover3,660$2.12$2.121Balfour Beatty Infrastructure IncNCDOT
15 SEP 2026C205206Onslow3,500$1.70$1.853Barnhill Contracting CompanyNCDOT
15 SEP 2026C205203Wayne1,700$2.25$2.086Legion Asphalt IncNCDOT
15 SEP 2026C204349Wake, Durham111,570$1.55$1.554Blythe Construction IncNCDOT
15 SEP 2026C204990Randolph10,000$1.65$1.829Apac - Atlantic, Inc. Thompson Arthur DivisionNCDOT
15 SEP 2026C205214Wilkes9,500$2.00$1.985James R Vannoy & Sons Construction Company IncNCDOT
15 SEP 2026C204947Caldwell33,795$1.80$1.753Branch Civil IncNCDOT
18 AUG 2026C205195Catawba35,000$1.82$1.814Blythe Development Co.NCDOT
18 AUG 2026C205205Robeson20,800$1.93$1.842Bmco Construction, Inc.NCDOT
18 AUG 2026C205202Guilford10,090$1.70$1.705Triangle Grading & Paving IncNCDOT
18 AUG 2026C204504Watauga123,125$1.80$1.803Branch Civil IncNCDOT
18 AUG 2026C204877Rutherford4,000$2.25$1.958R.E. Burns & Sons Co., Inc.NCDOT
Latest NCDOT contracts carrying Matting for erosion control

Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.

How these prices were read

NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the NCDOT letting of 20 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy