Low bidders on NCDOT contracts carried a median of $6.91 per SY for this item, over the 24 months to 20 OCT 2026, across 2 low bids. Half of all 5 bids fell between $6.00 and $6.75.
- Owner
- North Carolina DOT
- Item
- 6038000000-E
- Unit
- SY
- Data through
- 20 OCT 2026
NCDOT prints this item as “PERM SOIL REINF MAT”.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2013 | 72 | 72 | $5.30 | 364 | $5.75 |
| 2014 | 42 | 42 | $5.00 | 240 | $5.00 |
| 2015 | 35 | 34 | $5.00 | 230 | $5.22 |
| 2016 | 20 | 20 | $4.38 | 119 | $5.00 |
| 2017 | 20 | 20 | $5.30 | 123 | $4.75 |
| 2018 | 31 | 31 | $4.60 | 147 | $4.50 |
| 2019 | 10 | 10 | $5.25 | 46 | $5.03 |
| 2020 | 6 | 6 | $5.29 | 39 | $5.50 |
| 2021 | 21 | 21 | $6.00 | 107 | $5.75 |
| 2022 | 18 | 18 | $6.70 | 84 | $5.62 |
| 2023 | 18 | 18 | $5.62 | 75 | $6.00 |
| 2024 | 10 | 9 | $6.00 | 53 | $7.40 |
| 2025 | 2 | 2 | $6.91 | 5 | $6.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Guilford | 21 | $4.00 | 120 | $4.74 |
| Wake | 12 | $5.95 | 81 | $5.50 |
| Cabarrus | 13 | $4.60 | 81 | $4.50 |
| Forsyth | 12 | $4.83 | 76 | $4.75 |
| Davidson | 9 | $6.31 | 66 | $6.25 |
| Rockingham | 10 | $6.00 | 51 | $6.00 |
| Alamance | 7 | $7.00 | 48 | $6.00 |
| Johnston | 7 | $6.30 | 46 | $5.75 |
| Cleveland | 4 | $4.12 | 40 | $4.00 |
| Wilkes | 7 | $5.34 | 39 | $5.35 |
| Henderson | 9 | $6.60 | 37 | $6.60 |
| Randolph | 5 | $4.00 | 34 | $4.50 |
Countys with at least three low bids, over all lettings.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 10 to 150 | 75 | $6.00 |
| 150 to 500 | 76 | $5.50 |
| 500 to 2,005 | 76 | $5.19 |
| 2,015 to 115,220 | 76 | $4.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Dane Construction, Inc. | 110 | 47 (43%) |
| Smith-Rowe, LLC | 96 | 41 (43%) |
| Blythe Construction Inc | 74 | 33 (45%) |
| S T Wooten Corporation | 64 | 24 (38%) |
| Barnhill Contracting Company | 43 | 22 (51%) |
| NHM Constructors, LLC | 34 | 21 (62%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 25 JUN 2025 | C205078 | Henderson | 82.50 | $7.82 | $7.82 | 1 | Wright Brothers Construction Company Inc | NCDOT |
| 21 JAN 2025 | C204992 | Hoke | 6,000 | $6.00 | $6.00 | 4 | Barnhill Contracting Company | NCDOT |
| 15 OCT 2024 | C204339 | Wake | 280 | n/a | $8.50 | 6 | NCDOT | |
| 09 SEP 2024 | C204374 | Moore | 10,245 | $4.49 | $4.49 | 1 | Flatiron Fred Smith Company JV | NCDOT |
| 20 AUG 2024 | C204925 | Haywood | 350 | $11.50 | $10.00 | 7 | NHM Constructors, LLC | NCDOT |
| 16 JUL 2024 | C204878 | Buncombe | 235 | $4.50 | $4.06 | 3 | Archer Wright JV | NCDOT |
| 16 JUL 2024 | C204843 | Randolph | 365 | $6.00 | $7.00 | 4 | Conti Civil LLC | NCDOT |
| 18 JUN 2024 | C204204 | Wake | 35 | $7.40 | $7.40 | 8 | Blythe Construction Inc | NCDOT |
| 28 MAY 2024 | C204913 | Forsyth | 2,975 | $3.80 | $4.08 | 5 | Apac Atlantic Inc Smith Rowe LLC JV | NCDOT |
| 07 MAY 2024 | C204953 | Buncombe | 100 | $12.50 | $10.00 | 3 | Archer Wright JV | NCDOT |
| 16 APR 2024 | C204724 | Pender | 190 | $8.00 | $8.00 | 7 | Smith-Rowe, LLC | NCDOT |
| 16 JAN 2024 | C204830 | Stanly | 500 | $4.00 | $5.00 | 9 | Smith-Rowe, LLC | NCDOT |
| 19 DEC 2023 | C204842 | Union | 160 | $4.59 | $5.00 | 5 | K. West Group, LLC DBA | NCDOT |
| 19 DEC 2023 | C204431 | Mecklenburg | 750 | $4.95 | $5.47 | 2 | Caton Construction Group Inc | NCDOT |
| 19 DEC 2023 | C204887 | Cherokee | 17,585 | $4.60 | $5.55 | 2 | Wright Brothers Construction Company Inc | NCDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.
How these prices were read
NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the NCDOT letting of 20 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.