Blythe Development Co.: NCDOT bid record
Blythe Development Co. submitted 103 bids on North Carolina DOT contracts in the data, from 19 FEB 2013 to 18 AUG 2026, and was the low bidder on 24 of them (23%). When it was not low, its total sat a median +15% above the low bid.
- Owner
- North Carolina DOT
- Low bid volume
- $636,595,034
- Latest bid
- 18 AUG 2026
- Data through
- 20 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2013 | 20 | 7 | 35% |
| 2014 | 5 | 0 | 0% |
| 2015 | 15 | 2 | 13% |
| 2016 | 6 | 2 | 33% |
| 2017 | 8 | 3 | 38% |
| 2018 | 4 | 3 | 75% |
| 2019 | 3 | 2 | 67% |
| 2020 | 2 | 0 | 0% |
| 2021 | 8 | 0 | 0% |
| 2022 | 4 | 1 | 25% |
| 2023 | 6 | 0 | 0% |
| 2024 | 5 | 1 | 20% |
| 2025 | 10 | 1 | 10% |
| 2026 | 7 | 2 | 29% |
By county
| County | Bids | Low bids | Win rate |
|---|---|---|---|
| Mecklenburg | 21 | 8 | 38% |
| Cabarrus | 15 | 6 | 40% |
| Davidson | 8 | 1 | 13% |
| Cleveland | 5 | 0 | 0% |
| Union | 4 | 1 | 25% |
| Buncombe | 4 | 1 | 25% |
| Rowan | 4 | 2 | 50% |
| Mcdowell | 3 | 0 | 0% |
| Alamance | 3 | 0 | 0% |
| Guilford | 3 | 0 | 0% |
| Iredell | 3 | 0 | 0% |
| Rutherford | 2 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Asphalt binder for plant mix | 1575000000-E | TON | 89 | 31 (35%) | $598.33 | $595.00 |
| Incidental stone base | 1220000000-E | TON | 82 | 29 (35%) | $32.00 | $40.00 |
| **" skimmer - (1-1/2") | 6071050000-E | EACH | 68 | 23 (34%) | $890.00 | $1,084.98 |
| 1/4" hardware cloth | 6042000000-E | LF | 85 | 22 (26%) | $4.00 | $4.50 |
| Incidental milling | 1330000000-E | SY | 72 | 22 (31%) | $12.00 | $12.00 |
| 12" water line | 5326200000-E | LF | 42 | 22 (52%) | $115.00 | $135.00 |
| Geotextile for soil stabilization | 0196000000-E | SY | 87 | 21 (24%) | $2.26 | $2.50 |
| Aggregate base course | 1121000000-E | TON | 61 | 21 (34%) | $32.00 | $38.37 |
| Pipe collars | 2253000000-E | CY | 43 | 21 (49%) | $880.00 | $1,650.00 |
| Abandon 8" utility pipe | 5801000000-E | LF | 42 | 20 (48%) | $10.00 | $15.00 |
| Safety fence | 6029000000-E | LF | 86 | 19 (22%) | $2.00 | $2.20 |
| Paint pavement marking lines (4") | 4810000000-E | LF | 75 | 19 (25%) | $0.28 | $0.27 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Blythe Construction Inc | 63 | 27 of 63 |
| Smith-Rowe, LLC | 33 | 24 of 33 |
| Dane Construction, Inc. | 31 | 16 of 31 |
| Sealand Contractors Corp | 18 | 9 of 18 |
| W C English Incorporated | 17 | 8 of 17 |
| Vecellio & Grogan Inc | 16 | 8 of 16 |
| NJR Group Inc | 15 | 10 of 15 |
| Flatiron Constructors Inc | 15 | 5 of 15 |
| J. T. Russell & Sons, Inc. | 14 | 7 of 14 |
| Triangle Grading & Paving Inc | 14 | 8 of 14 |
Latest bids
| Let | Contract | County | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 18 AUG 2026 | C205195 | Catawba | GRADING, DRAINAGE, PAVING, AND SIGNALS. INTERCHANGE AT I-40 AND SR-1007 (LENOIR RHYNE BOULEVARD) | 1 of 4 | $13,758,420 | Low, 6.0% under the second |
| 17 MAR 2026 | C205013 | Mecklenburg | GRADING, DRAINAGE, PAVING, AND SIGNALS. GREYLOCK RIDGE RD FROM EAST JOHN ST TO TANK TOWN RD | 6 of 9 | $5,394,645 | +29% |
| 17 MAR 2026 | C205139 | Henderson | GREENWAY CONSTRUCTION & PEDESTRIAN BRIDGE REHAB. (DB). ECUSTA TRAIL FROM US-64 TO TRANSYLVANIA COUNTY LINE | 3 of 3 | $28,700,000 | +35% |
| 17 FEB 2026 | C204936 | Alamance | GRADING, DRAINAGE, PAVING, AND STRUCTURES., GRADING, DRAINAGE, PAVING, AND STURCTURES. BRIDGE #000014 OVER CANE CREEK ON NC-87 | 6 of 7 | $9,367,347 | +22% |
| 17 FEB 2026 | C205095 | Mecklenburg | GRADING, DRAINAGE, PAVING, SIGNALS, AND CULVERTS. SR-2415 (BAILEY RD) FROM POOLE PLACE DR TO US-21 (STATESVILLE RD) | 1 of 10 | $7,809,039 | Low, 9.0% under the second |
| 20 JAN 2026 | C205117 | Cabarrus | GRADING, DRAINAGE, PAVING, AND SIGNALS. US-29 FROM 0.6 MILES WEST OF SR-1414 (ROCK HILL CHURCH RD) TO JUST EAST OF SR-1414 (ROCK HILL CHURCH | 5 of 5 | $18,037,634 | +29% |
| 20 JAN 2026 | C205132 | Cleveland | GRADING, DRAINAGE, PAVING, AND STRUCTURE. BRIDGE #220075 ON NC-226 (POLKVILLE ROAD) OVER HINTON CREEK | 6 of 6 | $8,093,510 | +49% |
| 16 DEC 2025 | C205135 | Rutherford | GRADING, DRAINAGE, AND PAVING. (EXPRESS DESIGN BUILD). INTERSECTION OF US-64/US-74A (WEST MOUNTAIN ST) AND NORTH WASHINGTON ST | 4 of 4 | $5,238,000 | +16% |
| 18 NOV 2025 | C205118 | Mecklenburg | GRADING, DRAINAGE, AND PAVING. SR-2042 (OAKDALE RD), SR-2108 (SUNSET RD), SR-2025 (MIRANDA RD), AND SR-2040 (LAWING RD) | 3 of 6 | $7,995,407 | +17% |
| 18 NOV 2025 | C204505 | Mecklenburg | GRADING, DRAINAGE, PAVING, SIGNALS, AND RETAINING WALLS. SR-2195 (TORRENCE CHAPEL RD) AND SR-5544 (WEST CATAWBA AVE) IN CORNELIUS | 4 of 4 | $24,349,660 | +14% |
| 16 SEP 2025 | C205122 | Buncombe | ROADWAY AND BRIDGE CONSTRUCTION (EXPRESS DESIGN BUILD)., ROADWAY AND CULVERT CONSTRUCTION (EXPRESS DESIGN BUILD). BRIDGES ON SR-2109, SR-211 | 2 of 2 | $9,241,400 | +9.0% |
| 19 AUG 2025 | C204991 | Mecklenburg | BRIDGE #590165 OVER COFFEY CREEK ON SHOPTON RD., BRIDGE #590165 OVER COFFEY CREEK ON SR 5469 (SHOPTON RD)., BRIDGE #590165 OVER COFFEY CREEK | 1 of 6 | $6,807,682 | Low, 17% under the second |
| 19 AUG 2025 | C205039 | Mecklenburg | GRADING, DRAINAGE, AND PAVING. SR-3174 (IDLEWILD RD) FROM SR-3175 (STALLINGS RD) TO I-485 | 7 of 7 | $11,140,891 | +28% |
| 17 JUN 2025 | C205016 | Davidson | GRADING, DRAINAGE, PAVING, AND STRUCTURES. REPLACE BRIDGE #58 OVER US-64 ON NC-109 | 7 of 9 | $9,284,669 | +21% |
| 20 MAY 2025 | C205032 | Chatham | DRAINAGE, GRADING, PAVING, SIGNALS, AND STRUCTURES. SR-2700 (CHATHAM PARK WAY) FROM US-15/US-501 SOUTH OF PITTSBORO TO US-64 BUSINESS | 12 of 12 | $60,145,921 | +52% |
| 18 MAR 2025 | C205064 | Mcdowell | ROADWAY AND BRIDGE CONSTRUCTION (EXPRESS DESIGN BUILD). BRIDGE #580058 OVER MACKEY CREEK ON US-70 | 2 of 3 | $5,879,172 | +9.0% |
| 21 JAN 2025 | C205025 | Buncombe | ROADWAY AND BRIDGE CONSTRUCTION (EXPRESS DESIGN BUILD). BRG #100716 ON SR-2832, BRG #100394 ON SR-2783, BRG #100396 ON SR-2810, BRG #100118 | 3 of 3 | $13,380,695 | +109% |
| 17 DEC 2024 | C204384 | Cabarrus | GRADING, DRAINAGE, PAVING, AND STRUCTURE. BRIDGE #120109 OVER US-29 (NORTH CANNON BLVD) ON SR-1706 (MARTIN LUTHER KING JR AVENUE) | 8 of 9 | $7,553,599 | +32% |
| 15 OCT 2024 | C204348 | Iredell, Catawba | GRADING, DRAINAGE, PAVING, SIGNALS, AND STRUCTURES. NC-150 FROM SR-1840 (GREENWOOD ROAD) IN CATAWBA COUNTY TO US-21 IN IREDELL COUNTY | 1 of 5 | $249,369,373 | Low, 0.0% under the second |
| 15 OCT 2024 | C204966 | Mecklenburg | GRADING, DRAINAGE, PAVING, SIGNALS, AND STRUCTURES. SR-3440 (MCKEE RD EXT) FROM SR-3448 (PLEASANT PLAINS RD) TO SR-1010 (E JOHN ST) | 2 of 6 | $10,799,504 | 0.0% |
| 18 JUN 2024 | C204501 | Mecklenburg | GRADING, DRAINAGE, PAVING, AND STRUCTURES. SR-2316 (NORTHCROSS DR) FROM NORTH OF NC-73 (SAM FURR RD) TO SR-2147 (WESTMORELAND RD) | 3 of 9 | $21,179,560 | +2.0% |
| 19 MAR 2024 | C204822 | Union | GRADING, DRAINAGE, PAVING, AND SIGNALS. SR-1364 (PLEASANT PLAINS ROAD) AT SR-1357 (POTTERS ROAD) | 2 of 4 | $9,252,571 | +2.0% |
| 19 DEC 2023 | C204842 | Union | Grading, drainage, paving, signals, and structure. SR-1362 (CHESTNUT LANE CONNECTOR) FROM SR-1367 (MATTHEWS INDIAN TRAIL ROAD) TO SR-1368 (G | 4 of 5 | $20,732,765 | +15% |
| 19 DEC 2023 | C204431 | Mecklenburg | Grading, drainage and paving., grading, drainage, paving, and wall. ROUNDABOUTS AT NC-115/DAVIDSON ST/POTTS ST AND AT SR-6038/GRIFFITH ST/BE | 2 of 2 | $15,857,771 | +2.0% |
| 21 NOV 2023 | C204852 | Iredell | Widening, grading, drainage, paving, and structures. SR-1100 (BRAWLEY SCHOOL RD) FROM I-77 TO US-21 | 5 of 5 | $53,853,300 | +55% |
How this record was read
NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
- Every bid counted here matched its published total to within one dollar; NCDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.