NCDOT contract C205132 bid tabulation
GRADING, DRAINAGE, PAVING, AND STRUCTURE. BRIDGE #220075 ON NC-226 (POLKVILLE ROAD) OVER HINTON CREEK. Let by North Carolina DOT on January 20, 2026, Cleveland. 6 bids received; low bid $5,417,482 by Blythe Construction Inc.
- Owner
- North Carolina DOT
- Letting
- 20 JAN 2026
- Pay items
- 121
- Data through
- 20 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Blythe Construction Inc | $5,417,482 | Low |
| 2 | Kemp Sigmon Construction Co Inc | $6,385,066 | +18% |
| 3 | Dane Construction, Inc. | $6,896,818 | +27% |
| 4 | United Infrastructure Group Inc | $7,560,400 | +40% |
| 5 | Vecellio & Grogan Inc | $7,600,000 | +40% |
| 6 | Blythe Development Co. | $8,093,510 | +49% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Blythe Construction Inc | 2. Kemp Sigmon Construction Co Inc | 3. Dane Construction, Inc. | 4. United Infrastructure Group Inc | 5. Vecellio & Grogan Inc | 6. Blythe Development Co. |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Mobilization (0000100000-N) | LS | 1 | $269,000 | $305,000 | $344,500 | $378,020 | $375,000 | $404,000 |
| 0002 | Construction surveying (0000400000-N) | LS | 1 | $60,000 | $50,000 | $30,900 | $150,000 | $283,881 | $90,000 |
| 0003 | Supplementary clearing & grubbing (0050000000-E) | ACRE | 1 | $3,000.00 | $100.00 | $1.00 | $15,000 | $15,000 | $24,000 |
| 0004 | Undercut excavation (0057000000-E) | CY | 450 | $24.00 | $5.00 | $25.00 | $45.00 | $18.00 | $27.00 |
| 0005 | Grading (0063000000-N) | LS | 1 | $595,000 | $1,090,000 | $600,000 | $1,250,000 | $516,500 | $1,174,932 |
| 0006 | Borrow excavation (0106000000-E) | CY | 31,000 | $12.00 | $20.00 | $25.00 | $26.00 | $30.00 | $33.50 |
| 0007 | Select granular material (0195000000-E) | CY | 200 | $82.20 | $10.00 | $75.00 | $90.00 | $85.00 | $70.00 |
| 0008 | Geotextile for soil stabilization (0196000000-E) | SY | 200 | $3.00 | $3.00 | $5.00 | $10.00 | $6.00 | $3.50 |
| 0009 | Generic grading item (LS) - type 1 bridge approach fill, station 18+04.74 -L- (0248000000-N) | LS | 1 | $67,100 | $30,000 | $45,000 | $150,000 | $75,000 | $40,000 |
| 0010 | Foundation conditioning material, minor structures (0318000000-E) | TON | 70 | $63.00 | $10.00 | $75.00 | $70.00 | $50.00 | $53.00 |
| 0011 | FND condit geotextile (4A) (0321000000-E) | SY | 200 | $2.80 | $1.00 | $5.00 | $8.00 | $1.25 | $3.50 |
| 0012 | 15" drainage pipe (0335200000-E) | LF | 80 | $78.00 | $85.00 | $110.00 | $85.00 | $175.00 | $100.00 |
| 0013 | 18" drainage pipe (0335300000-E) | LF | 48 | $84.00 | $95.00 | $125.00 | $95.00 | $265.00 | $119.00 |
| 0014 | 24" RC pipe culverts, class III (0378000000-E) | LF | 60 | $125.00 | $110.00 | $200.00 | $175.00 | $285.00 | $179.00 |
| 0015 | 15" RC pipe culverts, class IV (0448200000-E) | LF | 260 | $75.00 | $90.00 | $125.00 | $155.00 | $175.00 | $144.00 |
| 0016 | 15" CS pipe culverts, 0.064" thick (0582000000-E) | LF | 128 | $78.00 | $90.00 | $110.00 | $85.00 | $165.00 | $120.00 |
| 0017 | **" CS elbow *****" thick - (15", 0.064") (0636000000-E) | EACH | 6 | $440.00 | $750.00 | $500.00 | $1,500.00 | $700.00 | $1,100.00 |
| 0018 | **"WLD STL pipe grad B in soil - (24", 0.500") (0973100000-E) | LF | 70 | $1,535.00 | $1,500.00 | $1,535.00 | $1,535.00 | $2,300.00 | $2,175.00 |
| 0019 | **"WLD STL pipe grad B not in soil - (24", 0.500") (0973300000-E) | LF | 70 | $0.01 | $10.00 | $0.01 | $0.01 | $0.15 | $3,100.00 |
| 0020 | Pipe removal (0995000000-E) | LF | 252 | $60.00 | $20.00 | $30.00 | $70.00 | $40.00 | $52.00 |
| 0021 | Shallow undercut (1099500000-E) | CY | 100 | $19.90 | $25.00 | $30.00 | $20.00 | $20.00 | $22.00 |
| 0022 | Class IV subgrade stabilization (1099700000-E) | TON | 200 | $44.43 | $40.00 | $45.00 | $75.00 | $65.00 | $49.00 |
| 0023 | Geotextile for subgrade stabilization (1112000000-E) | SY | 500 | $3.00 | $4.00 | $5.00 | $7.00 | $6.50 | $3.00 |
| 0024 | Aggregate base course (1121000000-E) | TON | 1,518 | $48.60 | $45.00 | $50.00 | $100.00 | $70.00 | $49.00 |
| 0025 | Incidental stone base (1220000000-E) | TON | 200 | $49.60 | $50.00 | $70.00 | $65.00 | $65.00 | $49.00 |
| 0026 | Prime coat (1275000000-E) | GAL | 1,310 | $5.30 | $10.00 | $5.30 | $25.22 | $8.50 | $10.50 |
| 0027 | Mill asp PVMT *****" DTH - (1-1/2") (1297000000-E) | SY | 940 | $11.00 | $25.00 | $15.00 | $9.03 | $12.95 | $65.00 |
| 0028 | Incidental milling (1330000000-E) | SY | 350 | $17.00 | $25.00 | $20.00 | $13.07 | $26.00 | $65.00 |
| 0029 | Asphalt conc base course, type B25.0C (1491000000-E) | TON | 750 | $100.00 | $100.00 | $100.00 | $100.90 | $120.81 | $130.00 |
| 0030 | Asphalt conc intermediate course, type I19.0C (1503000000-E) | TON | 760 | $100.00 | $100.00 | $100.00 | $100.90 | $120.81 | $135.00 |
| 0031 | Asphalt conc surface course, type S9.5C (1523000000-E) | TON | 1,260 | $100.00 | $100.00 | $100.00 | $100.90 | $120.81 | $141.00 |
| 0032 | Asphalt binder for plant mix (1575000000-E) | TON | 145 | $625.00 | $625.00 | $625.00 | $630.60 | $755.05 | $722.00 |
| 0033 | Subdrain excavation (2022000000-E) | CY | 44.80 | $45.00 | $20.00 | $35.00 | $25.00 | $41.86 | $26.00 |
| 0034 | Geotextile for subsurface drains (2026000000-E) | SY | 200 | $16.00 | $2.00 | $5.00 | $6.00 | $7.77 | $3.00 |
| 0035 | Subdrain coarse aggregate (2036000000-E) | CY | 33.60 | $107.00 | $100.00 | $110.00 | $130.00 | $77.74 | $123.00 |
| 0036 | 6" perforated subdrain pipe (2044000000-E) | LF | 200 | $22.00 | $10.00 | $25.00 | $30.00 | $47.84 | $23.00 |
| 0037 | Subdrain pipe outlet (2070000000-N) | EACH | 1 | $500.00 | $400.00 | $550.00 | $500.00 | $478.40 | $1,000.00 |
| 0038 | 6" outlet pipe (2077000000-E) | LF | 6 | $50.00 | $72.00 | $45.00 | $150.00 | $59.80 | $41.00 |
| 0039 | Endwalls (2209000000-E) | CY | 1.50 | $1,500.00 | $1,500.00 | $2,000.00 | $5,000.00 | $2,889.82 | $2,600.00 |
| 0040 | Flowable fill (2275000000-E) | CY | 16 | $340.00 | $400.00 | $250.00 | $400.00 | $515.83 | $420.00 |
| 0041 | Masonry drainage structures (2286000000-N) | EACH | 8 | $2,300.00 | $2,500.00 | $4,000.00 | $5,000.00 | $6,086.20 | $5,800.00 |
| 0042 | Frame with two grates, STD 840.29 (2367000000-N) | EACH | 7 | $1,300.00 | $1,000.00 | $2,000.00 | $1,500.00 | $1,124.88 | $1,200.00 |
| 0043 | Shoulder berm gutter (2556000000-E) | LF | 710 | $71.00 | $45.00 | $40.00 | $49.00 | $86.21 | $68.00 |
| 0044 | Steel beam guardrail (3030000000-E) | LF | 800 | $24.00 | $24.00 | $24.00 | $24.00 | $29.39 | $29.00 |
| 0045 | Additional guardrail posts (3150000000-N) | EACH | 5 | $11.00 | $11.00 | $11.00 | $11.00 | $13.47 | $13.00 |
| 0046 | Guardrail end units, type TL-3 (3287000000-N) | EACH | 4 | $3,350.00 | $3,350.00 | $3,350.00 | $3,350.00 | $4,102.50 | $4,000.00 |
| 0047 | Guardrail anchor units, type B-77 (3317000000-N) | EACH | 4 | $2,600.00 | $2,600.00 | $2,600.00 | $2,600.00 | $3,184.03 | $3,100.00 |
| 0048 | Temporary steel beam guardrail (3380000000-E) | LF | 875 | $7.50 | $7.50 | $7.50 | $7.50 | $9.18 | $9.00 |
| 0049 | Temp GDRL anch units ****** - (III) (3387000000-N) | EACH | 4 | $750.00 | $750.00 | $750.00 | $750.00 | $918.47 | $885.00 |
| 0050 | Temp GDRL end units ***** - (TL-3) (3389150000-N) | EACH | 4 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,449.25 | $2,400.00 |
| 0051 | Temporary additional guardrail posts (3389160000-N) | EACH | 5 | $11.00 | $11.00 | $11.00 | $11.00 | $13.47 | $13.00 |
| 0052 | Rip rap, class I (3628000000-E) | TON | 10 | $86.00 | $100.00 | $100.00 | $150.00 | $210.00 | $77.00 |
| 0053 | Rip rap, class II (3635000000-E) | TON | 640 | $92.00 | $75.00 | $125.00 | $110.00 | $140.00 | $77.00 |
| 0054 | Rip rap, class B (3649000000-E) | TON | 280 | $70.00 | $70.00 | $100.00 | $100.00 | $130.00 | $64.00 |
| 0055 | Geotextile for drainage (3656000000-E) | SY | 2,825 | $2.00 | $3.00 | $5.00 | $5.50 | $8.76 | $3.00 |
| 0056 | Sign erect, reloc ** GRD MTD - (D) (4116100000-N) | EACH | 2 | $275.00 | $275.00 | $268.00 | $250.00 | $1,161.84 | $585.00 |
| 0057 | Sign erect, reloc ** GRD MTD - (E) (4116100000-N) | EACH | 2 | $250.00 | $250.00 | $268.00 | $250.00 | $871.38 | $420.00 |
| 0058 | Work zone signs (stationary) (4400000000-E) | SF | 70 | $15.00 | $15.50 | $9.50 | $8.65 | $30.80 | $18.00 |
| 0059 | Work zone signs (portable) (4405000000-E) | SF | 330 | $8.45 | $8.45 | $9.50 | $8.55 | $9.99 | $12.00 |
| 0060 | Work zone signs (barricade mounted) (4410000000-E) | SF | 190 | $6.25 | $6.25 | $9.50 | $8.95 | $9.51 | $10.00 |
| 0061 | Drums (4430000000-N) | EACH | 70 | $54.50 | $125.00 | $50.00 | $46.00 | $115.44 | $75.00 |
| 0062 | Barricades (type III) (4445000000-E) | LF | 72 | $16.50 | $16.50 | $26.50 | $25.00 | $28.11 | $42.00 |
| 0063 | Flagger (4455000000-N) | DAY | 60 | $340.00 | $350.00 | $350.00 | $1,500.00 | $538.02 | $1,500.00 |
| 0064 | Temporary raised pavement markers (4650000000-N) | EACH | 40 | $51.60 | $15.00 | $15.00 | $15.00 | $73.70 | $50.00 |
| 0065 | Thermoplastic pavement marking lines (6", 90 mils) (4688000000-E) | LF | 6,000 | $1.52 | $1.25 | $1.25 | $1.25 | $2.17 | $1.50 |
| 0066 | Paint pavement marking lines (6") (4815000000-E) | LF | 14,200 | $0.30 | $0.50 | $0.50 | $0.50 | $0.43 | $0.50 |
| 0067 | Removal of pavement marking lines (6") (4855000000-E) | LF | 1,200 | $5.46 | $1.00 | $1.00 | $1.00 | $7.80 | $5.50 |
| 0068 | Generic pavement marking item (EA) - polycarbonate H-shaped markers (4895000000-N) | EACH | 20 | $315.67 | $100.00 | $100.00 | $100.00 | $450.90 | $310.00 |
| 0069 | Temporary silt fence (6000000000-E) | LF | 7,855 | $3.05 | $3.00 | $2.50 | $5.08 | $3.18 | $4.90 |
| 0070 | Stone for erosion control, class A (6006000000-E) | TON | 245 | $67.00 | $60.00 | $75.00 | $100.00 | $130.00 | $56.00 |
| 0071 | Stone for erosion control, class B (6009000000-E) | TON | 1,165 | $70.00 | $40.00 | $100.00 | $105.00 | $130.00 | $58.00 |
| 0072 | Sediment control stone (6012000000-E) | TON | 750 | $58.00 | $40.00 | $75.00 | $75.00 | $110.00 | $50.00 |
| 0073 | Temporary mulching (6015000000-E) | ACRE | 9 | $1,429.00 | $1,500.00 | $1,500.00 | $1,524.10 | $2,522.76 | $2,000.00 |
| 0074 | Seed for temporary seeding (6018000000-E) | LB | 500 | $1.00 | $5.00 | $5.00 | $5.08 | $3.85 | $2.50 |
| 0075 | Fertilizer for temporary seeding (6021000000-E) | TON | 2.50 | $829.00 | $1,900.00 | $1,900.00 | $1,930.52 | $1,822.00 | $1,200.00 |
| 0076 | Temporary slope drains (6024000000-E) | LF | 770 | $21.00 | $5.00 | $25.00 | $35.00 | $45.64 | $24.00 |
| 0077 | Safety fence (6029000000-E) | LF | 260 | $1.50 | $2.50 | $4.00 | $5.08 | $5.34 | $6.00 |
| 0078 | Silt excavation (6030000000-E) | CY | 2,000 | $15.00 | $5.00 | $15.00 | $15.00 | $13.63 | $23.00 |
| 0079 | Matting for erosion control (6036000000-E) | SY | 10,050 | $1.50 | $1.75 | $1.75 | $1.78 | $2.23 | $2.00 |
| 0080 | Coir fiber mat (6037000000-E) | SY | 100 | $4.60 | $4.00 | $4.00 | $4.06 | $16.00 | $7.00 |
| 0081 | 1/4" hardware cloth (6042000000-E) | LF | 835 | $6.00 | $5.00 | $4.50 | $7.11 | $5.75 | $6.00 |
| 0082 | **" temporary pipe - (24") (6045000000-E) | LF | 75 | $83.00 | $100.00 | $150.00 | $175.00 | $195.00 | $71.00 |
| 0083 | Floating turbidity curtain (6048000000-E) | SY | 230 | $30.00 | $25.00 | $45.00 | $30.48 | $14.35 | $17.00 |
| 0084 | Special stilling basins (6070000000-N) | EACH | 9 | $200.00 | $500.00 | $525.00 | $3,250.00 | $1,985.00 | $4,750.00 |
| 0085 | Flocculant (6071002000-E) | LB | 265 | $13.00 | $10.00 | $20.00 | $30.48 | $7.15 | $6.00 |
| 0086 | Coir fiber baffle (6071030000-E) | LF | 50 | $10.00 | $6.00 | $8.00 | $10.16 | $27.00 | $11.75 |
| 0087 | Seeding and mulching (6084000000-E) | ACRE | 9 | $2,395.00 | $2,300.00 | $2,300.00 | $2,336.95 | $3,925.00 | $3,300.00 |
| 0088 | Mowing (6087000000-E) | ACRE | 6 | $249.00 | $200.00 | $200.00 | $203.21 | $140.00 | $300.00 |
| 0089 | Seed for repair seeding (6090000000-E) | LB | 100 | $8.95 | $6.00 | $6.00 | $6.10 | $7.00 | $5.00 |
| 0090 | Fertilizer for repair seeding (6093000000-E) | TON | 0.25 | $1,125.00 | $2,100.00 | $2,100.00 | $2,133.74 | $1,540.00 | $1,880.00 |
| 0091 | Seed for supplemental seeding (6096000000-E) | LB | 200 | $8.95 | $4.00 | $4.00 | $4.06 | $8.40 | $5.00 |
| 0092 | Fertilizer topdressing (6108000000-E) | TON | 5.50 | $1,689.00 | $1,950.00 | $1,950.00 | $1,981.33 | $1,120.00 | $1,200.00 |
| 0093 | Impervious dike (6111000000-E) | LF | 55 | $154.00 | $100.00 | $58.00 | $182.73 | $200.00 | $6,500.00 |
| 0094 | Specialized hand mowing (6114500000-N) | MHR | 10 | $95.00 | $75.00 | $75.00 | $76.20 | $350.38 | $205.00 |
| 0095 | Manual litter removal (6114800000-N) | MHR | 4 | $125.00 | $75.00 | $50.00 | $200.00 | $260.00 | $200.00 |
| 0096 | Litter disposal (6114900000-E) | TON | 1 | $1,000.00 | $250.00 | $1,250.00 | $1,500.00 | $385.00 | $420.00 |
| 0097 | Response for erosion control (6117000000-N) | EACH | 75 | $95.00 | $100.00 | $100.00 | $102.00 | $70.00 | $300.00 |
| 0098 | Concrete washout structure (6117500000-N) | EACH | 1 | $750.00 | $1,500.00 | $4,800.00 | $1,500.00 | $4,500.00 | $1,000.00 |
| 0099 | Reforestation (6123000000-E) | ACRE | 1 | $6,500.00 | $1,200.00 | $1,200.00 | $1,219.28 | $4,200.00 | $17,000 |
| 0100 | Generic erosion control item (EA) - prefabricated concrete washout (6132000000-N) | EACH | 6 | $300.00 | $1,000.00 | $2,000.00 | $1,500.00 | $400.00 | $2,000.00 |
| 0101 | CM&R temp STR *********** - (18+04.74 -L-) (8007000000-N) | LS | 1 | $1,380,000 | $1,350,000 | $1,504,900 | $1,000,000 | $1,368,000 | $1,100,000 |
| 0102 | Remv exist STR ****** BRG (402) - (18+04.74 -L-) (8035000000-N) | LS | 1 | $100,000 | $200,000 | $420,000 | $400,000 | $165,000 | $148,000 |
| 0103 | Asbestos assessment (8065000000-N) | LS | 1 | $1,800.00 | $300,000 | $800.00 | $15,000 | $2,800.00 | $5,900.00 |
| 0104 | 3'-6" dia drilled piers in soil (8105540000-E) | LF | 80.50 | $1,750.00 | $1,250.00 | $2,000.00 | $800.00 | $1,325.00 | $2,100.00 |
| 0105 | 3'-6" dia drilled piers not in soil (8105640000-E) | LF | 28 | $2,200.00 | $2,500.00 | $3,000.00 | $2,100.00 | $2,815.00 | $4,800.00 |
| 0106 | CSL testing (8115000000-N) | EACH | 2 | $4,660.00 | $2,500.00 | $1,000.00 | $5,500.00 | $2,800.00 | $8,100.00 |
| 0107 | Uncl STR excav sta ***** - (18+04.74 -L-) (8121000000-N) | LS | 1 | $39,300 | $10,000 | $30,000 | $39,831 | $18,500 | $17,000 |
| 0108 | Reinforced concrete deck slab (8147000000-E) | SF | 6,280 | $55.00 | $60.00 | $60.00 | $80.00 | $80.00 | $76.00 |
| 0109 | Grooving bridge floors (8161000000-E) | SF | 6,145 | $2.00 | $1.25 | $0.75 | $2.00 | $1.75 | $2.50 |
| 0110 | Class A concrete (bridge) (8182000000-E) | CY | 111.80 | $1,500.00 | $1,000.00 | $2,950.00 | $2,500.00 | $2,530.00 | $2,000.00 |
| 0111 | BRG appr slab *********** - (18+04.74 -L-) (8210000000-N) | LS | 1 | $50,000 | $45,000 | $35,000 | $50,000 | $95,000 | $64,500 |
| 0112 | Reinforcing steel (bridge) (8217000000-E) | LB | 25,108 | $1.60 | $1.75 | $4.00 | $1.50 | $2.10 | $2.00 |
| 0113 | Spiral column reinforcing steel (bridge) (8238000000-E) | LB | 3,264 | $2.50 | $3.00 | $4.50 | $3.75 | $4.00 | $2.55 |
| 0114 | 45" prestressed concrete girders (8262000000-E) | LF | 628.17 | $325.00 | $450.00 | $550.00 | $425.00 | $600.00 | $475.00 |
| 0115 | Pile DRV equip setup ** steel piles - (HP 12 X 53) (8328200000-E) | EACH | 12 | $850.00 | $1,500.00 | $5,000.00 | $9,000.00 | $1,650.00 | $1,450.00 |
| 0116 | HP 12 X 53 steel piles (8364000000-E) | LF | 435 | $75.00 | $45.00 | $45.00 | $41.00 | $150.00 | $90.00 |
| 0117 | Dynamic pile testing (8394000000-N) | EACH | 1 | $3,500.00 | $3,000.00 | $2,200.00 | $7,500.00 | $1,495.00 | $3,550.00 |
| 0118 | Concrete barrier rail (8503000000-E) | LF | 316.55 | $158.00 | $160.00 | $160.00 | $130.00 | $315.00 | $195.00 |
| 0119 | Rip rap class II (2'-0" thick) (8608000000-E) | TON | 1,040 | $50.00 | $75.00 | $70.00 | $119.00 | $150.00 | $85.00 |
| 0120 | Geotextile for drainage (8622000000-E) | SY | 1,154 | $5.00 | $3.00 | $6.00 | $5.00 | $8.50 | $4.00 |
| 0121 | Elastomeric bearings (8657000000-N) | LS | 1 | $10,000 | $7,500.00 | $25,000 | $20,000 | $46,566 | $12,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NCDOT's tabulation for this contract. NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
Every contract let that day: NCDOT letting of January 20, 2026. Compiled by Mirage Metrics.