Thermoplastic pavement marking lines (6", 90 mils), NCDOT 4688000000-E
Low bidders on NCDOT contracts carried a median of $0.80 per LF for this item, over the 24 months to 20 OCT 2026, across 103 low bids. Half of all 387 bids fell between $0.67 and $1.25.
- Owner
- North Carolina DOT
- Item
- 4688000000-E
- Unit
- LF
- Data through
- 20 OCT 2026
NCDOT prints this item as “THERMO PVT MKG LINES,6"90 MILS”.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2013 | 14 | 14 | $0.68 | 45 | $0.80 |
| 2014 | 15 | 15 | $0.85 | 73 | $0.89 |
| 2015 | 19 | 19 | $0.83 | 68 | $0.89 |
| 2016 | 20 | 20 | $0.80 | 52 | $0.80 |
| 2017 | 10 | 10 | $0.90 | 48 | $0.99 |
| 2018 | 23 | 23 | $0.94 | 77 | $0.96 |
| 2019 | 14 | 14 | $0.90 | 49 | $0.98 |
| 2020 | 8 | 8 | $0.77 | 27 | $0.95 |
| 2021 | 27 | 27 | $0.93 | 90 | $0.99 |
| 2022 | 35 | 35 | $1.00 | 104 | $1.00 |
| 2023 | 31 | 31 | $1.25 | 126 | $1.25 |
| 2024 | 38 | 38 | $0.98 | 154 | $1.10 |
| 2025 | 46 | 46 | $0.80 | 159 | $0.81 |
| 2026 | 45 | 45 | $0.75 | 177 | $0.80 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Wake | 9 | $0.81 | 40 | $0.81 |
| Wayne | 4 | $1.45 | 26 | $1.70 |
| Randolph | 4 | $0.52 | 18 | $0.62 |
| Brunswick | 3 | $0.67 | 15 | $0.67 |
| Pender | 3 | $0.78 | 13 | $0.78 |
| Alamance | 3 | $1.20 | 12 | $1.00 |
| Lee | 3 | $0.68 | 11 | $0.68 |
| Moore | 3 | $0.66 | 10 | $0.66 |
| Chatham | 3 | $0.64 | 10 | $0.64 |
| Forsyth | 3 | $0.80 | 10 | $0.80 |
| Richmond | 3 | $0.82 | 7 | $0.82 |
| Union | 3 | $0.65 | 7 | $0.65 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 46 to 13,416 | 25 | $1.52 |
| 15,100 to 94,338 | 26 | $0.82 |
| 94,628 to 233,820 | 26 | $0.68 |
| 243,038 to 703,157 | 26 | $0.67 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Barnhill Contracting Company | 125 | 98 (78%) |
| S T Wooten Corporation | 117 | 98 (84%) |
| FSC II LLC DBA Fred Smith Company | 117 | 89 (76%) |
| Blythe Construction Inc | 90 | 52 (58%) |
| Apac - Atlantic, Inc. Thompson Arthur Division | 36 | 30 (83%) |
| Highland Paving Co LLC | 34 | 28 (82%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 20 OCT 2026 | C205216 | Martin | 44,083 | $0.85 | $0.85 | 4 | Barnhill Contracting Company | NCDOT |
| 20 OCT 2026 | C205207 | Pender | 9,950 | $1.25 | $1.31 | 5 | S T Wooten Corporation | NCDOT |
| 20 OCT 2026 | C205247 | Rowan | 280,268 | $0.79 | $0.79 | 2 | NJR Group Inc | NCDOT |
| 20 OCT 2026 | C205236 | Union | 85,056 | $0.85 | $0.85 | 3 | Truerock Construction LLC | NCDOT |
| 20 OCT 2026 | C205246 | Polk | 164,358 | $0.80 | $0.80 | 4 | Rogers Group, Inc. | NCDOT |
| 15 SEP 2026 | C205203 | Wayne | 13,416 | $1.05 | $1.70 | 6 | Legion Asphalt Inc | NCDOT |
| 15 SEP 2026 | C205233 | Wake | 134,605 | $0.80 | $0.80 | 4 | Blythe Construction Inc | NCDOT |
| 15 SEP 2026 | C204349 | Wake, Durham | 269,800 | $1.05 | $1.05 | 4 | Blythe Construction Inc | NCDOT |
| 15 SEP 2026 | C205234 | Rockingham | 332,155 | $0.54 | $0.76 | 3 | Apac - Atlantic, Inc. Thompson Arthur Division | NCDOT |
| 18 AUG 2026 | C205195 | Catawba | 16,465 | $1.88 | $1.10 | 4 | Blythe Development Co. | NCDOT |
| 18 AUG 2026 | C205205 | Robeson | 8,478 | $2.52 | $1.79 | 2 | Bmco Construction, Inc. | NCDOT |
| 18 AUG 2026 | C205070 | Rutherford | 5,750 | $1.75 | $1.75 | 9 | United Infrastructure Group Inc | NCDOT |
| 21 JUL 2026 | C205183 | Nash | 1,240 | $2.00 | $2.00 | 2 | FSC II LLC DBA Fred Smith Company | NCDOT |
| 16 JUN 2026 | C205182 | Carteret | 32,525 | $0.75 | $0.75 | 2 | Barnhill Contracting Company | NCDOT |
| 16 JUN 2026 | C205213 | New Hanover | 315,241 | $0.63 | $0.63 | 3 | Barnhill Contracting Company | NCDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.
How these prices were read
NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the NCDOT letting of 20 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way