NCDOT contract C205032 bid tabulation
DRAINAGE, GRADING, PAVING, SIGNALS, AND STRUCTURES. SR-2700 (CHATHAM PARK WAY) FROM US-15/US-501 SOUTH OF PITTSBORO TO US-64 BUSINESS. Let by North Carolina DOT on May 20, 2025, Chatham. 12 bids received; low bid $39,590,000 by FSC II LLC DBA Fred Smith Company.
- Owner
- North Carolina DOT
- Letting
- 20 MAY 2025
- Pay items
- 266
- Data through
- 20 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | FSC II LLC DBA Fred Smith Company | $39,590,000 | Low |
| 2 | Branch Civil Inc | $40,680,585 | +3.0% |
| 3 | Cardinal Civil Contracting LLC | $41,693,022 | +5.0% |
| 4 | Blythe Construction Inc | $41,853,734 | +6.0% |
| 5 | S T Wooten Corporation | $42,990,858 | +9.0% |
| 6 | Triangle Grading & Paving Inc | $43,390,059 | +10% |
| 7 | Vecellio & Grogan Inc | $43,695,000 | +10% |
| 8 | Sanford Contractors Inc | $47,315,185 | +20% |
| 9 | Barnhill Contracting Company | $48,926,071 | +24% |
| 10 | The Beaver Excavating Co. | $51,783,939 | +31% |
| 11 | Zachry Construction Corporation | $52,756,960 | +33% |
| 12 | Blythe Development Co. | $60,145,921 | +52% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. FSC II LLC DBA Fred Smith Company | 2. Branch Civil Inc | 3. Cardinal Civil Contracting LLC | 4. Blythe Construction Inc | 5. S T Wooten Corporation | 6. Triangle Grading & Paving Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Mobilization (0000100000-N) | LS | 1 | $1,979,500 | $2,000,000 | $1,515,000 | $2,145,000 | $2,145,500 | $2,150,000 |
| 0002 | Construction surveying (0000400000-N) | LS | 1 | $500,000 | $384,200 | $425,000 | $135,000 | $1,150,000 | $400,000 |
| 0003 | Clearing & grubbing (0001000000-E) | LS | 1 | $4,060,200 | $995,000 | $1,690,000 | $1,500,000 | $2,125,000 | $4,250,000 |
| 0004 | Sealing abandoned wells (0015000000-N) | EACH | 2 | $2,500.00 | $3,325.00 | $3,000.00 | $2,500.00 | $2,500.00 | $3,500.00 |
| 0005 | Unclassified excavation (0022000000-E) | CY | 457,000 | $5.20 | $7.75 | $10.00 | $12.00 | $8.90 | $10.25 |
| 0006 | Undercut excavation (0036000000-E) | CY | 12,375 | $14.00 | $6.25 | $31.50 | $10.00 | $21.00 | $14.00 |
| 0007 | Supplementary clearing & grubbing (0050000000-E) | ACRE | 3 | $7,000.00 | $8,100.00 | $10,000 | $500.00 | $4,800.00 | $3,500.00 |
| 0008 | Embankment settlement gauges (0127000000-N) | EACH | 5 | $2,300.00 | $2,517.00 | $875.00 | $2,000.00 | $2,425.00 | $2,800.00 |
| 0009 | Drainage ditch excavation (0134000000-E) | CY | 1,530 | $13.00 | $12.75 | $15.50 | $12.00 | $21.00 | $9.00 |
| 0010 | Berm ditch construction (0141000000-E) | LF | 2,700 | $4.50 | $8.00 | $9.70 | $6.00 | $5.00 | $6.00 |
| 0011 | Removal of existing asphalt pavement (0156000000-E) | SY | 350 | $7.00 | $6.00 | $4.80 | $22.00 | $5.00 | $5.00 |
| 0012 | Proof rolling (0192000000-N) | HR | 30 | $350.00 | $240.00 | $250.00 | $300.00 | $365.00 | $250.00 |
| 0013 | Select granular material, class III (0194000000-E) | CY | 8,275 | $30.00 | $55.00 | $50.50 | $45.00 | $49.00 | $30.00 |
| 0014 | Geotextile for soil stabilization (0196000000-E) | SY | 12,025 | $5.50 | $2.65 | $3.50 | $5.00 | $4.25 | $3.50 |
| 0015 | Geotextile for rock embankments (0222000000-E) | SY | 3,180 | $3.86 | $3.60 | $3.40 | $5.00 | $3.70 | $7.00 |
| 0016 | Generic grading item (LS) - type 1 bridge approach fill, station 134+65 -L- LT (0248000000-N) | LS | 1 | $38,000 | $62,685 | $56,600 | $55,000 | $54,500 | $80,066 |
| 0017 | Generic grading item (LS) - type 1 bridge approach fill, station 134+65 -L- RT (0248000000-N) | LS | 1 | $38,000 | $62,685 | $56,600 | $55,000 | $54,500 | $80,070 |
| 0018 | Generic grading item (LS) - type 1 bridge approach fill, station 76+49.00 -L- (0248000000-N) | LS | 1 | $55,000 | $78,315 | $70,700 | $55,000 | $72,000 | $80,070 |
| 0019 | Generic grading item (TON) - select material, class VI for rock embankments (0255000000-E) | TON | 1,730 | $39.00 | $46.50 | $38.00 | $45.00 | $33.50 | $35.00 |
| 0020 | Generic grading item (TON) - select material, class VII for rock embankments (0255000000-E) | TON | 16,640 | $60.00 | $5.00 | $58.00 | $55.00 | $59.00 | $56.00 |
| 0021 | Foundation conditioning material, minor structures (0318000000-E) | TON | 3,984.25 | $20.00 | $57.00 | $38.50 | $45.00 | $1.00 | $45.00 |
| 0022 | FND condit geotextile (4A) (0321000000-E) | SY | 8,942.25 | $1.00 | $3.75 | $4.40 | $5.00 | $1.00 | $5.00 |
| 0023 | 15" drainage pipe (0335200000-E) | LF | 116 | $75.00 | $85.25 | $60.50 | $70.00 | $135.00 | $60.00 |
| 0024 | 18" drainage pipe (0335300000-E) | LF | 104 | $84.00 | $84.25 | $76.00 | $80.00 | $110.00 | $70.00 |
| 0025 | 24" drainage pipe (0335400000-E) | LF | 112 | $94.00 | $97.00 | $72.00 | $85.00 | $120.00 | $80.00 |
| 0026 | 30" drainage pipe (0335500000-E) | LF | 48 | $115.00 | $125.50 | $110.00 | $100.00 | $157.00 | $90.00 |
| 0027 | **" drainage pipe elbow - (15") (0335850000-E) | EACH | 6 | $570.00 | $446.00 | $470.00 | $120.00 | $506.00 | $550.00 |
| 0028 | **" drainage pipe elbow - (18") (0335850000-E) | EACH | 4 | $650.00 | $584.50 | $555.00 | $200.00 | $621.00 | $600.00 |
| 0029 | **" drainage pipe elbow - (24") (0335850000-E) | EACH | 4 | $730.00 | $689.50 | $795.00 | $180.00 | $1,032.00 | $750.00 |
| 0030 | **" drainage pipe elbow - (30") (0335850000-E) | EACH | 2 | $840.00 | $1,066.00 | $1,400.00 | $420.00 | $1,346.00 | $950.00 |
| 0031 | 15" side drain pipe (0343000000-E) | LF | 140 | $68.00 | $39.75 | $73.00 | $60.00 | $135.00 | $60.00 |
| 0032 | ***" RCP culv class IV - (48") (0448000000-E) | LF | 428 | $300.00 | $391.50 | $315.00 | $300.00 | $400.00 | $350.00 |
| 0033 | 15" RC pipe culverts, class IV (0448200000-E) | LF | 8,184 | $76.50 | $88.25 | $77.50 | $55.00 | $91.00 | $70.00 |
| 0034 | 18" RC pipe culverts, class IV (0448300000-E) | LF | 11,372 | $88.00 | $91.00 | $91.00 | $65.00 | $100.00 | $80.00 |
| 0035 | 24" RC pipe culverts, class IV (0448400000-E) | LF | 3,744 | $122.00 | $134.00 | $120.00 | $90.00 | $132.00 | $105.00 |
| 0036 | 30" RC pipe culverts, class IV (0448500000-E) | LF | 1,436 | $164.00 | $178.00 | $145.00 | $115.00 | $182.00 | $140.00 |
| 0037 | 36" RC pipe culverts, class IV (0448600000-E) | LF | 264 | $214.00 | $233.00 | $190.00 | $180.00 | $228.00 | $185.00 |
| 0038 | **" RC pipe culv class V - (42") (0449000000-E) | LF | 112 | $290.00 | $363.50 | $440.00 | $300.00 | $357.00 | $300.00 |
| 0039 | Pipe removal (0995000000-E) | LF | 565 | $20.00 | $56.25 | $22.00 | $30.00 | $46.00 | $24.00 |
| 0040 | Fine grading (1011000000-N) | LS | 1 | $902,000 | $650,376 | $1,859,000 | $2,250,000 | $2,225,000 | $1,800,000 |
| 0041 | Lime treated soil (slurry method) (1044000000-E) | SY | 56,500 | $3.80 | $3.90 | $3.50 | $3.46 | $3.55 | $5.29 |
| 0042 | Lime for lime treated soil used based on county (1066000000-E) | TON | 700 | $350.00 | $346.50 | $310.00 | $306.94 | $347.00 | $308.00 |
| 0043 | Shallow undercut (1099500000-E) | CY | 1,500 | $23.00 | $11.25 | $25.00 | $11.00 | $30.00 | $29.00 |
| 0044 | Class IV subgrade stabilization (1099700000-E) | TON | 7,810 | $28.00 | $30.25 | $29.50 | $30.00 | $35.00 | $27.00 |
| 0045 | Stabilizer aggregate (1110000000-E) | TON | 500 | $30.00 | $30.25 | $39.50 | $45.00 | $35.00 | $30.00 |
| 0046 | Geotextile for subgrade stabilization (1112000000-E) | SY | 15,130 | $3.20 | $3.55 | $3.30 | $5.00 | $3.00 | $3.75 |
| 0047 | Aggregate base course (1121000000-E) | TON | 13,600 | $35.00 | $33.50 | $26.50 | $40.00 | $40.00 | $31.00 |
| 0048 | Soil cement base (1176000000-E) | SY | 56,500 | $3.20 | $4.00 | $3.58 | $3.46 | $3.20 | $5.29 |
| 0049 | Portland cement for soil cement base (1187000000-E) | TON | 1,600 | $253.00 | $249.50 | $222.00 | $215.15 | $253.00 | $232.00 |
| 0050 | Incidental stone base (1220000000-E) | TON | 100 | $80.00 | $39.25 | $44.50 | $45.00 | $50.00 | $35.00 |
| 0051 | Shoulder borrow (1231000000-E) | CY | 4,900 | $18.00 | $14.50 | $41.00 | $6.50 | $11.00 | $8.50 |
| 0052 | Prime coat (1275000000-E) | GAL | 56 | $20.00 | $11.00 | $25.00 | $25.00 | $45.00 | $5.00 |
| 0053 | Mill asp PVMT *****" DTH - (1-1/2") (1297000000-E) | SY | 1,150 | $7.50 | $7.50 | $6.75 | $8.60 | $5.00 | $6.50 |
| 0054 | Mill asp PVMT *****" DTH - (2-1/2") (1297000000-E) | SY | 6,150 | $6.00 | $5.25 | $4.75 | $1.80 | $5.15 | $5.75 |
| 0055 | Incidental milling (1330000000-E) | SY | 950 | $18.00 | $13.00 | $20.00 | $8.14 | $10.15 | $18.00 |
| 0056 | Asphalt conc base course, type B25.0C (1491000000-E) | TON | 22,000 | $72.00 | $88.00 | $77.00 | $81.00 | $81.50 | $78.00 |
| 0057 | Asphalt conc intermediate course, type I19.0C (1503000000-E) | TON | 27,000 | $72.00 | $79.00 | $72.00 | $80.00 | $74.25 | $78.00 |
| 0058 | Asphalt conc surface course, type S9.5B (1519000000-E) | TON | 20 | $180.00 | $1,100.00 | $150.00 | $90.00 | $1,000.00 | $80.00 |
| 0059 | Asphalt conc surface course, type S9.5C (1523000000-E) | TON | 24,000 | $72.00 | $93.00 | $69.00 | $90.00 | $87.25 | $80.00 |
| 0060 | Asphalt binder for plant mix (1575000000-E) | TON | 3,705 | $610.00 | $475.00 | $610.00 | $600.00 | $450.00 | $630.00 |
| 0061 | Asphalt plant mix, pavement repair (1693000000-E) | TON | 296 | $200.00 | $305.00 | $180.00 | $178.03 | $258.00 | $250.00 |
| 0062 | Generic paving item (SY) - 12" jointed concrete truck apron (1891000000-E) | SY | 270 | $150.00 | $166.50 | $151.50 | $150.00 | $166.50 | $150.00 |
| 0063 | Right-of-way markers (2000000000-N) | EACH | 4 | $400.00 | $83.25 | $400.00 | $400.00 | $450.00 | $330.00 |
| 0064 | Control-of-access markers (2020000000-N) | EACH | 199 | $350.00 | $83.25 | $400.00 | $100.00 | $450.00 | $350.00 |
| 0065 | Subdrain excavation (2022000000-E) | CY | 4,170 | $35.00 | $41.50 | $66.50 | $35.00 | $35.00 | $35.00 |
| 0066 | Geotextile for subsurface drains (2026000000-E) | SY | 12,400 | $12.00 | $14.25 | $20.50 | $12.00 | $12.00 | $12.00 |
| 0067 | Subdrain coarse aggregate (2036000000-E) | CY | 2,090 | $80.00 | $94.75 | $165.00 | $80.00 | $80.00 | $80.00 |
| 0068 | 6" perforated subdrain pipe (2044000000-E) | LF | 12,400 | $16.00 | $19.00 | $30.00 | $16.00 | $17.00 | $16.00 |
| 0069 | Subdrain pipe outlet (2070000000-N) | EACH | 25 | $400.00 | $474.00 | $1,400.00 | $400.00 | $400.00 | $400.00 |
| 0070 | 6" outlet pipe (2077000000-E) | LF | 150 | $40.00 | $47.50 | $73.50 | $40.00 | $40.00 | $40.00 |
| 0071 | Shoulder drain (2099000000-E) | LF | 300 | $17.00 | $20.25 | $17.00 | $17.00 | $22.79 | $17.00 |
| 0072 | 4" shoulder drain pipe (2110000000-E) | LF | 320 | $4.00 | $4.75 | $4.00 | $4.00 | $5.36 | $4.00 |
| 0073 | 4" outlet pipe for shoulder drains (2121000000-E) | LF | 80 | $21.50 | $25.50 | $21.50 | $21.50 | $28.82 | $21.50 |
| 0074 | Concrete pad for shoulder drain pipe outlet (2132000000-N) | EACH | 4 | $375.00 | $444.50 | $375.00 | $375.00 | $502.75 | $375.00 |
| 0075 | Blotting sand (2143000000-E) | TON | 20 | $120.00 | $77.50 | $135.00 | $450.00 | $112.00 | $150.00 |
| 0076 | Endwalls (2209000000-E) | CY | 22.50 | $1,150.00 | $1,415.00 | $1,050.00 | $2,000.00 | $1,542.00 | $1,350.00 |
| 0077 | Pipe collars (2253000000-E) | CY | 0.60 | $4,000.00 | $1,860.00 | $3,300.00 | $2,500.00 | $6,380.00 | $7,000.00 |
| 0078 | Masonry drainage structures (2286000000-N) | EACH | 275 | $3,950.00 | $3,138.00 | $2,950.00 | $4,000.00 | $3,830.00 | $2,700.00 |
| 0079 | Masonry drainage structures (2308000000-E) | LF | 157 | $250.00 | $364.50 | $525.00 | $500.00 | $705.00 | $590.00 |
| 0080 | Frame with two grates, STD 840.16 (2364000000-N) | EACH | 4 | $1,050.00 | $1,065.00 | $1,200.00 | $1,500.00 | $1,352.00 | $1,300.00 |
| 0081 | Frame with two grates, STD 840.24 (2366000000-N) | EACH | 76 | $995.00 | $897.00 | $1,100.00 | $1,500.00 | $1,210.00 | $1,100.00 |
| 0082 | Frame with two grates, STD 840.29 (2367000000-N) | EACH | 1 | $980.00 | $928.50 | $1,100.00 | $1,500.00 | $1,411.00 | $1,100.00 |
| 0083 | Frame-GRT-HD 840.03 ** - (E) (2374000000-N) | EACH | 15 | $1,135.00 | $1,159.00 | $1,300.00 | $1,500.00 | $1,433.00 | $1,300.00 |
| 0084 | Frame-GRT-HD 840.03 ** - (F) (2374000000-N) | EACH | 91 | $1,175.00 | $1,213.00 | $1,300.00 | $1,500.00 | $1,478.00 | $1,300.00 |
| 0085 | Frame-GRT-HD 840.03 ** - (G) (2374000000-N) | EACH | 53 | $1,175.00 | $1,213.00 | $1,300.00 | $1,500.00 | $1,478.00 | $1,300.00 |
| 0086 | Frame with cover, STD 840.54 (2396000000-N) | EACH | 5 | $835.00 | $763.00 | $1,700.00 | $1,200.00 | $793.03 | $1,000.00 |
| 0087 | Steel frame with two grates, STD 840.37 (2407000000-N) | EACH | 26 | $3,350.00 | $3,138.00 | $2,800.00 | $3,000.00 | $3,760.00 | $3,000.00 |
| 0088 | Concrete transitional section for catch basin (2440000000-N) | EACH | 59 | $1,500.00 | $1,053.00 | $959.50 | $950.00 | $1,175.00 | $950.00 |
| 0089 | Concrete transitional section for drop inlet (2451000000-N) | EACH | 25 | $1,500.00 | $1,053.00 | $959.50 | $950.00 | $1,575.00 | $950.00 |
| 0090 | **"X**" concrete curb - (9" X 18") (2535000000-E) | LF | 270 | $37.60 | $45.75 | $37.98 | $37.60 | $33.00 | $37.60 |
| 0091 | 1'-6" concrete curb & gutter (2542000000-E) | LF | 25,600 | $17.75 | $23.75 | $17.93 | $17.75 | $19.00 | $17.75 |
| 0092 | 2'-6" concrete curb & gutter (2549000000-E) | LF | 17,800 | $25.00 | $31.75 | $25.25 | $25.00 | $29.75 | $25.00 |
| 0093 | Concrete expressway gutter (2577000000-E) | LF | 340 | $54.50 | $64.25 | $54.94 | $54.40 | $46.50 | $54.40 |
| 0094 | Concrete curb ramps (2605000000-N) | EACH | 120 | $2,650.00 | $2,938.00 | $2,676.50 | $2,650.00 | $2,500.00 | $2,650.00 |
| 0095 | 6" concrete driveway (2612000000-E) | SY | 370 | $84.60 | $93.75 | $85.45 | $84.69 | $101.50 | $84.60 |
| 0096 | 4" concrete paved ditch (2619000000-E) | SY | 40 | $200.00 | $196.50 | $166.65 | $165.00 | $245.00 | $165.00 |
| 0097 | 5" monolithic concrete islands (keyed in) (2655000000-E) | SY | 3,460 | $69.75 | $77.25 | $70.45 | $69.75 | $82.50 | $69.75 |
| 0098 | Steel beam guardrail (3030000000-E) | LF | 2,125 | $23.00 | $25.50 | $23.00 | $23.00 | $23.00 | $24.00 |
| 0099 | Additional guardrail posts (3150000000-N) | EACH | 10 | $44.00 | $48.75 | $44.00 | $44.00 | $44.00 | $20.00 |
| 0100 | Guardrail end units, type cat-1 (3210000000-N) | EACH | 7 | $950.00 | $1,053.00 | $950.00 | $950.00 | $950.00 | $950.00 |
| 0101 | Guardrail end units, type TL-3 (3287000000-N) | EACH | 11 | $3,250.00 | $3,603.00 | $3,250.00 | $3,250.00 | $3,250.00 | $3,400.00 |
| 0102 | Guardrail anchor units, type B-77 (3317000000-N) | EACH | 12 | $2,450.00 | $2,716.00 | $2,450.00 | $2,450.00 | $2,450.00 | $2,750.00 |
| 0103 | Generic fencing item (LF) - bicycle/pedestrian safety rail (3575000000-E) | LF | 1,010 | $231.00 | $256.00 | $231.00 | $231.00 | $231.00 | $233.00 |
| 0104 | Rip rap, class I (3628000000-E) | TON | 520 | $62.00 | $97.50 | $82.50 | $55.00 | $71.00 | $52.00 |
| 0105 | Rip rap, class A (3642000000-E) | TON | 2,380 | $50.00 | $97.50 | $76.00 | $55.00 | $67.00 | $40.00 |
| 0106 | Rip rap, class B (3649000000-E) | TON | 4,440 | $50.00 | $79.25 | $65.50 | $55.00 | $71.00 | $50.00 |
| 0107 | Geotextile for drainage (3656000000-E) | SY | 8,820 | $3.25 | $3.80 | $4.00 | $5.00 | $3.00 | $4.50 |
| 0108 | Contr furn, type ***sign - (A) (4025000000-E) | SF | 2,970 | $33.00 | $36.50 | $15.00 | $33.00 | $33.00 | $33.00 |
| 0109 | Contr furn, type ***sign - (B) (4025000000-E) | SF | 165 | $33.00 | $36.50 | $15.00 | $33.00 | $33.00 | $33.00 |
| 0110 | Contr furn, type ***sign - (D) (4025000000-E) | SF | 203 | $20.00 | $22.25 | $15.00 | $20.00 | $20.00 | $15.00 |
| 0111 | Contr furn, type ***sign - (E) (4025000000-E) | SF | 985 | $20.00 | $22.25 | $15.00 | $20.00 | $20.00 | $15.00 |
| 0112 | Contr furn, type ***sign - (F) (4025000000-E) | SF | 1,114 | $20.00 | $22.25 | $15.00 | $20.00 | $20.00 | $15.00 |
| 0113 | Reinforced concrete sign foundations (4048000000-E) | CY | 9 | $900.00 | $997.50 | $1,000.00 | $900.00 | $900.00 | $900.00 |
| 0114 | Supports, breakaway steel beam (4060000000-E) | LB | 8,593 | $7.50 | $8.25 | $10.00 | $7.50 | $7.50 | $7.50 |
| 0115 | Supports, 3-LB steel U-channel (4072000000-E) | LF | 4,915 | $12.00 | $13.25 | $9.99 | $12.00 | $12.00 | $9.99 |
| 0116 | Sign erection, type D (4096000000-N) | EACH | 13 | $200.00 | $221.50 | $75.00 | $200.00 | $200.00 | $75.00 |
| 0117 | Sign erection, type E (4102000000-N) | EACH | 125 | $60.00 | $66.50 | $65.00 | $60.00 | $60.00 | $65.00 |
| 0118 | Sign erection, type F (4108000000-N) | EACH | 63 | $200.00 | $221.50 | $55.00 | $200.00 | $200.00 | $55.00 |
| 0119 | Sign erection, type *** (GRD MTD) - (A) (4110000000-N) | EACH | 20 | $750.00 | $831.50 | $150.00 | $750.00 | $750.00 | $750.00 |
| 0120 | Sign erection, type *** (GRD MTD) - (B) (4110000000-N) | EACH | 6 | $450.00 | $499.00 | $750.00 | $450.00 | $450.00 | $450.00 |
| 0121 | Sign erect, reloc ** GRD MTD - (F) (4116100000-N) | EACH | 33 | $350.00 | $388.00 | $65.00 | $350.00 | $350.00 | $65.00 |
| 0122 | Disposal of sign system, steel beam (4152000000-N) | EACH | 6 | $500.00 | $554.50 | $20.00 | $500.00 | $500.00 | $20.00 |
| 0123 | Disposal of sign system, U-channel (4155000000-N) | EACH | 24 | $10.00 | $11.00 | $10.00 | $10.00 | $10.00 | $10.00 |
| 0124 | Disposal of sign, A & B (ground mounted) (4236000000-N) | EACH | 12 | $50.00 | $55.50 | $10.00 | $50.00 | $50.00 | $50.00 |
| 0125 | Disposal of sign, D, E or F (4238000000-N) | EACH | 33 | $10.00 | $11.00 | $20.00 | $10.00 | $10.00 | $20.00 |
| 0126 | Work zone signs (stationary) (4400000000-E) | SF | 144 | $15.00 | $14.75 | $6.25 | $6.25 | $8.90 | $6.25 |
| 0127 | Work zone signs (portable) (4405000000-E) | SF | 768 | $12.00 | $14.50 | $20.00 | $13.00 | $26.75 | $20.00 |
| 0128 | Work zone signs (barricade mounted) (4410000000-E) | SF | 368 | $6.50 | $15.00 | $6.50 | $6.50 | $9.15 | $20.00 |
| 0129 | Drums (4430000000-N) | EACH | 93 | $20.00 | $74.00 | $73.50 | $45.00 | $60.00 | $95.00 |
| 0130 | Cones (4435000000-N) | EACH | 339 | $10.00 | $34.50 | $34.50 | $35.00 | $10.00 | $65.00 |
| 0131 | Barricades (type III) (4445000000-E) | LF | 72 | $25.00 | $41.25 | $19.00 | $19.00 | $25.00 | $49.00 |
| 0132 | Flagger (4455000000-N) | DAY | 80 | $845.00 | $551.50 | $640.00 | $400.00 | $430.00 | $600.00 |
| 0133 | Skinny drum (4516000000-N) | EACH | 131 | $16.00 | $52.75 | $62.00 | $20.00 | $40.00 | $80.00 |
| 0134 | Thermoplastic pavement marking lines (4", 90 mils) (4685000000-E) | LF | 51,500 | $1.10 | $1.20 | $1.10 | $1.10 | $1.10 | $1.10 |
| 0135 | Thermoplastic pavement marking lines (8", 90 mils) (4695000000-E) | LF | 8,200 | $2.00 | $2.20 | $2.00 | $2.00 | $2.00 | $2.00 |
| 0136 | Thermoplastic pavement marking lines (24", 90 mils) (4709000000-E) | LF | 560 | $12.00 | $13.25 | $12.00 | $12.00 | $12.00 | $12.00 |
| 0137 | Thermoplastic pavement marking symbol (90 mils) (4725000000-E) | EACH | 144 | $140.00 | $155.00 | $140.00 | $140.00 | $140.00 | $140.00 |
| 0138 | Paint pavement marking lines (4") (4810000000-E) | LF | 89,000 | $0.30 | $0.35 | $0.30 | $0.30 | $0.30 | $0.30 |
| 0139 | Paint pavement marking lines (8") (4820000000-E) | LF | 2,500 | $0.75 | $0.85 | $0.75 | $0.75 | $0.75 | $0.75 |
| 0140 | Paint pavement marking lines (24") (4835000000-E) | LF | 430 | $4.00 | $4.45 | $4.00 | $4.00 | $4.00 | $4.00 |
| 0141 | Paint pavement marking symbol (4845000000-N) | EACH | 40 | $50.00 | $55.50 | $50.00 | $50.00 | $50.00 | $50.00 |
| 0142 | Polyurea lines (**", *** mils) - (4", 30 mils) (4846000000-E) | LF | 810 | $4.00 | $4.45 | $4.00 | $4.00 | $4.00 | $4.00 |
| 0143 | Generic pavement marking item (LF) - yield line thermoplastic pavement marking (24", 90 mils) (4890000000-E) | LF | 70 | $12.00 | $13.25 | $12.00 | $12.00 | $12.00 | $12.00 |
| 0144 | Generic pavement marking item (EA) - polycarbonate H-shaped markers (4895000000-N) | EACH | 650 | $51.75 | $68.75 | $62.00 | $62.00 | $62.00 | $62.00 |
| 0145 | Permanent raised pavement markers (4900000000-N) | EACH | 5 | $10.00 | $11.00 | $10.00 | $10.00 | $10.00 | $10.00 |
| 0146 | 6" water line (5325600000-E) | LF | 32 | $355.00 | $101.50 | $185.00 | $94.00 | $250.00 | $75.00 |
| 0147 | 8" water line (5325800000-E) | LF | 400 | $165.00 | $116.00 | $115.00 | $107.00 | $125.00 | $105.00 |
| 0148 | 12" water line (5326200000-E) | LF | 9,512 | $109.00 | $133.00 | $115.00 | $123.00 | $126.00 | $115.00 |
| 0149 | 16" water line (5326600000-E) | LF | 588 | $94.00 | $112.50 | $105.00 | $104.00 | $64.00 | $155.00 |
| 0150 | DI H2O pipe fittings (5329000000-E) | LB | 14,800 | $12.00 | $18.00 | $9.40 | $17.00 | $11.65 | $13.00 |
| 0151 | 6" valve (5540000000-E) | EACH | 15 | $2,630.00 | $2,926.00 | $2,550.00 | $2,704.00 | $2,140.00 | $2,900.00 |
| 0152 | 12" valve (5558000000-E) | EACH | 13 | $6,360.00 | $7,765.00 | $5,800.00 | $7,176.00 | $6,265.00 | $6,700.00 |
| 0153 | 6" tapping sleeve & valve (5571600000-E) | EACH | 1 | $8,580.00 | $9,003.00 | $4,679.00 | $8,320.00 | $11,150 | $7,500.00 |
| 0154 | 2" air release valve (5589200000-E) | EACH | 4 | $15,600 | $10,972 | $13,800 | $10,140 | $10,900 | $13,000 |
| 0155 | Relocate water meter (5648000000-N) | EACH | 1 | $2,525.00 | $2,251.00 | $1,500.00 | $2,080.00 | $1,705.00 | $1,650.00 |
| 0156 | Fire hydrant (5666000000-N) | EACH | 16 | $7,225.00 | $8,778.00 | $7,250.00 | $8,112.00 | $5,815.00 | $7,300.00 |
| 0157 | Fire hydrant leg (5673000000-E) | LF | 237 | $90.00 | $67.50 | $96.50 | $62.00 | $125.00 | $90.00 |
| 0158 | Water service line (<2") (5686500000-E) | LF | 92 | $70.00 | $33.75 | $83.00 | $31.00 | $72.00 | $32.00 |
| 0159 | **" force main sewer - (3") (5709000000-E) | LF | 590 | $180.00 | $118.00 | $160.00 | $109.00 | $155.00 | $125.00 |
| 0160 | Ductile iron sewer pipe fittings (5769000000-E) | LB | 800 | $17.00 | $20.25 | $15.50 | $19.00 | $16.85 | $14.00 |
| 0161 | Abandon **" utility pipe - (3") (5798000000-E) | LF | 613 | $17.00 | $13.50 | $29.00 | $12.00 | $8.00 | $16.00 |
| 0162 | Abandon 8" utility pipe (5801000000-E) | LF | 248 | $33.00 | $17.00 | $40.00 | $16.00 | $20.50 | $21.00 |
| 0163 | Abandon 12" utility pipe (5804000000-E) | LF | 118 | $39.00 | $22.50 | $71.00 | $21.00 | $57.00 | $29.00 |
| 0164 | 12" encasement pipe (5835600000-E) | LF | 127 | $195.00 | $163.00 | $180.00 | $151.00 | $186.50 | $150.00 |
| 0165 | 16" encasement pipe (5835700000-E) | LF | 105 | $235.00 | $197.00 | $155.00 | $182.00 | $225.00 | $165.00 |
| 0166 | 20" encasement pipe (5835900000-E) | LF | 1,280 | $305.00 | $214.00 | $140.00 | $198.00 | $253.00 | $175.00 |
| 0167 | 30" encasement pipe (5836200000-E) | LF | 165 | $420.00 | $562.50 | $300.00 | $520.00 | $795.00 | $245.00 |
| 0168 | Bore & jack **" - (20") (5872500000-E) | LF | 108 | $1,100.00 | $2,251.00 | $1,375.00 | $2,080.00 | $1,970.00 | $680.00 |
| 0169 | Direct drill **" - (16") (5872600000-E) | LF | 588 | $800.00 | $963.50 | $796.25 | $890.00 | $800.00 | $1,100.00 |
| 0170 | Generic utility item (LF) - 2" PVC casing (5888000000-E) | LF | 1,744 | $15.00 | $24.75 | $20.00 | $23.00 | $22.30 | $15.00 |
| 0171 | Generic utility item (LF) - 4" PVC casing (5888000000-E) | LF | 6,193 | $24.00 | $29.25 | $22.50 | $27.00 | $25.50 | $19.00 |
| 0172 | Generic utility item (LF) - 6" PVC casing (5888000000-E) | LF | 3,744 | $16.50 | $38.25 | $28.00 | $35.00 | $30.75 | $24.00 |
| 0173 | Temporary silt fence (6000000000-E) | LF | 50,650 | $1.85 | $2.10 | $2.50 | $1.89 | $1.89 | $2.30 |
| 0174 | Stone for erosion control, class A (6006000000-E) | TON | 2,725 | $36.00 | $75.00 | $55.50 | $50.00 | $67.00 | $45.00 |
| 0175 | Stone for erosion control, class B (6009000000-E) | TON | 7,900 | $34.00 | $71.50 | $48.00 | $50.00 | $35.00 | $50.00 |
| 0176 | Sediment control stone (6012000000-E) | TON | 6,965 | $25.00 | $80.50 | $36.50 | $50.00 | $30.00 | $40.00 |
| 0177 | Temporary mulching (6015000000-E) | ACRE | 57 | $1,600.00 | $1,025.00 | $1,475.00 | $925.00 | $925.00 | $1,475.00 |
| 0178 | Seed for temporary seeding (6018000000-E) | LB | 2,500 | $4.00 | $1.10 | $3.00 | $1.00 | $1.00 | $3.00 |
| 0179 | Fertilizer for temporary seeding (6021000000-E) | TON | 13 | $1,000.00 | $1,108.00 | $900.00 | $1,000.00 | $1,000.00 | $900.00 |
| 0180 | Temporary slope drains (6024000000-E) | LF | 3,300 | $16.00 | $35.25 | $25.50 | $20.51 | $10.00 | $25.75 |
| 0181 | Safety fence (6029000000-E) | LF | 2,720 | $1.70 | $2.40 | $3.00 | $2.15 | $2.15 | $2.00 |
| 0182 | Silt excavation (6030000000-E) | CY | 38,800 | $0.01 | $9.25 | $9.20 | $8.00 | $1.00 | $3.25 |
| 0183 | Matting for erosion control (6036000000-E) | SY | 115,000 | $1.50 | $1.60 | $1.45 | $1.45 | $1.45 | $1.45 |
| 0184 | Coir fiber mat (6037000000-E) | SY | 10,100 | $6.00 | $5.50 | $6.00 | $4.99 | $4.99 | $6.00 |
| 0185 | 1/4" hardware cloth (6042000000-E) | LF | 12,400 | $5.00 | $4.45 | $4.00 | $4.00 | $4.00 | $5.50 |
| 0186 | Low permeability geotextile (6043000000-E) | SY | 5,200 | $1.85 | $4.20 | $5.50 | $6.00 | $3.00 | $4.25 |
| 0187 | **" temporary pipe - (15") (6045000000-E) | LF | 170 | $33.00 | $42.00 | $25.50 | $60.60 | $70.00 | $55.00 |
| 0188 | **" temporary pipe - (24") (6045000000-E) | LF | 430 | $50.00 | $55.25 | $39.50 | $60.59 | $73.01 | $65.00 |
| 0189 | Special stilling basins (6070000000-N) | EACH | 16 | $250.00 | $888.50 | $2,300.00 | $203.00 | $675.00 | $750.00 |
| 0190 | Flocculant (6071002000-E) | LB | 3,585 | $8.00 | $1.10 | $8.00 | $1.00 | $1.00 | $8.00 |
| 0191 | Coir fiber wattle (6071012000-E) | LF | 6,570 | $8.00 | $7.75 | $10.50 | $7.00 | $7.00 | $10.50 |
| 0192 | Coir fiber wattle barrier (6071014000-E) | LF | 930 | $8.00 | $10.00 | $15.00 | $9.00 | $9.00 | $12.00 |
| 0193 | Coir fiber baffle (6071030000-E) | LF | 11,310 | $4.50 | $7.75 | $7.00 | $7.00 | $3.50 | $7.00 |
| 0194 | **" skimmer - (1-1/2") (6071050000-E) | EACH | 16 | $2,600.00 | $7,718.00 | $1,525.00 | $974.90 | $3,840.00 | $1,500.00 |
| 0195 | **" skimmer - (2") (6071050000-E) | EACH | 11 | $2,700.00 | $7,988.00 | $1,450.00 | $1,135.78 | $5,660.00 | $1,800.00 |
| 0196 | **" skimmer - (2-1/2") (6071050000-E) | EACH | 1 | $3,265.25 | $8,288.00 | $1,600.61 | $1,355.64 | $5,935.00 | $2,050.00 |
| 0197 | Seeding and mulching (6084000000-E) | ACRE | 51 | $2,600.00 | $2,938.00 | $2,500.00 | $2,650.00 | $2,650.00 | $2,500.00 |
| 0198 | Mowing (6087000000-E) | ACRE | 48 | $225.00 | $166.50 | $225.00 | $150.00 | $150.00 | $225.00 |
| 0199 | Seed for repair seeding (6090000000-E) | LB | 600 | $6.00 | $5.50 | $6.00 | $5.00 | $5.00 | $6.00 |
| 0200 | Fertilizer for repair seeding (6093000000-E) | TON | 2.25 | $900.00 | $1,025.00 | $975.00 | $925.00 | $925.00 | $975.00 |
| 0201 | Seed for supplemental seeding (6096000000-E) | LB | 1,150 | $6.00 | $4.45 | $6.00 | $4.00 | $4.00 | $6.00 |
| 0202 | Fertilizer topdressing (6108000000-E) | TON | 34.25 | $900.00 | $1,053.00 | $1,000.00 | $950.00 | $950.00 | $1,000.00 |
| 0203 | Impervious dike (6111000000-E) | LF | 60 | $150.00 | $25.25 | $125.00 | $100.00 | $77.00 | $100.00 |
| 0204 | Specialized hand mowing (6114500000-N) | MHR | 10 | $225.00 | $166.50 | $175.00 | $150.00 | $150.00 | $175.00 |
| 0205 | Response for erosion control (6117000000-N) | EACH | 125 | $140.00 | $332.50 | $145.00 | $300.00 | $3.00 | $1.00 |
| 0206 | Concrete washout structure (6117500000-N) | EACH | 2 | $1,250.00 | $662.50 | $2,450.00 | $2,138.11 | $1,400.00 | $910.00 |
| 0207 | Reforestation (6123000000-E) | ACRE | 0.50 | $3,500.00 | $4,988.20 | $3,500.00 | $4,500.00 | $4,500.00 | $3,500.00 |
| 0208 | Generic erosion control item (EA) - prefabricated concrete washout (6132000000-N) | EACH | 12 | $1,000.00 | $260.00 | $1,100.00 | $2,000.00 | $1,825.00 | $910.00 |
| 0209 | Pedestrian signal head (16", 1 section W/countdown) (7048500000-E) | EACH | 16 | $1,250.00 | $1,413.00 | $1,250.00 | $1,250.00 | $1,250.00 | $1,250.00 |
| 0210 | Signal cable (7060000000-E) | LF | 6,925 | $4.00 | $4.50 | $4.00 | $4.00 | $4.00 | $4.00 |
| 0211 | Vehicle signal head (12", 3 section) (7120000000-E) | EACH | 22 | $1,000.00 | $1,131.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 0212 | Vehicle signal head (12", 4 section) (7132000000-E) | EACH | 4 | $1,475.00 | $1,668.00 | $1,475.00 | $1,475.00 | $1,475.00 | $1,475.00 |
| 0213 | Vehicle signal head (12", 5 section) (7144000000-E) | EACH | 2 | $1,800.00 | $2,035.00 | $1,800.00 | $1,800.00 | $1,800.00 | $1,800.00 |
| 0214 | Paved trench (***********) - (2, 2") (7288000000-E) | LF | 295 | $25.00 | $28.25 | $25.00 | $25.00 | $25.00 | $25.00 |
| 0215 | Unpaved trench (***********) - (2, 2") (7300000000-E) | LF | 990 | $18.00 | $20.25 | $18.00 | $18.00 | $18.00 | $18.00 |
| 0216 | Direct drill (***********) - (2, 2") (7301000000-E) | LF | 925 | $28.00 | $31.75 | $28.00 | $28.00 | $28.00 | $28.00 |
| 0217 | Junction box (standard size) (7324000000-N) | EACH | 15 | $800.00 | $904.50 | $800.00 | $800.00 | $800.00 | $800.00 |
| 0218 | Junction box (over-sized, heavy duty) (7348000000-N) | EACH | 8 | $1,250.00 | $1,413.00 | $1,250.00 | $1,250.00 | $1,250.00 | $1,250.00 |
| 0219 | Inductive loop sawcut (7444000000-E) | LF | 2,810 | $12.00 | $13.50 | $12.00 | $12.00 | $12.00 | $12.00 |
| 0220 | Lead-in cable (14-2) (7456100000-E) | LF | 7,370 | $2.25 | $2.55 | $2.25 | $2.25 | $2.25 | $2.25 |
| 0221 | Metal pole with single mast arm (7588000000-N) | EACH | 8 | $31,942 | $36,116 | $31,942 | $31,942 | $31,942 | $31,942 |
| 0222 | Soil test (7613000000-N) | EACH | 8 | $1,500.00 | $1,696.00 | $1,500.00 | $1,500.00 | $1,500.00 | $1,500.00 |
| 0223 | Drilled pier foundation (7614100000-E) | CY | 44 | $1,400.00 | $1,583.00 | $1,400.00 | $1,400.00 | $1,400.00 | $1,400.00 |
| 0224 | Mast arm with metal pole design (7631000000-N) | EACH | 8 | $100.00 | $113.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| 0225 | Sign for signals (7636000000-N) | EACH | 21 | $675.00 | $763.00 | $675.00 | $675.00 | $675.00 | $675.00 |
| 0226 | Type II pedestal with foundation (7642200000-N) | EACH | 11 | $3,500.00 | $3,957.00 | $3,500.00 | $3,500.00 | $3,500.00 | $3,500.00 |
| 0227 | Signal cabinet foundation (7684000000-N) | EACH | 2 | $2,500.00 | $2,827.00 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 |
| 0228 | Contlrs with CBNT (**************) - (2070LX, base MTD) (7696000000-N) | EACH | 2 | $22,000 | $24,875 | $22,000 | $22,000 | $22,000 | $22,000 |
| 0229 | Detector card (type 170) (7744000000-N) | EACH | 21 | $300.00 | $339.00 | $300.00 | $300.00 | $300.00 | $300.00 |
| 0230 | Cabinet base extender (7901000000-N) | EACH | 2 | $550.00 | $622.00 | $550.00 | $550.00 | $550.00 | $550.00 |
| 0231 | Generic signal item (EA) - protective coating for single mast arm pole (agate gray, ral 7038) (7980000000-N) | EACH | 8 | $2,000.00 | $2,261.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 |
| 0232 | Generic signal item (EA) - protective coating for type II signal pedestal (agate gray, ral 7038) (7980000000-N) | EACH | 12 | $200.00 | $226.00 | $200.00 | $200.00 | $200.00 | $200.00 |
| 0233 | Soil nail retaining walls (8802010000-E) | SF | 3,440 | $205.00 | $107.50 | $177.25 | $70.00 | $62.00 | $97.00 |
| 0234 | Soil nail verification tests (8802015100-N) | EACH | 4 | $1,000.00 | $776.00 | $1,125.00 | $1,975.00 | $5,000.00 | $700.00 |
| 0235 | Soil nail proof tests (8802015110-N) | EACH | 8 | $500.00 | $277.00 | $565.00 | $975.00 | $1,200.00 | $250.00 |
| 0236 | Generic ret wall item (SF) - non-standard cip gravity retaining walls (8847000000-E) | SF | 770 | $135.00 | $170.00 | $198.30 | $125.00 | $250.00 | $140.00 |
| 0237 | Pile excavation in soil (8096000000-E) | LF | 291.20 | $820.00 | $395.00 | $346.74 | $300.00 | $350.00 | $1,000.00 |
| 0238 | Pile excavation not in soil (8097000000-E) | LF | 146 | $820.00 | $480.00 | $423.18 | $500.00 | $426.00 | $1,000.00 |
| 0239 | 3'-6" dia drilled piers in soil (8105540000-E) | LF | 26.40 | $800.00 | $2,083.00 | $1,873.97 | $1,400.00 | $1,650.00 | $2,800.00 |
| 0240 | 3'-6" dia drilled piers not in soil (8105640000-E) | LF | 140.80 | $800.00 | $2,083.00 | $1,873.97 | $1,800.00 | $1,650.00 | $2,800.00 |
| 0241 | Permanent steel casing for 3'-6" dia drilled pier (8111400000-E) | LF | 34 | $300.00 | $670.00 | $604.25 | $405.00 | $405.00 | $1,000.00 |
| 0242 | CSL testing (8115000000-N) | EACH | 2 | $2,500.00 | $637.50 | $575.00 | $6,500.00 | $500.00 | $3,000.00 |
| 0243 | Uncl STR excav sta ***** - (134+65.00 -L- LT) (8121000000-N) | LS | 1 | $6,000.00 | $2,577.00 | $101,000 | $10,000 | $6,500.00 | $33,750 |
| 0244 | Uncl STR excav sta ***** - (134+65.00 -L- RT) (8121000000-N) | LS | 1 | $6,000.00 | $2,189.00 | $101,000 | $10,000 | $6,500.00 | $33,750 |
| 0245 | Reinforced concrete deck slab (8147000000-E) | SF | 20,484 | $55.00 | $65.75 | $59.36 | $55.00 | $62.50 | $48.00 |
| 0246 | Grooving bridge floors (8161000000-E) | SF | 22,495 | $0.50 | $1.15 | $1.06 | $1.00 | $0.82 | $1.10 |
| 0247 | Class A concrete (bridge) (8182000000-E) | CY | 327.50 | $875.00 | $1,460.00 | $1,317.02 | $1,200.00 | $1,250.00 | $900.00 |
| 0248 | BRG appr slab *********** - (134+65.00 -L- LT) (8210000000-N) | LS | 1 | $70,000 | $82,887 | $74,775 | $100,000 | $75,000 | $29,000 |
| 0249 | BRG appr slab *********** - (134+65.00 -L- RT) (8210000000-N) | LS | 1 | $70,000 | $82,887 | $74,775 | $80,000 | $75,000 | $29,000 |
| 0250 | BRG appr slab *********** - (76+49.00 -L-) (8210000000-N) | LS | 1 | $95,000 | $122,400 | $110,425 | $80,000 | $110,000 | $36,000 |
| 0251 | Reinforcing steel (bridge) (8217000000-E) | LB | 54,732 | $2.00 | $1.75 | $1.59 | $1.50 | $1.75 | $1.75 |
| 0252 | Spiral column reinforcing steel (bridge) (8238000000-E) | LB | 4,895 | $3.50 | $3.95 | $3.56 | $3.00 | $3.00 | $3.00 |
| 0253 | 45" prestressed concrete girders (8262000000-E) | LF | 1,111 | $310.00 | $352.00 | $317.41 | $275.00 | $300.00 | $310.00 |
| 0254 | Fib **" prestr conc girdr - (54") (8278000000-E) | LF | 1,179.58 | $445.00 | $512.00 | $462.10 | $425.00 | $460.00 | $357.00 |
| 0255 | Pile DRV equip setup ** steel piles - (HP 14 X 73) (8328200000-E) | EACH | 70 | $615.00 | $1.10 | $1.00 | $380.00 | $1,000.00 | $750.00 |
| 0256 | HP 14 X 73 steel piles (8384000000-E) | LF | 1,385 | $58.00 | $77.00 | $65.56 | $70.00 | $70.00 | $78.00 |
| 0257 | Steel pile points (8391000000-N) | EACH | 70 | $210.00 | $211.00 | $190.25 | $180.00 | $200.00 | $180.00 |
| 0258 | Dynamic pile testing (8394000000-N) | EACH | 1 | $2,100.00 | $1.10 | $1.00 | $3,000.00 | $7,500.00 | $5,000.00 |
| 0259 | Two bar metal rail (8475000000-E) | LF | 488.70 | $200.00 | $261.50 | $199.00 | $200.00 | $240.00 | $170.00 |
| 0260 | Concrete barrier rail (8503000000-E) | LF | 959.06 | $145.00 | $170.50 | $153.86 | $110.00 | $162.00 | $150.00 |
| 0261 | 1'-**"X*****"conc parapet - (1'-2" X 2'-6") (8517000000-E) | LF | 519.66 | $190.00 | $357.50 | $322.68 | $160.00 | $210.00 | $120.00 |
| 0262 | Rip rap class II (2'-0" thick) (8608000000-E) | TON | 1,480 | $73.00 | $80.25 | $77.00 | $50.00 | $80.00 | $55.00 |
| 0263 | Geotextile for drainage (8622000000-E) | SY | 1,647 | $4.50 | $5.75 | $4.50 | $5.00 | $4.00 | $5.00 |
| 0264 | Elastomeric bearings (8657000000-N) | LS | 1 | $16,000 | $17,874 | $16,125 | $14,000 | $16,000 | $52,000 |
| 0265 | Concrete barrier rail with moment slab (8504000000-E) | LF | 298 | $680.00 | $277.00 | $571.48 | $350.00 | $520.00 | $250.00 |
| 0266 | Generic ret wall item (SF) - simulated stone form liner finish (8847000000-E) | SF | 5,850 | $33.00 | $59.75 | $28.98 | $35.00 | $50.00 | $54.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NCDOT's tabulation for this contract. NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
Every contract let that day: NCDOT letting of May 20, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.