Portland cement for soil cement base, NCDOT 1187000000-E
Low bidders on NCDOT contracts carried a median of $268.95 per TON for this item, over the 24 months to 20 OCT 2026, across 5 low bids. Half of all 42 bids fell between $253.00 and $285.00.
- Owner
- North Carolina DOT
- Item
- 1187000000-E
- Unit
- TON
- Data through
- 20 OCT 2026
NCDOT prints this item as “PC FOR SOIL CEMENT BASE”.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2013 | 7 | 7 | $145.00 | 41 | $145.00 |
| 2014 | 5 | 5 | $136.50 | 45 | $136.50 |
| 2015 | 10 | 10 | $148.00 | 60 | $152.50 |
| 2016 | 11 | 11 | $169.00 | 52 | $170.97 |
| 2017 | 7 | 7 | $170.56 | 42 | $176.41 |
| 2018 | 9 | 9 | $190.00 | 46 | $183.32 |
| 2019 | 6 | 6 | $189.00 | 22 | $193.00 |
| 2020 | 2 | 2 | $195.25 | 9 | $198.00 |
| 2021 | 6 | 6 | $194.91 | 27 | $191.75 |
| 2022 | 1 | 1 | $214.00 | 3 | $214.00 |
| 2023 | 2 | 2 | $276.50 | 12 | $280.12 |
| 2024 | 4 | 4 | $273.00 | 21 | $287.25 |
| 2025 | 4 | 4 | $260.98 | 37 | $263.00 |
| 2026 | 1 | 1 | $309.41 | 5 | $269.05 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Guilford | 6 | $181.88 | 42 | $175.00 |
| Cabarrus | 7 | $190.00 | 39 | $190.00 |
| Mecklenburg | 9 | $190.50 | 37 | $190.50 |
| Forsyth | 4 | $169.78 | 36 | $172.78 |
| Chatham | 3 | $253.00 | 32 | $264.49 |
| Alamance | 3 | $175.00 | 24 | $181.98 |
| Union | 7 | $155.00 | 21 | $156.50 |
| Ashe | 3 | $185.00 | 19 | $180.00 |
| Cleveland | 3 | $170.14 | 18 | $151.00 |
| Anson | 4 | $151.51 | 14 | $151.51 |
Countys with at least three low bids, over all lettings.
By quantity
| Quantity (TON) | Low bids | Low-bid median |
|---|---|---|
| 78 to 617 | 18 | $190.00 |
| 621 to 1,480 | 19 | $180.00 |
| 1,493 to 2,810 | 19 | $170.56 |
| 2,875 to 9,358 | 19 | $152.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Blythe Construction Inc | 46 | 21 (46%) |
| Lynches River Contracting Inc | 12 | 10 (83%) |
| Branch Highways, Inc. | 12 | 6 (50%) |
| The Lane Construction Corp | 16 | 5 (31%) |
| Triangle Grading & Paving Inc | 11 | 5 (45%) |
| Zachry Construction Corporation | 12 | 4 (33%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 20 JAN 2026 | C205117 | Cabarrus | 219 | $309.41 | $269.05 | 5 | NJR Group Inc | NCDOT |
| 21 OCT 2025 | C205093 | Davie | 671 | $308.00 | $267.00 | 10 | Branch Civil Inc | NCDOT |
| 16 SEP 2025 | C204971 | Guilford | 2,180 | $268.95 | $304.65 | 3 | Blythe Construction Inc | NCDOT |
| 20 MAY 2025 | C205032 | Chatham | 1,600 | $253.00 | $253.00 | 12 | FSC II LLC DBA Fred Smith Company | NCDOT |
| 18 MAR 2025 | C204933 | Chatham | 590 | $232.00 | $251.90 | 12 | Barnhill Contracting Company | NCDOT |
| 15 OCT 2024 | C204348 | Iredell, Catawba | 1,865 | $295.00 | $271.00 | 5 | Blythe Development Co. | NCDOT |
| 16 JUL 2024 | C204843 | Randolph | 1,522 | $251.00 | $291.01 | 4 | Conti Civil LLC | NCDOT |
| 18 JUN 2024 | C204951 | Hoke, Cumberland | 9,358 | $208.00 | $211.00 | 3 | FSC II LLC DBA Fred Smith Company | NCDOT |
| 18 JUN 2024 | C204501 | Mecklenburg | 241 | $300.00 | $300.00 | 9 | Sealand Contractors Corp | NCDOT |
| 15 AUG 2023 | C204872 | Chatham | 900 | $278.00 | $280.12 | 8 | FSC II LLC DBA Fred Smith Company | NCDOT |
| 18 JUL 2023 | C204851 | Cleveland | 4,320 | $275.00 | $284.06 | 4 | Ames Construction Inc | NCDOT |
| 15 MAR 2022 | C204704 | Mecklenburg | 1,411 | $214.00 | $214.00 | 3 | Blythe Brothers Asphalt Co LLC | NCDOT |
| 21 DEC 2021 | C204397 | Rutherford | 5,179 | $240.00 | $240.00 | 2 | Wright Brothers Construction Company Inc | NCDOT |
| 21 DEC 2021 | C204686 | Cabarrus | 1,597 | $210.00 | $191.03 | 6 | NJR Group Inc | NCDOT |
| 15 JUN 2021 | C204646 | Mecklenburg | 283 | $198.06 | $186.88 | 4 | Boggs Contracting Inc | NCDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.
How these prices were read
NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the NCDOT letting of 20 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.