NCDOT contract C204971 bid tabulation
GRADING, DRAINAGE, PAVING, SIGNALS, AND STRUCTURE. SR-1818 (JOHNSON ST)/SR-1850 (SANDY RIDGE RD) FROM SR-1820 (SKEET CLUB RD) TO SOUTH OF I-40. Let by North Carolina DOT on September 16, 2025, Guilford. 3 bids received; low bid $68,053,985 by Blythe Construction Inc.
- Owner
- North Carolina DOT
- Letting
- 16 SEP 2025
- Pay items
- 330
- Data through
- 20 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Blythe Construction Inc | $68,053,985 | Low |
| 2 | Branch Civil Inc | $69,485,000 | +2.0% |
| 3 | Flatiron Dragados Constructors Inc | $71,710,338 | +5.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Blythe Construction Inc | 2. Branch Civil Inc | 3. Flatiron Dragados Constructors Inc |
|---|---|---|---|---|---|---|
| 0001 | Mobilization (0000100000-N) | LS | 1 | $3,406,000 | $3,200,000 | $3,585,000 |
| 0002 | Construction surveying (0000400000-N) | LS | 1 | $1,330,000 | $461,600 | $600,000 |
| 0003 | Clearing & grubbing (0001000000-E) | LS | 1 | $3,500,000 | $5,750,000 | $7,849,000 |
| 0004 | Supplementary clearing & grubbing (0008000000-E) | ACRE | 2 | $5,000.00 | $15,500 | $15,000 |
| 0005 | Sealing abandoned wells (0015000000-N) | EACH | 2 | $3,500.00 | $5,090.00 | $4,600.00 |
| 0006 | Unclassified excavation (0022000000-E) | CY | 83,700 | $12.00 | $25.25 | $20.00 |
| 0007 | Undercut excavation (0036000000-E) | CY | 16,600 | $20.00 | $25.25 | $35.00 |
| 0008 | Borrow excavation (0106000000-E) | CY | 146,900 | $18.00 | $0.01 | $0.01 |
| 0009 | Embankment settlement gauges (0127000000-N) | EACH | 3 | $3,000.00 | $3,030.00 | $1,200.00 |
| 0010 | Drainage ditch excavation (0134000000-E) | CY | 2,570 | $15.00 | $5.65 | $15.00 |
| 0011 | Removal of existing asphalt pavement (0156000000-E) | SY | 9,100 | $11.00 | $9.90 | $13.00 |
| 0012 | Proof rolling (0192000000-N) | HR | 40 | $270.00 | $415.00 | $225.00 |
| 0013 | Select granular material (0195000000-E) | CY | 6,400 | $16.00 | $66.75 | $0.01 |
| 0014 | Geotextile for soil stabilization (0196000000-E) | SY | 11,250 | $5.00 | $2.65 | $5.00 |
| 0015 | Temporary shoring (0199000000-E) | SF | 800 | $40.00 | $167.00 | $52.00 |
| 0016 | Generic grading item (SY) - geotextile for embankment stabilization (0241000000-E) | SY | 1,050 | $5.00 | $4.40 | $7.00 |
| 0017 | Generic grading item (LS) - type 1 bridge approach fill, station 55+24 -L- (0248000000-N) | LS | 1 | $65,000 | $81,310 | $80,000 |
| 0018 | Foundation conditioning material, minor structures (0318000000-E) | TON | 5,148 | $80.00 | $81.00 | $48.50 |
| 0019 | FND condit geotextile (4A) (0321000000-E) | SY | 18,168 | $5.00 | $4.40 | $2.50 |
| 0020 | 15" drainage pipe (0335200000-E) | LF | 3,340 | $80.00 | $86.25 | $105.00 |
| 0021 | 18" drainage pipe (0335300000-E) | LF | 912 | $90.00 | $108.00 | $118.00 |
| 0022 | 24" drainage pipe (0335400000-E) | LF | 588 | $110.00 | $129.00 | $140.00 |
| 0023 | 30" drainage pipe (0335500000-E) | LF | 1,034 | $260.00 | $158.00 | $150.00 |
| 0024 | 36" drainage pipe (0335600000-E) | LF | 372 | $170.00 | $205.00 | $165.00 |
| 0025 | 42" drainage pipe (0335700000-E) | LF | 32 | $220.00 | $327.00 | $250.00 |
| 0026 | **" drainage pipe elbow - (30") (0335850000-E) | EACH | 2 | $1,100.00 | $2,620.00 | $650.00 |
| 0027 | **" drainage pipe elbow - (36") (0335850000-E) | EACH | 2 | $1,200.00 | $3,280.00 | $750.00 |
| 0028 | ***" RCP culv class IV - (12") (0448000000-E) | LF | 60 | $100.00 | $99.75 | $125.00 |
| 0029 | 15" RC pipe culverts, class IV (0448200000-E) | LF | 15,020 | $90.00 | $116.00 | $120.00 |
| 0030 | 18" RC pipe culverts, class IV (0448300000-E) | LF | 13,876 | $110.00 | $159.00 | $142.00 |
| 0031 | 24" RC pipe culverts, class IV (0448400000-E) | LF | 4,752 | $130.00 | $196.00 | $185.00 |
| 0032 | 30" RC pipe culverts, class IV (0448500000-E) | LF | 1,732 | $170.00 | $279.00 | $265.00 |
| 0033 | 36" RC pipe culverts, class IV (0448600000-E) | LF | 304 | $230.00 | $395.00 | $280.00 |
| 0034 | 42" RC pipe culverts, class IV (0448700000-E) | LF | 160 | $260.00 | $488.00 | $325.00 |
| 0035 | **" RC pipe culv class V - (18") (0449000000-E) | LF | 204 | $130.00 | $169.00 | $165.00 |
| 0036 | **" caa pipe CLVT *****" - (24", 0.064") (0546000000-E) | LF | 178 | $150.00 | $216.00 | $175.00 |
| 0037 | Generic pipe item (LF) - 18" ductile iron pipe, class 150, (sealed) (0986000000-E) | LF | 68 | $110.00 | $248.00 | $150.00 |
| 0038 | Pipe removal (0995000000-E) | LF | 7,963 | $30.00 | $49.00 | $35.00 |
| 0039 | Fine grading (1011000000-N) | LS | 1 | $3,000,000 | $2,569,100 | $2,878,000 |
| 0040 | Lime treated soil (slurry method) (1044000000-E) | SY | 77,620 | $6.15 | $4.20 | $3.52 |
| 0041 | Lime for lime treated soil used based on county (1066000000-E) | TON | 940 | $379.50 | $447.00 | $374.00 |
| 0042 | Shallow undercut (1099500000-E) | CY | 1,100 | $28.68 | $15.75 | $40.00 |
| 0043 | Class IV subgrade stabilization (1099700000-E) | TON | 27,727 | $44.26 | $50.00 | $40.00 |
| 0044 | Stabilizer aggregate (1110000000-E) | TON | 500 | $60.00 | $73.50 | $40.00 |
| 0045 | Geotextile for subgrade stabilization (1112000000-E) | SY | 62,114 | $4.00 | $4.20 | $5.00 |
| 0046 | Aggregate base course (1121000000-E) | TON | 6,140 | $65.00 | $76.00 | $43.00 |
| 0047 | Soil cement base (1176000000-E) | SY | 77,620 | $6.73 | $4.10 | $3.41 |
| 0048 | Incidental stone base (1220000000-E) | TON | 100 | $60.00 | $100.00 | $250.00 |
| 0049 | Mill asp PVMT *****" DTH - (1-1/2") (1297000000-E) | SY | 2,790 | $6.00 | $5.85 | $6.65 |
| 0050 | Mill asp PVMT *****" DTH - (2-1/2") (1297000000-E) | SY | 6,130 | $6.00 | $5.40 | $7.00 |
| 0051 | Mill asp PVMT *****" DTH - (4") (1297000000-E) | SY | 280 | $22.00 | $19.25 | $18.50 |
| 0052 | Incidental milling (1330000000-E) | SY | 6,500 | $15.00 | $7.15 | $12.00 |
| 0053 | Asphalt conc base course, type B25.0C (1491000000-E) | TON | 45,520 | $100.00 | $97.00 | $88.71 |
| 0054 | Asphalt conc intermediate course, type I19.0C (1503000000-E) | TON | 43,820 | $100.00 | $90.00 | $83.20 |
| 0055 | Asphalt conc surface course, type S9.5B (1519000000-E) | TON | 8,490 | $110.00 | $107.00 | $100.17 |
| 0056 | Asphalt conc surface course, type S9.5C (1523000000-E) | TON | 35,530 | $100.00 | $91.00 | $84.73 |
| 0057 | Asphalt binder for plant mix (1575000000-E) | TON | 6,825 | $600.00 | $675.00 | $619.79 |
| 0058 | Asphalt plant mix, pavement repair (1693000000-E) | TON | 896 | $250.00 | $315.00 | $250.00 |
| 0059 | Subdrain excavation (2022000000-E) | CY | 157 | $44.05 | $43.50 | $35.53 |
| 0060 | Geotextile for subsurface drains (2026000000-E) | SY | 700 | $15.10 | $15.00 | $12.18 |
| 0061 | Subdrain coarse aggregate (2036000000-E) | CY | 118 | $106.98 | $106.00 | $86.29 |
| 0062 | 6" perforated subdrain pipe (2044000000-E) | LF | 700 | $21.40 | $21.00 | $17.26 |
| 0063 | Subdrain pipe outlet (2070000000-N) | EACH | 2 | $503.44 | $497.00 | $406.09 |
| 0064 | 6" outlet pipe (2077000000-E) | LF | 12 | $50.34 | $49.75 | $40.61 |
| 0065 | Blotting sand (2143000000-E) | TON | 20 | $35.00 | $278.00 | $119.57 |
| 0066 | Temporary steel plate covers for masonry drainage structure (2190000000-N) | EACH | 1 | $3,500.00 | $4,570.00 | $2,500.00 |
| 0067 | Endwalls (2209000000-E) | CY | 6.80 | $1,600.00 | $1,520.00 | $1,850.00 |
| 0068 | Pipe collars (2253000000-E) | CY | 3.35 | $2,600.00 | $4,520.00 | $1,500.00 |
| 0069 | Pipe plugs (2264000000-E) | CY | 0.18 | $10,000 | $16,215 | $5,500.00 |
| 0070 | Flowable fill (2275000000-E) | CY | 3 | $1,000.00 | $837.00 | $650.00 |
| 0071 | Masonry drainage structures (2286000000-N) | EACH | 414 | $3,000.00 | $4,240.00 | $4,200.00 |
| 0072 | Masonry drainage structures (2308000000-E) | LF | 117.70 | $600.00 | $511.00 | $1,000.00 |
| 0073 | Frame with grate, STD 840.22 (2354000000-N) | EACH | 3 | $1,282.65 | $1,250.00 | $1,300.00 |
| 0074 | Frame with grate, STD 840.24 (2354200000-N) | EACH | 2 | $1,500.00 | $1,250.00 | $1,600.00 |
| 0075 | Frame with two grates, STD 840.16 (2364000000-N) | EACH | 67 | $1,500.00 | $1,670.00 | $1,700.00 |
| 0076 | Frame with two grates, STD 840.22 (2365000000-N) | EACH | 1 | $1,500.00 | $1,600.00 | $1,600.00 |
| 0077 | Frame with two grates, STD 840.24 (2366000000-N) | EACH | 20 | $1,500.00 | $1,590.00 | $1,600.00 |
| 0078 | Frame with two grates, STD 840.29 (2367000000-N) | EACH | 73 | $1,500.00 | $1,570.00 | $1,600.00 |
| 0079 | Frame-GRT-HD 840.03 ** - (E) (2374000000-N) | EACH | 25 | $1,500.00 | $1,800.00 | $1,850.00 |
| 0080 | Frame-GRT-HD 840.03 ** - (F) (2374000000-N) | EACH | 97 | $1,500.00 | $1,800.00 | $1,900.00 |
| 0081 | Frame-GRT-HD 840.03 ** - (G) (2374000000-N) | EACH | 121 | $1,500.00 | $1,800.00 | $1,900.00 |
| 0082 | Frame with cover, STD 840.54 (2396000000-N) | EACH | 5 | $1,500.00 | $1,380.00 | $1,300.00 |
| 0083 | Concrete transitional section for drop inlet (2451000000-N) | EACH | 121 | $960.00 | $1,420.00 | $1,523.00 |
| 0084 | Generic drainage item (EA) - structure sealed with boots (2473000000-N) | EACH | 1 | $7,088.07 | $4,170.00 | $5,000.00 |
| 0085 | **'-**" concrete curb & gutter - (2'-9") (2538000000-E) | LF | 8,700 | $34.00 | $44.00 | $42.00 |
| 0086 | 1'-6" concrete curb & gutter (2542000000-E) | LF | 16,800 | $28.00 | $25.25 | $29.00 |
| 0087 | 2'-6" concrete curb & gutter (2549000000-E) | LF | 55,000 | $30.00 | $29.75 | $39.00 |
| 0088 | 4" concrete sidewalk (2591000000-E) | SY | 14,100 | $49.00 | $66.25 | $85.00 |
| 0089 | Concrete curb ramps (2605000000-N) | EACH | 79 | $2,950.00 | $1,970.00 | $2,976.00 |
| 0090 | 6" concrete driveway (2612000000-E) | SY | 200 | $97.00 | $150.00 | $112.00 |
| 0091 | 5" monolithic concrete islands (keyed in) (2655000000-E) | SY | 10,650 | $109.00 | $87.00 | $93.00 |
| 0092 | Precast reinforced concrete barrier, single faced (2724000000-E) | LF | 800 | $133.48 | $119.00 | $120.00 |
| 0093 | Adjustment of catch basins (2800000000-N) | EACH | 1 | $1,800.00 | $407.00 | $6,000.00 |
| 0094 | Adjustment of manholes (2830000000-N) | EACH | 3 | $3,500.00 | $1,130.00 | $7,500.00 |
| 0095 | Reconstruct manhole structures (2847000000-N) | EACH | 3 | $5,200.00 | $5,300.00 | $7,500.00 |
| 0096 | Impact attenuator units, type TL-3 (3001000000-N) | EACH | 1 | $34,000 | $40,250 | $34,518 |
| 0097 | Steel beam guardrail (3030000000-E) | LF | 1,400 | $23.50 | $27.75 | $23.86 |
| 0098 | Additional guardrail posts (3150000000-N) | EACH | 5 | $1.00 | $1.20 | $1.02 |
| 0099 | Guardrail end units, type cat-1 (3210000000-N) | EACH | 4 | $950.00 | $1,120.00 | $964.47 |
| 0100 | Guardrail anchor units, type III (3215000000-N) | EACH | 4 | $2,350.00 | $2,780.00 | $2,385.79 |
| 0101 | Guardrail end units, type TL-3 (3287000000-N) | EACH | 5 | $3,200.00 | $3,790.00 | $3,248.73 |
| 0102 | Guardrail end units, type TL-2 (3288000000-N) | EACH | 1 | $3,100.00 | $3,670.00 | $3,147.21 |
| 0103 | Guardrail anchor units, type B-77 (3317000000-N) | EACH | 4 | $2,600.00 | $3,080.00 | $2,639.60 |
| 0104 | Remove existing guardrail (3360000000-E) | LF | 1,850 | $0.90 | $1.05 | $0.91 |
| 0105 | CHN LK fence **" fabric - (72") (3533000000-E) | LF | 1,716 | $22.00 | $15.50 | $14.21 |
| 0106 | Chain link fence, 48" fabric (3536000000-E) | LF | 860 | $16.00 | $14.50 | $13.20 |
| 0107 | Met line PST **" CL fen - (72") (3539000000-E) | EACH | 148 | $125.00 | $66.75 | $60.91 |
| 0108 | Metal line posts for 48" chain link fence (3542000000-E) | EACH | 73 | $100.00 | $55.50 | $50.76 |
| 0109 | Met term PST **" CL fen - (72") (3545000000-E) | EACH | 41 | $150.00 | $111.00 | $101.52 |
| 0110 | Metal terminal posts for 48" chain link fence (3548000000-E) | EACH | 7 | $150.00 | $89.00 | $81.22 |
| 0111 | Generic fencing item 866 (EA) - black vinyl coated metal line posts for 48" chain link fence (3579000000-N) | EACH | 175 | $125.00 | $55.50 | $50.76 |
| 0112 | Generic fencing item 866 (EA) - black vinyl coated metal terminal posts for 48" chain link fence (3579000000-N) | EACH | 34 | $175.00 | $111.00 | $101.52 |
| 0113 | Generic fencing item 866 (EA) - black vinyl coated single gates, 48" high, 10' wide, 10' opening (3579000000-N) | EACH | 3 | $2,500.00 | $667.00 | $609.14 |
| 0114 | Generic fencing item 866 (LF) - black vinyl coated chain link fence, 48" fabric (3580000000-E) | LF | 2,052 | $20.00 | $13.25 | $12.18 |
| 0115 | Rip rap, class I (3628000000-E) | TON | 1,200 | $80.00 | $114.00 | $85.00 |
| 0116 | Rip rap, class II (3635000000-E) | TON | 710 | $80.00 | $175.00 | $84.00 |
| 0117 | Rip rap, class A (3642000000-E) | TON | 600 | $80.00 | $65.00 | $81.00 |
| 0118 | Rip rap, class B (3649000000-E) | TON | 4,700 | $80.00 | $108.00 | $92.00 |
| 0119 | Geotextile for drainage (3656000000-E) | SY | 16,230 | $4.00 | $3.60 | $4.50 |
| 0120 | Reinforced concrete sign foundations (4048000000-E) | CY | 2 | $10.00 | $12.00 | $10.31 |
| 0121 | Plain concrete sign foundations (4054000000-E) | CY | 1 | $10.00 | $12.00 | $10.31 |
| 0122 | Supports, 3-LB steel U-channel (4072000000-E) | LF | 2,345 | $12.00 | $14.50 | $12.37 |
| 0123 | Sign erection, type D (4096000000-N) | EACH | 7 | $300.00 | $361.00 | $309.28 |
| 0124 | Sign erection, type E (4102000000-N) | EACH | 156 | $175.00 | $211.00 | $180.41 |
| 0125 | Sign erection, type F (4108000000-N) | EACH | 2 | $300.00 | $361.00 | $309.28 |
| 0126 | Sign erection, type *** (GRD MTD) - (A) (4110000000-N) | EACH | 4 | $2,000.00 | $2,410.00 | $2,061.86 |
| 0127 | Sign erection, type *** (GRD MTD) - (B) (4110000000-N) | EACH | 1 | $1,000.00 | $1,200.00 | $1,030.93 |
| 0128 | Sign erect, reloc ** GRD MTD - (A) (4116100000-N) | EACH | 2 | $2,000.00 | $2,410.00 | $2,061.86 |
| 0129 | Sign erect, reloc ** GRD MTD - (D) (4116100000-N) | EACH | 4 | $300.00 | $361.00 | $309.28 |
| 0130 | Sign erect, reloc ** GRD MTD - (E) (4116100000-N) | EACH | 10 | $300.00 | $361.00 | $309.28 |
| 0131 | Disposal of sign system, U-channel (4155000000-N) | EACH | 117 | $5.00 | $6.00 | $5.15 |
| 0132 | Work zone signs (stationary) (4400000000-E) | SF | 1,143 | $6.10 | $9.00 | $8.12 |
| 0133 | Work zone signs (portable) (4405000000-E) | SF | 592 | $8.65 | $9.25 | $14.21 |
| 0134 | Work zone signs (barricade mounted) (4410000000-E) | SF | 500 | $8.75 | $9.95 | $7.11 |
| 0135 | Flashing arrow board (4415000000-N) | EACH | 2 | $3,000.00 | $2,440.00 | $3,000.00 |
| 0136 | Portable changeable message sign (4420000000-N) | EACH | 2 | $9,500.00 | $9,340.00 | $20,000 |
| 0137 | Drums (4430000000-N) | EACH | 1,200 | $45.00 | $47.75 | $45.00 |
| 0138 | Cones (4435000000-N) | EACH | 300 | $25.00 | $22.00 | $30.00 |
| 0139 | Barricades (type III) (4445000000-E) | LF | 520 | $25.00 | $24.50 | $25.00 |
| 0140 | Pedestrian channelizing devices (4447000000-E) | LF | 132 | $45.00 | $20.50 | $26.00 |
| 0141 | Flagger (4455000000-N) | DAY | 350 | $360.00 | $725.00 | $1,500.00 |
| 0142 | Temporary crash cushions (4465000000-N) | EACH | 2 | $12,500 | $8,490.00 | $9,100.00 |
| 0143 | Remove & reset temporary crash cushion (4470000000-N) | EACH | 4 | $3,250.00 | $2,830.00 | $3,300.00 |
| 0144 | TMA (4480000000-N) | EACH | 2 | $140,000 | $47,270 | $45,000 |
| 0145 | Portable concrete barrier (4485000000-E) | LF | 474 | $74.10 | $88.00 | $76.00 |
| 0146 | Portable concrete barrier (anchored) (4490000000-E) | LF | 440 | $93.90 | $68.00 | $96.00 |
| 0147 | Remove and reset portable concrete barrier (4500000000-E) | LF | 474 | $24.20 | $28.75 | $25.00 |
| 0148 | Law enforcement (4510000000-N) | HR | 48 | $65.00 | $94.50 | $75.00 |
| 0149 | Temporary raised pavement markers (4650000000-N) | EACH | 1,825 | $12.25 | $15.00 | $12.20 |
| 0150 | Thermoplastic pavement marking lines (4", 90 mils) (4685000000-E) | LF | 128,192 | $0.60 | $0.75 | $0.60 |
| 0151 | Thermoplastic pavement marking lines (8", 90 mils) (4695000000-E) | LF | 9,965 | $3.60 | $4.50 | $3.65 |
| 0152 | Thermoplastic pavement marking lines (24", 90 mils) (4709000000-E) | LF | 2,256 | $13.25 | $16.25 | $13.40 |
| 0153 | Thermoplastic pavement marking character (90 mils) (4720000000-E) | EACH | 6 | $400.00 | $489.00 | $403.00 |
| 0154 | Thermoplastic pavement marking symbol (90 mils) (4725000000-E) | EACH | 407 | $200.00 | $245.00 | $202.00 |
| 0155 | Paint pavement marking lines (4") (4810000000-E) | LF | 248,291 | $0.20 | $0.25 | $0.20 |
| 0156 | Paint pavement marking lines (8") (4820000000-E) | LF | 130 | $0.60 | $0.75 | $0.60 |
| 0157 | Paint pavement marking lines (24") (4835000000-E) | LF | 3,032 | $1.25 | $1.50 | $1.26 |
| 0158 | Paint pavement marking symbol (4845000000-N) | EACH | 228 | $20.00 | $24.50 | $21.00 |
| 0159 | Polyurea lines (**", *** mils) - (4", 90 mils) (4846000000-E) | LF | 1,170 | $6.75 | $8.25 | $6.80 |
| 0160 | Removal of pavement marking lines (4") (4850000000-E) | LF | 11,375 | $2.50 | $3.05 | $2.55 |
| 0161 | Removal of pavement marking symbols & characters (4875000000-N) | EACH | 2 | $120.00 | $1,470.00 | $121.00 |
| 0162 | Permanent raised pavement markers (4900000000-N) | EACH | 1,250 | $13.50 | $16.50 | $13.60 |
| 0163 | STD foundat *********** - (type R1) (5070000000-N) | EACH | 2 | $1,806.00 | $2,270.00 | $1,824.24 |
| 0164 | STD foundat *********** - (type R2) (5070000000-N) | EACH | 1 | $1,894.00 | $2,380.00 | $1,913.13 |
| 0165 | Elect duct **, size ***** - (TL, 3") (5150000000-E) | LF | 150 | $23.00 | $29.00 | $23.23 |
| 0166 | **-#6 W/G feeder circuit - (2) (5175000000-E) | LF | 260 | $9.00 | $11.25 | $9.09 |
| 0167 | **-#4 W/G feeder circuit - (2) (5180000000-E) | LF | 430 | $10.00 | $12.50 | $10.10 |
| 0168 | **-#6 W/G feedr N *****" - (2, 1-1/2") (5210000000-E) | LF | 230 | $16.00 | $20.00 | $16.16 |
| 0169 | **-#4 W/G feeder N *****" - (2, 1-1/2") (5215000000-E) | LF | 350 | $18.00 | $22.50 | $18.18 |
| 0170 | Elec JB ************ - (IG18) (5240000000-N) | EACH | 3 | $1,393.00 | $1,750.00 | $1,407.07 |
| 0171 | Elec JB ************ - (LS18) (5240000000-N) | EACH | 3 | $1,393.00 | $1,750.00 | $1,407.07 |
| 0172 | Generic lighting item (LS) - luminaire storage (5260000000-N) | LS | 1 | $255.00 | $320.00 | $257.58 |
| 0173 | Generic lighting item (EA) - reinstall roadway luminaire (5270000000-N) | EACH | 3 | $330.00 | $415.00 | $333.33 |
| 0174 | Generic lighting item (EA) - relocate light standard (5270000000-N) | EACH | 3 | $2,508.00 | $3,150.00 | $2,533.33 |
| 0175 | Generic lighting item (EA) - remove light standard foundation (5270000000-N) | EACH | 3 | $1,810.00 | $2,270.00 | $1,828.28 |
| 0176 | 6" water line (5325600000-E) | LF | 56 | $180.00 | $433.00 | $178.89 |
| 0177 | 8" water line (5325800000-E) | LF | 643 | $145.00 | $169.00 | $164.03 |
| 0178 | 10" water line (5326000000-E) | LF | 50 | $215.00 | $500.00 | $273.45 |
| 0179 | 12" water line (5326200000-E) | LF | 594 | $185.00 | $218.00 | $263.93 |
| 0180 | 16" water line (5326600000-E) | LF | 5,070 | $205.00 | $239.00 | $295.00 |
| 0181 | DI H2O pipe fittings (5329000000-E) | LB | 54,675 | $15.00 | $17.75 | $14.21 |
| 0182 | 6" valve (5540000000-E) | EACH | 12 | $3,250.00 | $3,790.00 | $3,045.69 |
| 0183 | 8" valve (5546000000-E) | EACH | 1 | $4,950.00 | $5,770.00 | $4,263.96 |
| 0184 | 12" valve (5558000000-E) | EACH | 2 | $7,950.00 | $9,270.00 | $7,309.65 |
| 0185 | 16" valve (5558600000-E) | EACH | 16 | $16,250 | $18,950 | $18,274 |
| 0186 | 6" tapping sleeve & valve (5571600000-E) | EACH | 1 | $14,750 | $17,200 | $11,168 |
| 0187 | 16" tapping sleeve & valve (5572600000-E) | EACH | 3 | $33,750 | $39,370 | $25,381 |
| 0188 | 2" air release valve (5589200000-E) | EACH | 4 | $18,600 | $21,690 | $18,274 |
| 0189 | Relocate water meter (5648000000-N) | EACH | 3 | $3,450.00 | $4,020.00 | $4,060.91 |
| 0190 | Reconnect water meter (5649000000-N) | EACH | 2 | $2,890.00 | $3,370.00 | $2,842.64 |
| 0191 | 10" RPZ backflow prevention assembly (5656900000-E) | EACH | 1 | $47,250 | $55,110 | $60,914 |
| 0192 | 12" RPZ backflow prevention assembly (5657000000-E) | EACH | 1 | $61,875 | $72,170 | $91,371 |
| 0193 | Fire hydrant (5666000000-N) | EACH | 4 | $6,825.00 | $7,960.00 | $9,137.06 |
| 0194 | Relocate fire hydrant (5672000000-N) | EACH | 26 | $3,725.00 | $4,340.00 | $3,248.73 |
| 0195 | Fire hydrant leg (5673000000-E) | LF | 1,106 | $155.00 | $181.00 | $152.28 |
| 0196 | 16" line stop (5679200000-E) | EACH | 8 | $36,785 | $42,910 | $19,289 |
| 0197 | Water service line (<2") (5686500000-E) | LF | 176 | $85.00 | $102.00 | $118.38 |
| 0198 | 6" force main sewer (5709300000-E) | LF | 5,343 | $155.00 | $181.00 | $190.00 |
| 0199 | Sanitary sewer clean-out (5768000000-N) | EACH | 5 | $1,250.00 | $1,460.00 | $3,045.69 |
| 0200 | Sewer service line (5768500000-E) | LF | 25 | $220.00 | $257.00 | $512.63 |
| 0201 | Ductile iron sewer pipe fittings (5769000000-E) | LB | 2,585 | $16.00 | $18.75 | $19.29 |
| 0202 | 4' dia utility manhole (5775000000-E) | EACH | 1 | $9,250.00 | $10,790 | $11,168 |
| 0203 | Utility manhole wall 4' dia (5781000000-E) | LF | 2 | $850.00 | $991.00 | $1,218.28 |
| 0204 | Abandon 8" utility pipe (5801000000-E) | LF | 8 | $250.00 | $292.00 | $25.38 |
| 0205 | Abandon 12" utility pipe (5804000000-E) | LF | 319 | $55.00 | $64.25 | $25.38 |
| 0206 | Abandon 16" utility pipe (5810000000-E) | LF | 3,635 | $30.00 | $35.00 | $25.38 |
| 0207 | Remove water meter (5815000000-N) | EACH | 1 | $1,950.00 | $2,270.00 | $2,233.50 |
| 0208 | Abandon utility manhole (5816000000-N) | EACH | 2 | $2,195.00 | $2,560.00 | $2,538.07 |
| 0209 | 16" encasement pipe (5835700000-E) | LF | 315 | $190.00 | $222.00 | $182.74 |
| 0210 | 18" encasement pipe (5835800000-E) | LF | 108 | $220.00 | $257.00 | $243.65 |
| 0211 | Bore & jack **" - (16") (5872500000-E) | LF | 315 | $446.00 | $490.00 | $1,218.27 |
| 0212 | Generic utility item (EA) - remove existing vault (5882000000-N) | EACH | 2 | $3,975.00 | $4,640.00 | $8,121.83 |
| 0213 | Generic utility item (LS) - remove existing blow off, valve, and flap valve (5912000000-N) | LS | 1 | $3,975.00 | $4,640.00 | $15,228 |
| 0214 | Temporary silt fence (6000000000-E) | LF | 83,835 | $1.81 | $2.30 | $1.90 |
| 0215 | Stone for erosion control, class A (6006000000-E) | TON | 2,020 | $80.00 | $110.00 | $75.00 |
| 0216 | Stone for erosion control, class B (6009000000-E) | TON | 11,695 | $80.00 | $0.01 | $90.00 |
| 0217 | Sediment control stone (6012000000-E) | TON | 8,440 | $65.00 | $0.01 | $95.00 |
| 0218 | Temporary mulching (6015000000-E) | ACRE | 126 | $897.25 | $925.00 | $855.00 |
| 0219 | Seed for temporary seeding (6018000000-E) | LB | 7,300 | $2.04 | $2.25 | $1.95 |
| 0220 | Fertilizer for temporary seeding (6021000000-E) | TON | 38 | $791.54 | $885.00 | $755.00 |
| 0221 | Temporary slope drains (6024000000-E) | LF | 2,505 | $30.00 | $0.01 | $55.00 |
| 0222 | Safety fence (6029000000-E) | LF | 1,280 | $0.95 | $1.20 | $1.00 |
| 0223 | Silt excavation (6030000000-E) | CY | 39,350 | $25.00 | $0.01 | $0.01 |
| 0224 | Matting for erosion control (6036000000-E) | SY | 125,000 | $1.69 | $1.75 | $1.60 |
| 0225 | Coir fiber mat (6037000000-E) | SY | 2,421 | $5.03 | $5.50 | $4.80 |
| 0226 | 1/4" hardware cloth (6042000000-E) | LF | 22,115 | $2.61 | $3.35 | $2.70 |
| 0227 | Low permeability geotextile (6043000000-E) | SY | 800 | $6.45 | $6.20 | $3.00 |
| 0228 | Special stilling basins (6070000000-N) | EACH | 2 | $350.00 | $1,110.00 | $1,000.00 |
| 0229 | Flocculant (6071002000-E) | LB | 5,800 | $9.14 | $10.75 | $8.70 |
| 0230 | Coir fiber wattle (6071012000-E) | LF | 5,800 | $8.12 | $10.25 | $8.30 |
| 0231 | Coir fiber baffle (6071030000-E) | LF | 4,910 | $5.94 | $7.50 | $6.10 |
| 0232 | **" skimmer - (1-1/2") (6071050000-E) | EACH | 16 | $1,800.00 | $5,080.00 | $1,500.00 |
| 0233 | **" skimmer - (2") (6071050000-E) | EACH | 16 | $2,000.00 | $5,310.00 | $1,900.00 |
| 0234 | Seeding and mulching (6084000000-E) | ACRE | 126 | $2,527.82 | $2,700.00 | $2,400.00 |
| 0235 | Mowing (6087000000-E) | ACRE | 63 | $102.13 | $114.00 | $97.00 |
| 0236 | Seed for repair seeding (6090000000-E) | LB | 1,550 | $5.11 | $5.70 | $4.90 |
| 0237 | Fertilizer for repair seeding (6093000000-E) | TON | 4.25 | $1,021.34 | $1,140.00 | $970.00 |
| 0238 | Seed for supplemental seeding (6096000000-E) | LB | 2,650 | $5.11 | $5.70 | $4.90 |
| 0239 | Fertilizer topdressing (6108000000-E) | TON | 79.25 | $1,021.34 | $1,140.00 | $970.00 |
| 0240 | Specialized hand mowing (6114500000-N) | MHR | 10 | $102.13 | $114.00 | $97.00 |
| 0241 | Response for erosion control (6117000000-N) | EACH | 100 | $51.07 | $61.00 | $49.00 |
| 0242 | Concrete washout structure (6117500000-N) | EACH | 8 | $900.00 | $1,100.00 | $2,180.00 |
| 0243 | Reforestation (6123000000-E) | ACRE | 0.10 | $7,660.10 | $8,570.00 | $7,275.00 |
| 0244 | Generic erosion control item (EA) - fabric insert inlet protection cleanout (6132000000-N) | EACH | 300 | $118.75 | $152.00 | $122.00 |
| 0245 | Generic erosion control item (EA) - fabric insert inlet protection, type 1 (6132000000-N) | EACH | 100 | $118.75 | $152.00 | $122.00 |
| 0246 | Generic erosion control item (EA) - prefabricated concrete washout (6132000000-N) | EACH | 12 | $800.00 | $1,090.00 | $2,179.00 |
| 0247 | Pedestrian signal head (16", 1 section W/countdown) (7048500000-E) | EACH | 50 | $1,179.00 | $1,320.00 | $1,190.91 |
| 0248 | Signal cable (7060000000-E) | LF | 42,400 | $4.00 | $4.50 | $4.04 |
| 0249 | Vehicle signal head (12", 3 section) (7120000000-E) | EACH | 142 | $1,350.00 | $1,520.00 | $1,363.64 |
| 0250 | Vehicle signal head (12", 4 section) (7132000000-E) | EACH | 42 | $1,670.00 | $1,880.00 | $1,686.87 |
| 0251 | Vehicle signal head (12", 5 section) (7144000000-E) | EACH | 10 | $2,274.00 | $2,560.00 | $2,296.97 |
| 0252 | Messenger cable (1/4") (7252000000-E) | LF | 24,075 | $5.00 | $5.60 | $5.05 |
| 0253 | Messenger cable (3/8") (7264000000-E) | LF | 8,820 | $9.00 | $10.00 | $9.09 |
| 0254 | Tracer wire (7279000000-E) | LF | 1,750 | $1.50 | $1.70 | $1.52 |
| 0255 | Paved trench (***********) - (1, 2") (7288000000-E) | LF | 320 | $55.00 | $61.75 | $55.56 |
| 0256 | Unpaved trench (***********) - (1, 2") (7300000000-E) | LF | 10,145 | $11.00 | $12.25 | $11.11 |
| 0257 | Direct drill (***********) - (2, 2") (7301000000-E) | LF | 385 | $30.00 | $33.75 | $30.30 |
| 0258 | Junction box (standard size) (7324000000-N) | EACH | 91 | $826.00 | $928.00 | $834.34 |
| 0259 | Junction box (over-sized, heavy duty) (7348000000-N) | EACH | 11 | $1,561.00 | $1,750.00 | $1,576.77 |
| 0260 | Wood pole (7360000000-N) | EACH | 11 | $2,507.00 | $2,820.00 | $2,532.32 |
| 0261 | Guy assembly (7372000000-N) | EACH | 113 | $1,038.00 | $1,170.00 | $1,048.48 |
| 0262 | 1" riser with weatherhead (7408000000-E) | EACH | 4 | $631.00 | $709.00 | $637.37 |
| 0263 | 2" riser with weatherhead (7420000000-E) | EACH | 8 | $1,110.00 | $1,250.00 | $1,121.21 |
| 0264 | 2" riser with heat shrink tubing (7432000000-E) | EACH | 10 | $1,305.00 | $1,470.00 | $1,318.18 |
| 0265 | Inductive loop sawcut (7444000000-E) | LF | 11,130 | $25.00 | $28.00 | $25.25 |
| 0266 | Lead-in cable (14-2) (7456100000-E) | LF | 47,400 | $3.00 | $3.35 | $3.03 |
| 0267 | Site survey (7481000000-N) | EACH | 6 | $1,346.00 | $1,510.00 | $1,359.60 |
| 0268 | Camera without internal loop emulator processing unit (7481240000-N) | EACH | 13 | $5,878.00 | $6,600.00 | $5,937.37 |
| 0269 | External loop emulator processing unit (7481260000-N) | EACH | 5 | $17,643 | $19,820 | $17,821 |
| 0270 | Communications cable (** fiber) - (24) (7516000000-E) | LF | 25,685 | $5.00 | $5.60 | $5.05 |
| 0271 | Drop cable (7528000000-E) | LF | 4,825 | $5.00 | $5.60 | $5.05 |
| 0272 | Splice enclosure (7540000000-N) | EACH | 10 | $2,254.00 | $2,530.00 | $2,276.77 |
| 0273 | Modify splice enclosure (7541000000-N) | EACH | 1 | $1,649.00 | $1,850.00 | $1,665.66 |
| 0274 | Interconnect center (7552000000-N) | EACH | 11 | $2,591.00 | $2,910.00 | $2,617.17 |
| 0275 | Remove existing communications cable (7575160000-E) | LF | 315 | $1.00 | $1.10 | $1.01 |
| 0276 | Metal strain signal pole (7576000000-N) | EACH | 41 | $22,000 | $24,720 | $22,222 |
| 0277 | Soil test (7613000000-N) | EACH | 41 | $2,500.00 | $2,810.00 | $2,525.25 |
| 0278 | Drilled pier foundation (7614100000-E) | CY | 246 | $1,884.00 | $2,120.00 | $1,903.03 |
| 0279 | Sign for signals (7636000000-N) | EACH | 29 | $774.00 | $870.00 | $781.82 |
| 0280 | Type I post with foundation (7642100000-N) | EACH | 5 | $3,164.00 | $3,560.00 | $3,195.96 |
| 0281 | Type II pedestal with foundation (7642200000-N) | EACH | 45 | $3,877.00 | $4,360.00 | $3,916.16 |
| 0282 | Relocate existing sign (7648000000-N) | EACH | 7 | $399.00 | $448.00 | $403.03 |
| 0283 | Signal cabinet foundation (7684000000-N) | EACH | 9 | $3,081.00 | $3,460.00 | $3,112.12 |
| 0284 | Contlrs with CBNT (**************) - (2070E, base mounted) (7696000000-N) | EACH | 1 | $28,605 | $32,140 | $28,894 |
| 0285 | Detector card (***********) - (170) (7708000000-N) | EACH | 80 | $268.00 | $301.00 | $270.71 |
| 0286 | Install department supplied 2070 controller (7853000000-N) | EACH | 9 | $981.00 | $1,100.00 | $990.91 |
| 0287 | Cabinet base extender (7901000000-N) | EACH | 9 | $1,469.00 | $1,650.00 | $1,483.84 |
| 0288 | Metal pole foundation removal (7960000000-N) | EACH | 2 | $6,671.00 | $7,500.00 | $6,738.39 |
| 0289 | Metal pole removal (7972000000-N) | EACH | 2 | $1,866.00 | $2,100.00 | $1,884.85 |
| 0290 | Generic signal item (EA) - cabinet without controller (type 170, base mounted) (7980000000-N) | EACH | 8 | $22,069 | $24,800 | $22,292 |
| 0291 | Generic signal item (EA) - ethernet edge switch (7980000000-N) | EACH | 11 | $5,725.00 | $6,430.00 | $5,782.83 |
| 0292 | Generic signal item (EA) - luminaire arm for temporary video system (7980000000-N) | EACH | 10 | $1,018.00 | $1,140.00 | $1,028.28 |
| 0293 | Generic signal item (EA) - protective coating for strain pole (black) (7980000000-N) | EACH | 39 | $2,401.00 | $2,700.00 | $2,425.25 |
| 0294 | Generic signal item (EA) - protective coating for type I pushbutton post (black) (7980000000-N) | EACH | 4 | $136.00 | $153.00 | $137.37 |
| 0295 | Generic signal item (EA) - protective coating for type II signal pedestal (black) (7980000000-N) | EACH | 42 | $136.00 | $153.00 | $137.37 |
| 0296 | Generic signal item (EA) - relocate digital CCTV camera assembly (7980000000-N) | EACH | 2 | $2,700.00 | $3,030.00 | $2,727.28 |
| 0297 | Concrete barrier rail with moment slab (8504000000-E) | LF | 100 | $1,200.00 | $661.00 | $784.07 |
| 0298 | MSE retain wall no ** - (1) (8801000000-E) | SF | 522 | $180.00 | $235.00 | $200.00 |
| 0299 | MSE retain wall no ** - (2) (8801000000-E) | SF | 2,500 | $110.00 | $119.00 | $150.00 |
| 0300 | Generic ret wall item (LF) - concrete parapet with moment slab (8839000000-E) | LF | 269.91 | $800.00 | $725.00 | $500.00 |
| 0301 | CM&R temp access *********** - (55+24.00 -L-) (8017000000-N) | LS | 1 | $75,000 | $20,020 | $200,000 |
| 0302 | Remv exist STR ****** BRG (402) - (55+24.00 -L-) (8035000000-N) | LS | 1 | $100,000 | $98,730 | $200,000 |
| 0303 | Asbestos assessment (8065000000-N) | LS | 1 | $1,300.00 | $1,780.00 | $1,500.00 |
| 0304 | 3'-0" dia drilled piers in soil (8105520000-E) | LF | 107.40 | $1,500.00 | $790.00 | $1,555.00 |
| 0305 | 3'-0" dia drilled piers not in soil (8105620000-E) | LF | 108 | $2,000.00 | $2,290.00 | $2,400.00 |
| 0306 | Permanent steel casing for 3'-0" dia drilled pier (8111200000-E) | LF | 125 | $275.00 | $80.25 | $569.00 |
| 0307 | Sid inspections (8113000000-N) | EACH | 1 | $1,200.00 | $2,470.00 | $565.00 |
| 0308 | SPT testing (8114000000-N) | EACH | 1 | $1,500.00 | $2,470.00 | $565.00 |
| 0309 | CSL testing (8115000000-N) | EACH | 1 | $5,000.00 | $6,540.00 | $20,000 |
| 0310 | Uncl STR excav sta ***** - (55+24.00 -L-) (8121000000-N) | LS | 1 | $20,000 | $9,730.00 | $25,000 |
| 0311 | Reinforced concrete deck slab (8147000000-E) | SF | 11,620 | $60.00 | $64.75 | $60.00 |
| 0312 | Grooving bridge floors (8161000000-E) | SF | 10,316 | $1.50 | $1.85 | $1.80 |
| 0313 | Class A concrete (bridge) (8182000000-E) | CY | 234.10 | $1,500.00 | $2,110.00 | $1,500.00 |
| 0314 | BRG appr slab *********** - (55+24.00 -L-) (8210000000-N) | LS | 1 | $140,000 | $226,034 | $175,000 |
| 0315 | Reinforcing steel (bridge) (8217000000-E) | LB | 49,557 | $1.50 | $1.90 | $2.00 |
| 0316 | Spiral column reinforcing steel (bridge) (8238000000-E) | LB | 5,697 | $2.50 | $4.00 | $3.50 |
| 0317 | 36" prestressed concrete girders (8259000000-E) | LF | 1,300.01 | $450.00 | $340.00 | $450.00 |
| 0318 | Pile DRV equip setup ** steel piles - (HP 12 X 53) (8328200000-E) | EACH | 22 | $1,000.00 | $1,340.00 | $6,500.00 |
| 0319 | HP 12 X 53 steel piles (8364000000-E) | LF | 585 | $65.00 | $59.25 | $50.00 |
| 0320 | Steel pile points (8391000000-N) | EACH | 22 | $180.00 | $195.00 | $250.00 |
| 0321 | Two bar metal rail (8475000000-E) | LF | 542.58 | $200.00 | $225.00 | $275.00 |
| 0322 | 1'-**"X*****"conc parapet - (1'-2" X 3'-3") (8517000000-E) | LF | 131.17 | $280.00 | $263.00 | $215.00 |
| 0323 | 1'-**"X*****"conc parapet - (1'-2" X 3'-6") (8517000000-E) | LF | 131.17 | $280.00 | $267.00 | $220.00 |
| 0324 | Rip rap class II (2'-0" thick) (8608000000-E) | TON | 671 | $0.01 | $281.00 | $100.00 |
| 0325 | Geotextile for drainage (8622000000-E) | SY | 746 | $6.00 | $6.80 | $3.00 |
| 0326 | Elastomeric bearings (8657000000-N) | LS | 1 | $10,000 | $11,180 | $35,000 |
| 0327 | Foam joint seals (8692000000-N) | LS | 1 | $55,000 | $55,120 | $100,000 |
| 0328 | Portland cement for soil cement base (1187000000-E) | TON | 2,180 | $268.95 | $363.00 | $304.65 |
| 0329 | Asphalt curing seal (1209000000-E) | GAL | 23,290 | $6.00 | $7.50 | $6.23 |
| 0330 | Relocate camera sensor unit (7481280000-N) | EACH | 4 | $409.00 | $460.00 | $413.13 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NCDOT's tabulation for this contract. NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
Every contract let that day: NCDOT letting of September 16, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.