Pedestrian signal head (16", 1 section W/countdown), NCDOT 7048500000-E

Low bidders on NCDOT contracts carried a median of $1,250.00 per EACH for this item, over the 24 months to 20 OCT 2026, across 45 low bids. Half of all 228 bids fell between $1,200.00 and $1,552.70.

Owner
North Carolina DOT
Item
7048500000-E
Unit
EACH
Data through
20 OCT 2026

NCDOT prints this item as “16" PEDEST SIG HEAD 1 SEC W/CD”.

$1,250.00Low bidder's median, per EACH
$1,300.00Median of all bids, per EACH
45Contracts in the window

By year of letting

Pedestrian signal head (16", 1 section W/countdown), NCDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
201377$675.0031$737.56
201466$785.5032$751.34
20151010$762.5057$767.00
201666$746.4329$725.00
201799$700.0042$715.00
20181211$907.3353$861.10
20191313$975.0054$966.94
202011$1,000.004$1,122.00
20211111$933.0035$926.00
20221010$1,009.0033$970.00
20231818$1,130.0068$1,248.03
20241615$1,300.0072$1,342.50
20252121$1,311.00101$1,311.00
20261919$1,250.00107$1,300.00

Bid prices as published, not adjusted for inflation.

By county

CountyLow bidsLow-bid medianAll bidsMedian, all bids
Wake4$1,195.3625$1,300.00
Mecklenburg3$1,552.7020$1,450.00
Wayne3$1,250.0020$1,227.50
Forsyth3$1,641.6817$1,641.68
Cumberland4$1,250.0016$1,250.00
Guilford3$1,311.0012$1,335.00
Pedestrian signal head (16", 1 section W/countdown), NCDOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Quantity (EACH)Low bidsLow-bid median
2 to 611$1,250.00
6 to 811$1,250.00
8 to 1811$1,311.00
18 to 7712$1,270.36
Pedestrian signal head (16", 1 section W/countdown), NCDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

Pedestrian signal head (16", 1 section W/countdown), NCDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
20 OCT 2026C204338Wake9$1,200.00$1,444.008Blythe Construction IncNCDOT
15 SEP 2026C205206Onslow4$1,100.00$1,200.003Barnhill Contracting CompanyNCDOT
15 SEP 2026C205214Wilkes6$178.00$1,254.365James R Vannoy & Sons Construction Company IncNCDOT
15 SEP 2026C204947Caldwell16$1,292.00$1,292.003Branch Civil IncNCDOT
18 AUG 2026C205195Catawba18$1,367.35$1,163.504Blythe Development Co.NCDOT
18 AUG 2026C205219Rutherford37$1,150.00$1,150.001Wright Brothers Civil Construction LLCNCDOT
16 JUN 2026C205160Forsyth10$1,641.68$1,625.005Blythe Construction IncNCDOT
16 JUN 2026C205182Carteret8$1,200.00$1,200.002Barnhill Contracting CompanyNCDOT
16 JUN 2026C205157Randolph8$1,361.00$1,200.0011Branch Civil IncNCDOT
19 MAY 2026C205187Cumberland4$1,250.00$1,375.004Highland Paving Co LLCNCDOT
19 MAY 2026C204773Gaston, Mecklenburg18$1,714.92$1,709.9610Zachry Construction CorporationNCDOT
21 APR 2026C205130Wayne16$1,572.00$1,100.005Branch Civil IncNCDOT
17 MAR 2026C204512Wake28$1,190.72$1,216.364Conti Civil LLCNCDOT
17 MAR 2026C205013Mecklenburg8$1,100.00$1,250.009Mountaineer Contractors Inc and SubsidiariesNCDOT
17 FEB 2026C205036Robeson31$1,350.00$1,350.004Barnhill Contracting CompanyNCDOT
Latest NCDOT contracts carrying Pedestrian signal head (16", 1 section W/countdown)

Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.

How these prices were read

NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the NCDOT letting of 20 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy