NCDOT contract C204936 bid tabulation
GRADING, DRAINAGE, PAVING, AND STRUCTURES., GRADING, DRAINAGE, PAVING, AND STURCTURES. BRIDGE #000014 OVER CANE CREEK ON NC-87. Let by North Carolina DOT on February 17, 2026, Alamance. 7 bids received; low bid $7,695,971 by Kemp Sigmon Construction Co Inc.
- Owner
- North Carolina DOT
- Letting
- 17 FEB 2026
- Pay items
- 137
- Data through
- 20 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Kemp Sigmon Construction Co Inc | $7,695,971 | Low |
| 2 | Smith-Rowe, LLC | $7,776,815 | +1.0% |
| 3 | Blythe Construction Inc | $8,299,499 | +8.0% |
| 4 | W C English Incorporated | $8,640,573 | +12% |
| 5 | Dane Construction, Inc. | $8,756,539 | +14% |
| 6 | Blythe Development Co. | $9,367,347 | +22% |
| 7 | Caton Construction Group Inc | $9,883,100 | +28% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Kemp Sigmon Construction Co Inc | 2. Smith-Rowe, LLC | 3. Blythe Construction Inc | 4. W C English Incorporated | 5. Dane Construction, Inc. | 6. Blythe Development Co. |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Mobilization (0000100000-N) | LS | 1 | $373,000 | $388,800 | $410,000 | $432,000 | $437,825 | $480,000 |
| 0002 | Construction surveying (0000400000-N) | LS | 1 | $75,000 | $32,500 | $195,000 | $101,308 | $41,000 | $120,000 |
| 0003 | Grading (0043000000-N) | LS | 1 | $1,350,000 | $1,763,914 | $1,600,000 | $1,628,733 | $1,652,435 | $1,982,000 |
| 0004 | Supplementary clearing & grubbing (0050000000-E) | ACRE | 1 | $100.00 | $1.00 | $7,500.00 | $0.01 | $3,000.00 | $9,900.00 |
| 0005 | Undercut excavation (0057000000-E) | CY | 920 | $10.00 | $32.30 | $13.00 | $14.60 | $39.00 | $25.00 |
| 0006 | Select granular material (0195000000-E) | CY | 200 | $10.00 | $62.45 | $71.00 | $58.00 | $36.00 | $50.00 |
| 0007 | Geotextile for soil stabilization (0196000000-E) | SY | 1,400 | $1.50 | $5.40 | $4.00 | $3.90 | $4.00 | $3.00 |
| 0008 | Temporary shoring (0199000000-E) | SF | 750 | $150.00 | $207.95 | $150.00 | $107.00 | $325.00 | $145.00 |
| 0009 | Generic grading item (LS) - type 1 bridge approach fill, station 21+19.00 -L- (0248000000-N) | LS | 1 | $30,000 | $47,550 | $45,000 | $28,000 | $50,000 | $39,800 |
| 0010 | Foundation conditioning material, minor structures (0318000000-E) | TON | 100 | $10.00 | $54.50 | $60.00 | $54.55 | $65.00 | $50.00 |
| 0011 | FND condit geotextile (4A) (0321000000-E) | SY | 305 | $1.00 | $6.15 | $4.00 | $4.45 | $5.00 | $3.00 |
| 0012 | 15" drainage pipe (0335200000-E) | LF | 308 | $75.00 | $71.61 | $110.00 | $75.45 | $78.00 | $100.00 |
| 0013 | 15" RC pipe culverts, class III (0366000000-E) | LF | 168 | $85.00 | $106.29 | $120.00 | $108.05 | $113.00 | $110.00 |
| 0014 | 18" RC pipe culverts, class III (0372000000-E) | LF | 32 | $95.00 | $121.16 | $155.00 | $177.90 | $128.00 | $125.00 |
| 0015 | 24" RC pipe culverts, class III (0378000000-E) | LF | 52 | $125.00 | $123.48 | $205.00 | $190.85 | $186.00 | $175.00 |
| 0016 | 30" RC pipe culverts, class III (0384000000-E) | LF | 236 | $175.00 | $185.65 | $195.00 | $177.10 | $241.00 | $190.00 |
| 0017 | 18" RC pipe culverts, class IV (0448300000-E) | LF | 44 | $100.00 | $110.00 | $210.00 | $153.05 | $223.00 | $200.00 |
| 0018 | 15" CS pipe culverts, 0.064" thick (0582000000-E) | LF | 32 | $85.00 | $139.48 | $225.00 | $166.00 | $113.00 | $120.00 |
| 0019 | 18" CS pipe culverts, 0.064" thick inlet used based on county (0588000000-E) | LF | 36 | $100.00 | $110.34 | $230.00 | $152.00 | $123.00 | $80.00 |
| 0020 | **" CS elbow *****" thick - (15", 0.064") (0636000000-E) | EACH | 2 | $750.00 | $1,213.14 | $1,625.00 | $512.90 | $900.00 | $1,100.00 |
| 0021 | **" CS elbow *****" thick - (18", 0.064") (0636000000-E) | EACH | 2 | $800.00 | $1,261.05 | $1,675.00 | $540.95 | $930.00 | $1,100.00 |
| 0022 | Pipe removal (0995000000-E) | LF | 179 | $10.00 | $118.17 | $35.00 | $18.80 | $21.00 | $45.00 |
| 0023 | Shallow undercut (1099500000-E) | CY | 150 | $15.00 | $27.20 | $17.00 | $14.60 | $19.00 | $26.00 |
| 0024 | Class IV subgrade stabilization (1099700000-E) | TON | 450 | $25.00 | $54.05 | $45.00 | $38.35 | $41.00 | $40.00 |
| 0025 | Geotextile for subgrade stabilization (1112000000-E) | SY | 450 | $3.50 | $6.55 | $4.00 | $4.85 | $4.00 | $6.00 |
| 0026 | Aggregate base course (1121000000-E) | TON | 1,727 | $38.00 | $58.52 | $47.50 | $56.65 | $38.00 | $45.00 |
| 0027 | Incidental stone base (1220000000-E) | TON | 500 | $10.00 | $56.60 | $47.00 | $49.90 | $43.00 | $40.00 |
| 0028 | Prime coat (1275000000-E) | GAL | 602 | $10.00 | $7.00 | $4.00 | $15.75 | $5.00 | $6.00 |
| 0029 | Incidental milling (1330000000-E) | SY | 220 | $35.00 | $49.55 | $30.63 | $36.75 | $35.00 | $60.00 |
| 0030 | Asphalt conc base course, type B25.0C (1491000000-E) | TON | 2,170 | $110.00 | $110.00 | $110.00 | $99.75 | $95.00 | $140.00 |
| 0031 | Asphalt conc intermediate course, type I19.0C (1503000000-E) | TON | 1,060 | $115.00 | $115.00 | $115.00 | $115.50 | $110.00 | $140.00 |
| 0032 | Asphalt conc surface course, type S9.5C (1523000000-E) | TON | 1,870 | $115.00 | $115.00 | $115.00 | $94.50 | $90.00 | $140.00 |
| 0033 | Asphalt binder for plant mix (1575000000-E) | TON | 275 | $735.00 | $735.00 | $735.00 | $630.00 | $600.00 | $900.00 |
| 0034 | Asphalt plant mix, pavement repair (1693000000-E) | TON | 500 | $50.00 | $1.00 | $308.00 | $190.50 | $75.00 | $240.00 |
| 0035 | Subdrain excavation (2022000000-E) | CY | 44.80 | $30.00 | $27.65 | $55.00 | $44.00 | $20.00 | $30.00 |
| 0036 | Geotextile for subsurface drains (2026000000-E) | SY | 200 | $2.00 | $4.30 | $4.00 | $4.20 | $8.00 | $4.00 |
| 0037 | Subdrain coarse aggregate (2036000000-E) | CY | 33.60 | $85.00 | $53.35 | $60.00 | $84.05 | $100.00 | $110.00 |
| 0038 | 6" perforated subdrain pipe (2044000000-E) | LF | 200 | $12.00 | $6.25 | $18.00 | $17.00 | $18.00 | $15.00 |
| 0039 | Subdrain pipe outlet (2070000000-N) | EACH | 1 | $500.00 | $547.25 | $550.00 | $378.30 | $521.00 | $800.00 |
| 0040 | 6" outlet pipe (2077000000-E) | LF | 6 | $50.00 | $64.20 | $60.00 | $56.60 | $43.00 | $30.00 |
| 0041 | Pipe plugs (2264000000-E) | CY | 0.13 | $7,500.00 | $1.00 | $8,000.00 | $7,343.00 | $3,800.00 | $1,500.00 |
| 0042 | Flowable fill (2275000000-E) | CY | 3 | $500.00 | $2,241.57 | $450.00 | $312.20 | $620.00 | $500.00 |
| 0043 | Masonry drainage structures (2286000000-N) | EACH | 8 | $2,500.00 | $4,867.32 | $5,250.00 | $5,501.60 | $3,200.00 | $5,000.00 |
| 0044 | Masonry drainage structures (2308000000-E) | LF | 1 | $500.00 | $698.97 | $1,500.00 | $907.00 | $700.00 | $730.00 |
| 0045 | Frame with two grates, STD 840.20 (2364200000-N) | EACH | 4 | $1,000.00 | $1,369.95 | $1,950.00 | $1,414.09 | $1,000.00 | $1,300.00 |
| 0046 | Frame with two grates, STD 840.22 (2365000000-N) | EACH | 3 | $1,200.00 | $2,904.17 | $1,950.00 | $1,511.30 | $1,000.00 | $1,300.00 |
| 0047 | Shoulder berm gutter (2556000000-E) | LF | 98 | $85.00 | $60.50 | $60.50 | $72.30 | $60.50 | $72.00 |
| 0048 | Steel beam guardrail (3030000000-E) | LF | 1,800 | $23.00 | $23.50 | $23.00 | $25.85 | $23.50 | $30.00 |
| 0049 | Additional guardrail posts (3150000000-N) | EACH | 10 | $50.00 | $1.00 | $50.00 | $1.10 | $1.00 | $1.00 |
| 0050 | Guardrail end units, type TL-3 (3287000000-N) | EACH | 6 | $3,300.00 | $3,200.00 | $3,300.00 | $3,520.00 | $3,200.00 | $4,000.00 |
| 0051 | Guardrail anchor units, type B-77 (3317000000-N) | EACH | 4 | $300.00 | $2,600.00 | $3,000.00 | $2,860.00 | $2,600.00 | $3,100.00 |
| 0052 | Remove existing guardrail (3360000000-E) | LF | 990 | $2.00 | $1.00 | $2.00 | $1.10 | $1.00 | $1.00 |
| 0053 | Temporary steel beam guardrail (3380000000-E) | LF | 1,738 | $11.00 | $12.00 | $11.00 | $13.20 | $12.00 | $14.00 |
| 0054 | Temp GDRL anch units ****** - (III) (3387000000-N) | EACH | 4 | $1,500.00 | $1,800.00 | $1,500.00 | $1,980.00 | $1,800.00 | $2,100.00 |
| 0055 | Temp GDRL end units ***** - (TL-3) (3389150000-N) | EACH | 6 | $1,650.00 | $1,500.00 | $1,650.00 | $1,650.00 | $1,500.00 | $1,800.00 |
| 0056 | Temporary additional guardrail posts (3389160000-N) | EACH | 10 | $15.00 | $1.00 | $15.00 | $1.10 | $1.00 | $1.00 |
| 0057 | Rip rap, class I (3628000000-E) | TON | 11 | $125.00 | $99.50 | $260.00 | $106.85 | $57.00 | $80.00 |
| 0058 | Rip rap, class B (3649000000-E) | TON | 590 | $80.00 | $84.50 | $70.00 | $67.55 | $57.00 | $60.00 |
| 0059 | Geotextile for drainage (3656000000-E) | SY | 1,550 | $2.00 | $5.35 | $4.00 | $3.15 | $4.00 | $3.00 |
| 0060 | Contr furn, type ***sign - (D) (4025000000-E) | SF | 8 | $25.00 | $25.00 | $28.00 | $27.50 | $28.00 | $18.00 |
| 0061 | Contr furn, type ***sign - (E) (4025000000-E) | SF | 18 | $20.00 | $20.00 | $24.00 | $22.00 | $24.00 | $18.00 |
| 0062 | Supports, 3-LB steel U-channel (4072000000-E) | LF | 60 | $12.00 | $12.00 | $7.65 | $13.20 | $7.65 | $10.00 |
| 0063 | Sign erection, type D (4096000000-N) | EACH | 2 | $125.00 | $125.00 | $285.00 | $137.50 | $285.00 | $180.00 |
| 0064 | Sign erection, type E (4102000000-N) | EACH | 2 | $125.00 | $125.00 | $225.00 | $137.50 | $225.00 | $150.00 |
| 0065 | Disposal of sign system, U-channel (4155000000-N) | EACH | 4 | $2.00 | $2.00 | $15.00 | $4.40 | $15.00 | $30.00 |
| 0066 | Work zone signs (stationary) (4400000000-E) | SF | 128 | $12.00 | $12.00 | $7.55 | $13.20 | $7.55 | $8.00 |
| 0067 | Work zone signs (portable) (4405000000-E) | SF | 224 | $9.50 | $21.05 | $8.55 | $10.45 | $8.55 | $16.00 |
| 0068 | Work zone signs (barricade mounted) (4410000000-E) | SF | 72 | $8.00 | $8.00 | $8.85 | $8.80 | $8.85 | $8.50 |
| 0069 | Drums (4430000000-N) | EACH | 117 | $125.00 | $90.00 | $46.00 | $69.00 | $46.00 | $65.00 |
| 0070 | Barricades (type III) (4445000000-E) | LF | 36 | $25.00 | $25.00 | $25.00 | $27.50 | $25.00 | $34.00 |
| 0071 | Flagger (4455000000-N) | DAY | 28 | $350.00 | $1,055.00 | $737.37 | $440.45 | $400.00 | $1,000.00 |
| 0072 | Temporary raised pavement markers (4650000000-N) | EACH | 122 | $8.70 | $9.00 | $9.00 | $9.90 | $9.00 | $10.00 |
| 0073 | Paint pavement marking lines (4") (4810000000-E) | LF | 11,456 | $0.40 | $0.10 | $0.10 | $0.11 | $0.10 | $0.10 |
| 0074 | Removal of pavement marking lines (4") (4850000000-E) | LF | 4,093 | $0.55 | $0.95 | $0.95 | $1.05 | $0.95 | $5.00 |
| 0075 | Generic pavement marking item (LF) - integrated multipolymer pavement marking lines (4", 90 mils) (4890000000-E) | LF | 11,788 | $2.00 | $1.55 | $1.55 | $1.71 | $1.55 | $1.80 |
| 0076 | Generic pavement marking item (EA) - polycarbonate H-shaped markers (4895000000-N) | EACH | 42 | $117.00 | $75.00 | $75.00 | $82.50 | $75.00 | $90.00 |
| 0077 | Permanent raised pavement markers (4900000000-N) | EACH | 3 | $37.00 | $9.00 | $9.00 | $9.90 | $9.00 | $10.00 |
| 0078 | Temporary silt fence (6000000000-E) | LF | 5,600 | $2.70 | $2.51 | $2.70 | $2.75 | $2.51 | $4.00 |
| 0079 | Stone for erosion control, class A (6006000000-E) | TON | 150 | $20.00 | $80.50 | $70.00 | $66.20 | $55.00 | $60.00 |
| 0080 | Stone for erosion control, class B (6009000000-E) | TON | 1,850 | $20.00 | $0.01 | $70.00 | $66.20 | $58.00 | $60.00 |
| 0081 | Sediment control stone (6012000000-E) | TON | 660 | $20.00 | $78.50 | $60.00 | $57.55 | $53.00 | $50.00 |
| 0082 | Temporary mulching (6015000000-E) | ACRE | 6 | $1,900.00 | $1,050.00 | $1,900.00 | $1,155.00 | $1,050.00 | $1,050.00 |
| 0083 | Seed for temporary seeding (6018000000-E) | LB | 400 | $1.00 | $1.00 | $1.00 | $1.10 | $1.00 | $1.00 |
| 0084 | Fertilizer for temporary seeding (6021000000-E) | TON | 3 | $275.00 | $1,000.00 | $275.00 | $1,100.00 | $1,000.00 | $1,000.00 |
| 0085 | Temporary slope drains (6024000000-E) | LF | 570 | $10.00 | $22.85 | $18.79 | $14.85 | $30.00 | $24.00 |
| 0086 | Safety fence (6029000000-E) | LF | 460 | $1.80 | $3.00 | $1.80 | $3.30 | $3.00 | $3.00 |
| 0087 | Silt excavation (6030000000-E) | CY | 4,580 | $0.01 | $0.01 | $20.00 | $0.01 | $1.00 | $20.00 |
| 0088 | Matting for erosion control (6036000000-E) | SY | 22,100 | $1.70 | $1.49 | $1.70 | $1.65 | $1.49 | $1.50 |
| 0089 | Coir fiber mat (6037000000-E) | SY | 100 | $5.00 | $28.00 | $5.00 | $19.80 | $18.00 | $18.00 |
| 0090 | 1/4" hardware cloth (6042000000-E) | LF | 550 | $6.00 | $4.00 | $6.00 | $4.40 | $4.00 | $4.00 |
| 0091 | Low permeability geotextile (6043000000-E) | SY | 200 | $10.00 | $18.50 | $13.00 | $4.55 | $6.50 | $5.00 |
| 0092 | **" temporary pipe - (24") (6045000000-E) | LF | 285 | $50.00 | $92.70 | $95.00 | $46.30 | $75.00 | $70.00 |
| 0093 | Floating turbidity curtain (6048000000-E) | SY | 80 | $75.00 | $55.70 | $100.00 | $80.60 | $55.00 | $40.00 |
| 0094 | Flocculant (6071002000-E) | LB | 485 | $7.00 | $1.00 | $7.00 | $1.10 | $1.00 | $5.00 |
| 0095 | Coir fiber wattle (6071012000-E) | LF | 80 | $13.00 | $25.00 | $13.00 | $16.50 | $8.00 | $15.00 |
| 0096 | Coir fiber baffle (6071030000-E) | LF | 660 | $6.50 | $7.50 | $6.50 | $8.25 | $8.00 | $7.50 |
| 0097 | **" skimmer - (1-1/2") (6071050000-E) | EACH | 6 | $1,750.00 | $1,405.00 | $2,500.00 | $1,544.00 | $1,700.00 | $880.00 |
| 0098 | Seeding and mulching (6084000000-E) | ACRE | 6 | $2,790.00 | $2,650.00 | $2,790.00 | $2,915.00 | $2,650.00 | $2,650.00 |
| 0099 | Mowing (6087000000-E) | ACRE | 3 | $400.00 | $200.00 | $175.00 | $220.00 | $200.00 | $200.00 |
| 0100 | Seed for repair seeding (6090000000-E) | LB | 100 | $4.00 | $5.00 | $4.00 | $5.50 | $5.00 | $5.00 |
| 0101 | Fertilizer for repair seeding (6093000000-E) | TON | 0.25 | $400.00 | $1,100.00 | $400.00 | $1,210.00 | $1,100.00 | $1,100.00 |
| 0102 | Seed for supplemental seeding (6096000000-E) | LB | 200 | $4.00 | $5.00 | $4.00 | $5.50 | $5.00 | $5.00 |
| 0103 | Fertilizer topdressing (6108000000-E) | TON | 5.75 | $400.00 | $1,000.00 | $400.00 | $1,100.00 | $1,000.00 | $1,000.00 |
| 0104 | Specialized hand mowing (6114500000-N) | MHR | 10 | $55.00 | $250.00 | $55.00 | $275.00 | $250.00 | $250.00 |
| 0105 | Manual litter removal (6114800000-N) | MHR | 3 | $55.00 | $116.15 | $136.03 | $243.80 | $75.00 | $200.00 |
| 0106 | Litter disposal (6114900000-E) | TON | 1 | $250.00 | $502.75 | $500.00 | $2,105.00 | $450.00 | $400.00 |
| 0107 | Response for erosion control (6117000000-N) | EACH | 25 | $200.00 | $10.00 | $200.00 | $11.00 | $10.00 | $200.00 |
| 0108 | Concrete washout structure (6117500000-N) | EACH | 1 | $1,500.00 | $1,065.00 | $900.00 | $3,259.00 | $3,250.00 | $1,100.00 |
| 0109 | Reforestation (6123000000-E) | ACRE | 0.10 | $7,850.00 | $3,000.00 | $7,850.00 | $3,300.00 | $3,000.00 | $5,000.00 |
| 0110 | Generic erosion control item (EA) - fabric insert inlet protection cleanout (6132000000-N) | EACH | 18 | $125.00 | $85.50 | $200.00 | $184.55 | $450.00 | $83.00 |
| 0111 | Generic erosion control item (EA) - fabric insert inlet protection, type 1 (6132000000-N) | EACH | 6 | $200.00 | $267.80 | $200.00 | $302.00 | $500.00 | $138.00 |
| 0112 | Generic erosion control item (EA) - prefabricated concrete washout (6132000000-N) | EACH | 3 | $1,000.00 | $650.00 | $600.00 | $302.00 | $1,500.00 | $2,000.00 |
| 0113 | CM&R temp STR *********** - (21+22.00 -L- det) (8007000000-N) | LS | 1 | $2,150,000 | $1,578,222 | $1,350,000 | $2,108,000 | $1,677,700 | $2,200,000 |
| 0114 | Remv exist STR ****** BRG (402) - (21+19.00 -L-) (8035000000-N) | LS | 1 | $175,000 | $322,586 | $325,000 | $723,000 | $545,000 | $303,000 |
| 0115 | Asbestos assessment (8065000000-N) | LS | 1 | $230,000 | $1,559.99 | $1,000.00 | $1,980.00 | $1,400.00 | $2,000.00 |
| 0116 | Pile excavation in soil (8096000000-E) | LF | 18.80 | $345.00 | $478.44 | $698.00 | $550.00 | $930.00 | $700.00 |
| 0117 | Pile excavation not in soil (8097000000-E) | LF | 51.20 | $345.00 | $478.44 | $613.00 | $550.00 | $645.00 | $700.00 |
| 0118 | 3'-0" dia drilled piers in soil (8105520000-E) | LF | 50.60 | $1,700.00 | $1,669.15 | $1,400.00 | $1,650.00 | $2,250.00 | $1,500.00 |
| 0119 | 3'-0" dia drilled piers not in soil (8105620000-E) | LF | 111.40 | $1,700.00 | $1,669.15 | $1,400.00 | $1,650.00 | $2,550.00 | $1,500.00 |
| 0120 | Permanent steel casing for 3'-0" dia drilled pier (8111200000-E) | LF | 51.60 | $245.00 | $368.06 | $245.00 | $280.00 | $350.00 | $300.00 |
| 0121 | CSL testing (8115000000-N) | EACH | 2 | $1,000.00 | $1,725.00 | $1,000.00 | $1,150.00 | $1,000.00 | $2,500.00 |
| 0122 | Uncl STR excav sta ***** - (21+19.00 -L-) (8121000000-N) | LS | 1 | $10,000 | $73,410 | $45,000 | $124,000 | $145,000 | $25,000 |
| 0123 | Reinforced concrete deck slab (8147000000-E) | SF | 8,962 | $65.00 | $57.97 | $75.00 | $57.00 | $60.50 | $70.00 |
| 0124 | Grooving bridge floors (8161000000-E) | SF | 8,492 | $1.00 | $1.31 | $1.00 | $0.91 | $0.85 | $1.10 |
| 0125 | Class A concrete (bridge) (8182000000-E) | CY | 103.70 | $1,250.00 | $1,798.75 | $1,800.00 | $1,900.00 | $2,975.00 | $2,150.00 |
| 0126 | BRG appr slab *********** - (21+19.00 -L-) (8210000000-N) | LS | 1 | $55,000 | $47,525 | $60,000 | $42,000 | $50,000 | $70,000 |
| 0127 | Reinforcing steel (bridge) (8217000000-E) | LB | 29,971 | $2.00 | $1.76 | $5.00 | $1.34 | $2.00 | $2.00 |
| 0128 | Spiral column reinforcing steel (bridge) (8238000000-E) | LB | 3,580 | $3.00 | $3.98 | $5.00 | $2.69 | $4.25 | $3.50 |
| 0129 | 54" prestressed concrete girders (8265000000-E) | LF | 909 | $350.00 | $414.03 | $605.00 | $385.00 | $750.00 | $430.00 |
| 0130 | Pile DRV equip setup ** steel piles - (HP 12 X 53) (8328200000-E) | EACH | 14 | $1,792.31 | $1.00 | $2,000.00 | $120.00 | $1,750.00 | $1,350.00 |
| 0131 | HP 12 X 53 steel piles (8364000000-E) | LF | 300 | $55.00 | $59.78 | $160.00 | $106.00 | $50.00 | $90.00 |
| 0132 | Steel pile points (8391000000-N) | EACH | 14 | $160.00 | $1.00 | $180.00 | $188.00 | $600.00 | $450.00 |
| 0133 | Dynamic pile testing (8394000000-N) | EACH | 1 | $3,000.00 | $1.00 | $2,500.00 | $2,200.00 | $2,000.00 | $2,400.00 |
| 0134 | Concrete barrier rail (8503000000-E) | LF | 456.67 | $180.00 | $160.13 | $145.00 | $146.00 | $150.00 | $180.00 |
| 0135 | Rip rap class II (2'-0" thick) (8608000000-E) | TON | 1,025 | $75.00 | $82.41 | $90.00 | $68.00 | $88.25 | $90.00 |
| 0136 | Geotextile for drainage (8622000000-E) | SY | 1,140 | $2.00 | $5.10 | $4.00 | $3.50 | $4.00 | $4.00 |
| 0137 | Elastomeric bearings (8657000000-N) | LS | 1 | $10,000 | $8,450.00 | $24,650 | $24,000 | $25,000 | $13,500 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NCDOT's tabulation for this contract. NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
Every contract let that day: NCDOT letting of February 17, 2026. Compiled by Mirage Metrics.