NCDOT contract C205044 bid tabulation
GRADING, DRAINAGE, PAVING, AND STRUCTURE. BRIDGE #850006 OVER NC-268, SOUTHERN RAILROAD TRACKS, AND THE YADKIN RIVER ON I-77. Let by North Carolina DOT on November 18, 2025, Surry, Yadkin. 6 bids received; low bid $16,781,818 by Smith-Rowe, LLC.
- Owner
- North Carolina DOT
- Letting
- 18 NOV 2025
- Pay items
- 189
- Data through
- 20 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Smith-Rowe, LLC | $16,781,818 | Low |
| 2 | Zachry Construction Corporation | $17,043,768 | +2.0% |
| 3 | W C English Incorporated | $19,502,517 | +16% |
| 4 | Caton Construction Group Inc | $19,548,450 | +16% |
| 5 | Crowder Construction Company | $21,817,897 | +30% |
| 6 | Blythe Construction Inc | $22,843,170 | +36% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Smith-Rowe, LLC | 2. Zachry Construction Corporation | 3. W C English Incorporated | 4. Caton Construction Group Inc | 5. Crowder Construction Company | 6. Blythe Construction Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Mobilization (0000100000-N) | LS | 1 | $839,000 | $851,823 | $1,000,000 | $977,423 | $1,090,895 | $1,126,000 |
| 0002 | Construction surveying (0000400000-N) | LS | 1 | $45,000 | $250,000 | $169,188 | $44,746 | $118,603 | $360,000 |
| 0003 | Unclassified excavation (0022000000-E) | CY | 22,640 | $0.01 | $12.30 | $20.27 | $25.50 | $27.75 | $20.00 |
| 0004 | Supplementary clearing & grubbing (0050000000-E) | ACRE | 1 | $1.00 | $23,326 | $1.15 | $28,210 | $5,282.06 | $5,000.00 |
| 0005 | Undercut excavation (0057000000-E) | CY | 450 | $39.61 | $56.89 | $28.70 | $78.00 | $73.11 | $20.00 |
| 0006 | Grading (0063000000-N) | LS | 1 | $1,742,086 | $750,000 | $925,000 | $898,553 | $520,553 | $4,860,000 |
| 0007 | Drainage ditch excavation (0134000000-E) | CY | 330 | $0.01 | $8.21 | $20.37 | $38.50 | $62.68 | $26.00 |
| 0008 | Select granular material (0195000000-E) | CY | 400 | $0.01 | $71.85 | $75.35 | $123.50 | $97.61 | $66.00 |
| 0009 | Geotextile for soil stabilization (0196000000-E) | SY | 500 | $3.45 | $3.07 | $3.73 | $6.50 | $6.20 | $5.00 |
| 0010 | Temporary shoring (0199000000-E) | SF | 1,035 | $59.48 | $70.00 | $88.70 | $68.73 | $286.21 | $150.00 |
| 0011 | Generic grading item (LS) - type 1 bridge approach fill, station 32+28.00 -L- (0248000000-N) | LS | 1 | $54,800 | $109,525 | $37,371 | $71,874 | $130,034 | $50,000 |
| 0012 | Generic grading item (TON) - hauling and disposal of petroleum contaminated soil (0255000000-E) | TON | 100 | $83.28 | $105.53 | $118.09 | $348.00 | $1,523.30 | $200.00 |
| 0013 | Foundation conditioning material, minor structures (0318000000-E) | TON | 240 | $61.85 | $60.58 | $68.38 | $86.50 | $94.34 | $70.00 |
| 0014 | FND condit geotextile (4A) (0321000000-E) | SY | 760 | $6.25 | $4.30 | $4.89 | $6.50 | $4.56 | $5.00 |
| 0015 | **" side drain pipe - (30") (0342000000-E) | LF | 12 | $281.80 | $149.77 | $252.43 | $196.50 | $341.74 | $140.00 |
| 0016 | 15" side drain pipe (0343000000-E) | LF | 784 | $89.16 | $86.18 | $77.04 | $149.50 | $130.88 | $140.00 |
| 0017 | 18" side drain pipe (0344000000-E) | LF | 52 | $150.04 | $107.58 | $147.43 | $162.00 | $176.20 | $135.00 |
| 0018 | 24" side drain pipe (0345000000-E) | LF | 76 | $131.86 | $136.80 | $120.05 | $176.00 | $163.10 | $130.00 |
| 0019 | 15" RC pipe culverts, class III (0366000000-E) | LF | 160 | $115.34 | $97.48 | $118.14 | $126.50 | $198.39 | $110.00 |
| 0020 | 15" RC pipe culverts, class IV (0448200000-E) | LF | 60 | $90.54 | $104.08 | $117.30 | $134.50 | $186.91 | $130.00 |
| 0021 | 18" RC pipe culverts, class IV (0448300000-E) | LF | 164 | $111.87 | $128.34 | $136.41 | $264.50 | $193.22 | $125.00 |
| 0022 | 30" RC pipe culverts, class IV (0448500000-E) | LF | 40 | $362.93 | $234.83 | $222.50 | $374.00 | $354.28 | $130.00 |
| 0023 | 15" CS pipe culverts, 0.064" thick (0582000000-E) | LF | 80 | $108.14 | $79.56 | $129.69 | $370.50 | $227.32 | $95.00 |
| 0024 | 24" CS pipe culverts, 0.064" thick (0594000000-E) | LF | 448 | $121.51 | $120.71 | $158.19 | $159.00 | $203.91 | $155.00 |
| 0025 | **" CS elbow *****" thick - (15", 0.064") (0636000000-E) | EACH | 2 | $300.00 | $1,003.66 | $530.31 | $1,919.00 | $916.40 | $450.00 |
| 0026 | **" CS elbow *****" thick - (24", 0.064") (0636000000-E) | EACH | 8 | $400.00 | $1,209.38 | $763.74 | $2,256.00 | $1,214.64 | $500.00 |
| 0027 | **"WLD STL pipe grad B in soil - (18", 0.500") (0973100000-E) | LF | 38 | $1,358.66 | $2,169.54 | $1,753.75 | $739.80 | $1,813.27 | $700.00 |
| 0028 | **"WLD STL pipe grad B in soil - (24", 0.500") (0973100000-E) | LF | 151 | $3,065.20 | $2,210.54 | $1,817.00 | $893.88 | $1,870.49 | $715.00 |
| 0029 | **"WLD STL pipe grad B not in soil - (18", 0.500") (0973300000-E) | LF | 38 | $1.00 | $2,169.54 | $2,725.50 | $1,693.88 | $2,692.41 | $1,355.00 |
| 0030 | **"WLD STL pipe grad B not in soil - (24", 0.500") (0973300000-E) | LF | 151 | $1.00 | $2,210.54 | $2,794.50 | $2,857.14 | $2,754.84 | $1,420.00 |
| 0031 | Pipe removal (0995000000-E) | LF | 1,309 | $17.91 | $35.68 | $19.20 | $94.00 | $39.10 | $20.00 |
| 0032 | Shallow undercut (1099500000-E) | CY | 1,200 | $17.75 | $23.90 | $20.13 | $53.50 | $75.38 | $25.00 |
| 0033 | Class IV subgrade stabilization (1099700000-E) | TON | 3,800 | $48.14 | $44.28 | $47.21 | $92.50 | $82.51 | $40.00 |
| 0034 | Geotextile for subgrade stabilization (1112000000-E) | SY | 5,640 | $4.73 | $5.33 | $5.02 | $6.00 | $4.39 | $5.00 |
| 0035 | Aggregate base course (1121000000-E) | TON | 50 | $87.11 | $46.83 | $78.28 | $446.00 | $109.08 | $100.00 |
| 0036 | Mill asp PVMT *****" DTH - (1-1/2") (1297000000-E) | SY | 630 | $16.02 | $16.26 | $23.00 | $9.55 | $20.20 | $25.00 |
| 0037 | Mill asp PVMT *****" DTH - (3") (1297000000-E) | SY | 630 | $16.02 | $16.26 | $34.50 | $9.55 | $30.30 | $12.00 |
| 0038 | Asphalt conc base course, type B25.0C (1491000000-E) | TON | 2,650 | $103.00 | $124.75 | $118.45 | $104.04 | $104.04 | $103.00 |
| 0039 | Asphalt conc intermediate course, type I19.0C (1503000000-E) | TON | 2,110 | $103.00 | $124.75 | $118.45 | $104.04 | $104.04 | $103.00 |
| 0040 | Asphalt conc surface course, type S9.5B (1519000000-E) | TON | 270 | $120.00 | $145.34 | $138.00 | $121.21 | $121.21 | $120.00 |
| 0041 | Asphalt conc surface course, type S9.5C (1523000000-E) | TON | 1,770 | $113.00 | $136.86 | $129.95 | $114.14 | $114.14 | $113.00 |
| 0042 | Asphalt binder for plant mix (1575000000-E) | TON | 345 | $865.00 | $1,047.65 | $994.75 | $873.74 | $873.74 | $865.00 |
| 0043 | Asphalt plant mix, pavement repair (1693000000-E) | TON | 75 | $290.29 | $419.71 | $231.06 | $600.00 | $225.00 | $191.28 |
| 0044 | Generic paving item (LF) 665 - milled rumble strips (asphalt concrete), (16") (1841000000-E) | LF | 1,097 | $3.77 | $1.22 | $8.27 | $6.15 | $1.06 | $2.00 |
| 0045 | ******"PCC PVMT thru LNS - (13") (1847000000-E) | SY | 3,200 | $269.00 | $182.63 | $314.06 | $269.00 | $273.10 | $140.00 |
| 0046 | ******"PCC PVMT misc - (13") (1869000000-E) | SY | 775 | $237.00 | $161.00 | $276.70 | $237.00 | $240.61 | $140.00 |
| 0047 | Nonwoven geotextile interlayer (1920000000-E) | SY | 3,920 | $6.20 | $4.81 | $9.09 | $5.50 | $4.86 | $6.00 |
| 0048 | Milled rumble strips (concrete shoulders) (1925000000-E) | LF | 1,097 | $15.46 | $1.22 | $8.27 | $6.15 | $1.06 | $2.00 |
| 0049 | Right-of-way markers (2000000000-N) | EACH | 9 | $275.00 | $479.67 | $316.25 | $302.00 | $0.00 | $355.00 |
| 0050 | Subdrain excavation (2022000000-E) | CY | 44.80 | $27.63 | $13.20 | $44.83 | $85.00 | $70.03 | $56.00 |
| 0051 | Geotextile for subsurface drains (2026000000-E) | SY | 200 | $4.29 | $2.85 | $4.30 | $12.00 | $5.89 | $20.00 |
| 0052 | Subdrain coarse aggregate (2036000000-E) | CY | 33.60 | $94.34 | $84.47 | $104.47 | $209.00 | $159.94 | $150.00 |
| 0053 | 6" perforated subdrain pipe (2044000000-E) | LF | 200 | $6.22 | $24.36 | $17.34 | $45.00 | $18.93 | $31.00 |
| 0054 | Subdrain pipe outlet (2070000000-N) | EACH | 1 | $547.24 | $198.50 | $387.38 | $3,499.50 | $605.78 | $600.00 |
| 0055 | 6" outlet pipe (2077000000-E) | LF | 6 | $64.21 | $47.96 | $57.80 | $104.00 | $66.79 | $125.00 |
| 0056 | Shoulder drain (2099000000-E) | LF | 2,150 | $15.12 | $24.36 | $27.08 | $24.30 | $24.75 | $26.83 |
| 0057 | 4" shoulder drain pipe (2110000000-E) | LF | 2,150 | $8.13 | $21.44 | $2.88 | $2.58 | $2.63 | $2.85 |
| 0058 | 4" outlet pipe for shoulder drains (2121000000-E) | LF | 170 | $22.30 | $22.11 | $33.73 | $30.26 | $30.83 | $33.42 |
| 0059 | Concrete pad for shoulder drain pipe outlet (2132000000-N) | EACH | 1 | $528.42 | $508.09 | $632.73 | $567.71 | $578.27 | $626.88 |
| 0060 | Temporary steel plate covers for masonry drainage structure (2190000000-N) | EACH | 3 | $1,939.89 | $9,947.48 | $1,288.92 | $2,008.50 | $1,606.17 | $3,100.00 |
| 0061 | Endwalls (2209000000-E) | CY | 1.40 | $2,730.38 | $2,402.94 | $3,397.01 | $5,191.50 | $8,418.52 | $3,000.00 |
| 0062 | Flowable fill (2275000000-E) | CY | 36 | $769.13 | $402.06 | $294.75 | $352.50 | $856.31 | $225.00 |
| 0063 | Masonry drainage structures (2286000000-N) | EACH | 42 | $5,086.71 | $4,499.33 | $5,741.44 | $8,648.00 | $13,336 | $3,000.00 |
| 0064 | Masonry drainage structures (2308000000-E) | LF | 22.10 | $704.53 | $719.77 | $640.06 | $1,027.50 | $1,272.64 | $700.00 |
| 0065 | Frame with two grates, STD 840.20 (2364200000-N) | EACH | 14 | $2,864.77 | $1,137.82 | $1,456.16 | $1,217.50 | $1,442.14 | $1,500.00 |
| 0066 | Frame with two grates, STD 840.22 (2365000000-N) | EACH | 15 | $2,850.53 | $1,137.82 | $1,554.35 | $1,217.50 | $1,442.15 | $1,500.00 |
| 0067 | Frame with two grates, STD 840.29 (2367000000-N) | EACH | 3 | $1,311.13 | $1,137.82 | $1,738.93 | $1,217.50 | $1,442.15 | $1,500.00 |
| 0068 | Frame with cover, STD 840.54 (2396000000-N) | EACH | 1 | $1,176.48 | $963.99 | $1,211.90 | $910.50 | $1,201.88 | $1,500.00 |
| 0069 | Steel frame with two grates, STD 840.37 (2407000000-N) | EACH | 7 | $3,299.79 | $3,328.28 | $2,169.60 | $4,312.00 | $4,470.19 | $3,500.00 |
| 0070 | Shoulder berm gutter (2556000000-E) | LF | 570 | $50.00 | $40.88 | $57.62 | $56.35 | $80.25 | $50.00 |
| 0071 | Precast reinforced concrete barrier, single faced (2724000000-E) | LF | 207 | $124.66 | $103.35 | $130.79 | $96.34 | $172.00 | $120.00 |
| 0072 | Steel beam guardrail (3030000000-E) | LF | 737.50 | $23.00 | $28.13 | $26.45 | $23.00 | $24.40 | $25.00 |
| 0073 | Additional guardrail posts (3150000000-N) | EACH | 10 | $1.00 | $1.23 | $1.15 | $1.00 | $1.06 | $1.00 |
| 0074 | Guardrail end units, type cat-1 (3210000000-N) | EACH | 1 | $950.00 | $1,161.99 | $1,092.50 | $950.00 | $1,007.86 | $950.00 |
| 0075 | Guardrail end units, type TL-3 (3287000000-N) | EACH | 5 | $3,200.00 | $3,914.03 | $3,680.00 | $3,200.00 | $3,394.88 | $3,200.00 |
| 0076 | Guardrail anchor units, type B-77 (3317000000-N) | EACH | 6 | $2,600.00 | $3,180.16 | $3,105.00 | $2,600.00 | $2,758.34 | $2,600.00 |
| 0077 | Remove & reset existing guardrail (3345000000-E) | LF | 222 | $10.00 | $12.23 | $11.50 | $10.00 | $10.61 | $10.00 |
| 0078 | Remove existing guardrail (3360000000-E) | LF | 870 | $1.00 | $1.23 | $1.15 | $1.00 | $1.06 | $1.00 |
| 0079 | Remove existing guiderail (3365000000-E) | LF | 3,100 | $2.00 | $2.44 | $2.30 | $2.00 | $2.12 | $2.00 |
| 0080 | Double faced cable guiderail (3389400000-E) | LF | 3,050 | $14.00 | $17.12 | $16.10 | $14.00 | $14.85 | $14.00 |
| 0081 | Additional guiderail posts (3389500000-N) | EACH | 10 | $1.00 | $91.74 | $86.25 | $75.00 | $79.57 | $75.00 |
| 0082 | Cable guiderail anchor units (3389600000-N) | EACH | 4 | $2,500.00 | $3,057.84 | $2,875.00 | $2,500.00 | $2,652.25 | $2,500.00 |
| 0083 | Woven wire fence reset (3566000000-E) | LF | 60 | $20.00 | $24.46 | $23.00 | $75.00 | $21.22 | $20.00 |
| 0084 | Rip rap, class I (3628000000-E) | TON | 90 | $82.27 | $83.52 | $79.09 | $112.50 | $158.45 | $60.00 |
| 0085 | Geotextile for drainage (3656000000-E) | SY | 3,770 | $5.28 | $4.19 | $4.11 | $5.50 | $4.79 | $5.00 |
| 0086 | Reinforced concrete sign foundations (4048000000-E) | CY | 1.82 | $850.00 | $1,049.86 | $977.50 | $850.00 | $2,562.96 | $850.00 |
| 0087 | Plain concrete sign foundations (4054000000-E) | CY | 0.30 | $10.00 | $12.35 | $11.50 | $10.00 | $6,137.83 | $10.00 |
| 0088 | Supports, breakaway steel beam (4060000000-E) | LB | 1,508.50 | $9.00 | $11.12 | $10.35 | $9.00 | $6.37 | $9.00 |
| 0089 | Supports, simple steel beam (4066000000-E) | LB | 304.27 | $14.00 | $17.29 | $16.10 | $14.00 | $6.37 | $14.00 |
| 0090 | Supports, 3-LB steel U-channel (4072000000-E) | LF | 129 | $8.00 | $9.88 | $9.20 | $8.00 | $9.55 | $8.00 |
| 0091 | Sign erection, type D (4096000000-N) | EACH | 2 | $250.00 | $308.79 | $287.50 | $250.00 | $212.18 | $250.00 |
| 0092 | Sign erection, type E (4102000000-N) | EACH | 4 | $75.00 | $92.64 | $86.25 | $75.00 | $164.44 | $75.00 |
| 0093 | Sign erection, type *** (GRD MTD) - (A) (4110000000-N) | EACH | 1 | $1,000.00 | $1,235.12 | $1,150.00 | $1,000.00 | $1,591.35 | $1,000.00 |
| 0094 | Sign erection, type *** (GRD MTD) - (B) (4110000000-N) | EACH | 3 | $1,000.00 | $1,235.13 | $1,150.00 | $1,000.00 | $1,591.35 | $1,000.00 |
| 0095 | Disposal of sign system, steel beam (4152000000-N) | EACH | 2 | $500.00 | $617.56 | $575.00 | $500.00 | $795.68 | $500.00 |
| 0096 | Disposal of sign system, U-channel (4155000000-N) | EACH | 3 | $2.00 | $2.47 | $2.30 | $2.00 | $26.52 | $2.00 |
| 0097 | Disposal of sign system, wood (4158000000-N) | EACH | 2 | $2.00 | $2.47 | $2.30 | $2.00 | $26.53 | $2.00 |
| 0098 | Work zone signs (stationary) (4400000000-E) | SF | 602 | $7.50 | $6.42 | $8.63 | $6.10 | $6.38 | $7.50 |
| 0099 | High visibility stationary signs (4402000000-E) | SF | 304 | $12.00 | $8.25 | $13.80 | $8.75 | $9.15 | $12.00 |
| 0100 | Work zone signs (portable) (4405000000-E) | SF | 96 | $28.91 | $11.01 | $24.95 | $8.45 | $8.83 | $9.00 |
| 0101 | High visibility portable signs (4407000000-E) | SF | 176 | $42.72 | $11.92 | $24.95 | $9.65 | $10.09 | $9.00 |
| 0102 | Work zone signs (barricade mounted) (4410000000-E) | SF | 112 | $7.00 | $9.78 | $8.05 | $8.95 | $9.36 | $7.00 |
| 0103 | Flashing arrow board (4415000000-N) | EACH | 7 | $3,300.00 | $2,385.12 | $1,539.21 | $2,100.00 | $2,195.55 | $2,500.00 |
| 0104 | Portable changeable message sign (4420000000-N) | EACH | 5 | $12,365 | $11,131 | $9,825.39 | $8,478.26 | $8,154.90 | $11,000 |
| 0105 | Work zone digital speed limit signs (4423000000-N) | EACH | 8 | $5,020.65 | $3,791.71 | $13,340 | $3,500.00 | $3,659.25 | $4,600.00 |
| 0106 | Work zone presence lighting (4424000000-N) | EACH | 28 | $3,830.00 | $3,057.84 | $7,935.00 | $2,200.00 | $2,300.10 | $6,900.00 |
| 0107 | Drums (4430000000-N) | EACH | 40 | $72.85 | $66.30 | $90.00 | $45.00 | $47.05 | $46.00 |
| 0108 | High visibility drums (4432000000-N) | EACH | 100 | $160.15 | $66.30 | $112.15 | $56.00 | $58.55 | $68.00 |
| 0109 | Sequential flashing warning lights (4434000000-N) | EACH | 30 | $228.40 | $165.12 | $182.54 | $135.00 | $141.14 | $95.00 |
| 0110 | Barricades (type III) (4445000000-E) | LF | 72 | $20.00 | $24.46 | $23.00 | $25.00 | $26.14 | $20.00 |
| 0111 | Flagger (4455000000-N) | DAY | 10 | $1,048.75 | $375.89 | $449.06 | $1,450.00 | $1,515.98 | $354.29 |
| 0112 | Temporary crash cushions (4465000000-N) | EACH | 3 | $10,975 | $13,760 | $9,487.50 | $11,608 | $8,801.40 | $11,250 |
| 0113 | TMA (4480000000-N) | EACH | 2 | $11,850 | $34,859 | $14,417 | $33,000 | $20,701 | $46,800 |
| 0114 | Portable concrete barrier (4485000000-E) | LF | 4,950 | $43.20 | $49.31 | $46.37 | $41.60 | $72.50 | $40.32 |
| 0115 | Portable concrete barrier (anchored) (4490000000-E) | LF | 2,250 | $59.70 | $71.11 | $66.86 | $59.99 | $62.03 | $58.14 |
| 0116 | Law enforcement (4510000000-N) | HR | 500 | $91.75 | $95.94 | $115.00 | $100.00 | $83.64 | $65.00 |
| 0117 | Temporary glare screen (4570000000-E) | LF | 3,325 | $23.45 | $24.32 | $22.87 | $20.52 | $21.22 | $19.89 |
| 0118 | Generic traffic control item (EA) - connected lane closure system (4600000000-N) | EACH | 1 | $3,732.83 | $2,935.53 | $1,150.00 | $1,800.00 | $1,881.90 | $1,000.00 |
| 0119 | Temporary raised pavement markers (4650000000-N) | EACH | 260 | $12.50 | $15.29 | $5.75 | $12.50 | $13.26 | $30.00 |
| 0120 | Thermoplastic pavement marking lines (4", 90 mils) (4685000000-E) | LF | 1,648 | $1.65 | $2.02 | $0.23 | $1.65 | $1.75 | $7.50 |
| 0121 | Thermoplastic pavement marking symbol (90 mils) (4725000000-E) | EACH | 10 | $250.00 | $305.80 | $287.50 | $250.00 | $265.23 | $600.00 |
| 0122 | Cold appl plastic sym type ** - (IV) (4805000000-N) | EACH | 5 | $300.00 | $366.94 | $230.00 | $300.00 | $318.27 | $2,850.00 |
| 0123 | Paint pavement marking lines (6") (4815000000-E) | LF | 7,425 | $1.00 | $1.23 | $0.35 | $1.00 | $1.06 | $1.25 |
| 0124 | Polyurea lines (**", *** mils) - (12", 30) (4846000000-E) | LF | 430 | $3.50 | $4.28 | $17.25 | $3.50 | $3.71 | $20.00 |
| 0125 | Polyurea lines (**", *** mils) - (6", 30) (4846000000-E) | LF | 27,355 | $1.50 | $1.83 | $5.75 | $1.50 | $1.59 | $1.55 |
| 0126 | Removal of pavement marking lines (6") (4855000000-E) | LF | 7,000 | $1.80 | $0.98 | $2.30 | $0.80 | $0.85 | $1.50 |
| 0127 | Generic pavement marking item (LF) - integrated mutipolymer pavement marking lines, (6", 90 mils) (4890000000-E) | LF | 27,399 | $1.85 | $2.27 | $11.50 | $1.85 | $1.96 | $1.55 |
| 0128 | Generic pavement marking item (EA) - polycarbonate H-shaped markers (4895000000-N) | EACH | 132 | $45.00 | $55.03 | $80.50 | $45.00 | $47.74 | $175.00 |
| 0129 | Permanent raised pavement markers (4900000000-N) | EACH | 35 | $25.00 | $30.57 | $80.50 | $25.00 | $26.52 | $135.00 |
| 0130 | Portable lighting (5255000000-N) | LS | 1 | $150,000 | $38,703 | $100,585 | $60,000 | $32,393 | $250,000 |
| 0131 | Temporary silt fence (6000000000-E) | LF | 1,860 | $2.00 | $3.07 | $2.30 | $2.50 | $3.09 | $3.15 |
| 0132 | Stone for erosion control, class A (6006000000-E) | TON | 455 | $87.55 | $79.52 | $75.38 | $101.50 | $95.20 | $65.00 |
| 0133 | Stone for erosion control, class B (6009000000-E) | TON | 685 | $86.40 | $79.52 | $75.95 | $99.50 | $95.16 | $65.00 |
| 0134 | Sediment control stone (6012000000-E) | TON | 1,550 | $0.01 | $60.44 | $70.81 | $87.50 | $84.64 | $60.00 |
| 0135 | Temporary mulching (6015000000-E) | ACRE | 6 | $1,800.00 | $1,536.41 | $2,070.00 | $1,250.00 | $1,751.00 | $1,800.00 |
| 0136 | Seed for temporary seeding (6018000000-E) | LB | 400 | $1.00 | $1.23 | $1.15 | $1.00 | $2.06 | $2.00 |
| 0137 | Fertilizer for temporary seeding (6021000000-E) | TON | 3 | $1.00 | $1,597.87 | $1,150.00 | $1,300.00 | $978.50 | $1,000.00 |
| 0138 | Temporary slope drains (6024000000-E) | LF | 360 | $22.85 | $22.97 | $15.39 | $50.50 | $30.50 | $23.25 |
| 0139 | Safety fence (6029000000-E) | LF | 960 | $2.00 | $2.46 | $2.30 | $2.00 | $3.09 | $3.15 |
| 0140 | Silt excavation (6030000000-E) | CY | 3,490 | $0.01 | $14.76 | $0.01 | $98.50 | $34.87 | $20.00 |
| 0141 | Matting for erosion control (6036000000-E) | SY | 12,000 | $1.35 | $1.96 | $1.55 | $1.60 | $1.70 | $1.70 |
| 0142 | Coir fiber mat (6037000000-E) | SY | 100 | $30.00 | $6.63 | $23.00 | $5.40 | $6.18 | $6.25 |
| 0143 | 1/4" hardware cloth (6042000000-E) | LF | 1,110 | $4.00 | $4.92 | $4.60 | $9.00 | $5.15 | $5.25 |
| 0144 | Low permeability geotextile (6043000000-E) | SY | 100 | $13.50 | $5.99 | $4.71 | $4.08 | $6.18 | $6.25 |
| 0145 | Floating turbidity curtain (6048000000-E) | SY | 735 | $0.01 | $35.34 | $128.42 | $40.00 | $66.95 | $68.00 |
| 0146 | Special stilling basins (6070000000-N) | EACH | 36 | $9.35 | $14.80 | $1,573.81 | $1,063.00 | $937.50 | $300.00 |
| 0147 | Flocculant (6071002000-E) | LB | 400 | $1.00 | $1.23 | $1.15 | $1.00 | $5.15 | $5.25 |
| 0148 | Wattle (6071010000-E) | LF | 560 | $8.00 | $8.60 | $9.20 | $7.00 | $9.27 | $9.50 |
| 0149 | Wattle barrier (6071013000-E) | LF | 800 | $8.00 | $8.60 | $9.20 | $7.00 | $12.36 | $12.50 |
| 0150 | Coir fiber baffle (6071030000-E) | LF | 390 | $10.00 | $8.60 | $11.50 | $7.00 | $8.24 | $8.50 |
| 0151 | **" skimmer - (2") (6071050000-E) | EACH | 1 | $1,575.85 | $1,905.19 | $1,596.51 | $2,993.50 | $1,339.00 | $1,000.00 |
| 0152 | **" skimmer - (2-1/2") (6071050000-E) | EACH | 1 | $1,815.00 | $2,152.51 | $1,781.08 | $3,350.00 | $1,596.50 | $1,200.00 |
| 0153 | Seeding and mulching (6084000000-E) | ACRE | 5.40 | $2,700.00 | $3,072.84 | $3,105.00 | $2,500.00 | $2,884.00 | $2,900.00 |
| 0154 | Mowing (6087000000-E) | ACRE | 2.70 | $100.00 | $122.92 | $115.00 | $100.00 | $257.50 | $260.00 |
| 0155 | Seed for repair seeding (6090000000-E) | LB | 100 | $5.00 | $3.07 | $5.75 | $2.50 | $4.64 | $4.75 |
| 0156 | Fertilizer for repair seeding (6093000000-E) | TON | 0.25 | $1,000.00 | $1,229.09 | $1,150.00 | $1,000.00 | $1,442.00 | $1,450.00 |
| 0157 | Seed for supplemental seeding (6096000000-E) | LB | 150 | $4.00 | $3.69 | $4.60 | $3.00 | $4.64 | $4.75 |
| 0158 | Fertilizer topdressing (6108000000-E) | TON | 4 | $500.00 | $2,212.44 | $575.00 | $1,800.00 | $978.50 | $1,000.00 |
| 0159 | Impervious dike (6111000000-E) | LF | 300 | $1.05 | $160.08 | $48.73 | $127.00 | $80.98 | $100.00 |
| 0160 | Specialized hand mowing (6114500000-N) | MHR | 10 | $200.00 | $61.46 | $230.00 | $50.00 | $180.25 | $185.00 |
| 0161 | Manual litter removal (6114800000-N) | MHR | 2 | $316.00 | $149.89 | $247.01 | $102.52 | $180.25 | $185.00 |
| 0162 | Litter disposal (6114900000-E) | TON | 1 | $502.00 | $3,597.46 | $2,182.82 | $2,167.00 | $206.00 | $200.00 |
| 0163 | Response for erosion control (6117000000-N) | EACH | 75 | $1.00 | $1.23 | $1.15 | $1.00 | $180.25 | $185.00 |
| 0164 | Concrete washout structure (6117500000-N) | EACH | 2 | $1,000.00 | $987.69 | $3,332.93 | $5,175.50 | $1,696.48 | $773.21 |
| 0165 | Generic erosion control item (EA) - fabric insert inlet protection cleanout (6132000000-N) | EACH | 81 | $56.00 | $157.49 | $187.12 | $134.00 | $257.50 | $199.59 |
| 0166 | Generic erosion control item (EA) - fabric insert inlet protection, type 1 (6132000000-N) | EACH | 27 | $267.00 | $456.14 | $310.17 | $571.50 | $257.50 | $201.63 |
| 0167 | Generic erosion control item (EA) - prefabricated concrete washout (6132000000-N) | EACH | 9 | $650.00 | $2,222.25 | $310.17 | $5,074.50 | $515.00 | $444.26 |
| 0168 | CM&R temp access *********** - (32+28.00 -L-) (8017000000-N) | LS | 1 | $529,000 | $534,720 | $1,248,000 | $858,071 | $968,731 | $1,000,000 |
| 0169 | Remv exist STR ****** BRG (402) - (32+28.00 -L-) (8035000000-N) | LS | 1 | $1,066,501 | $1,500,000 | $1,151,000 | $515,886 | $1,050,808 | $1,000,000 |
| 0170 | Asbestos assessment (8065000000-N) | LS | 1 | $1,586.01 | $1,438.99 | $1,380.00 | $1,200.00 | $4,302.08 | $7,000.00 |
| 0171 | **'-**" dia drilld piers - (5'-0") (8108000000-E) | LF | 728.05 | $1,715.01 | $1,569.31 | $1,807.32 | $1,613.00 | $1,892.07 | $2,600.00 |
| 0172 | Perm STL casing for ** pier - (5'-0") (8111000000-E) | LF | 70.89 | $576.81 | $931.66 | $697.67 | $680.00 | $800.30 | $1,000.00 |
| 0173 | Sid inspections (8113000000-N) | EACH | 18 | $1.00 | $1,814.92 | $1,162.79 | $1,000.00 | $5,239.52 | $500.00 |
| 0174 | CSL testing (8115000000-N) | EACH | 18 | $1.00 | $1,678.82 | $4,069.77 | $9,999.50 | $6,278.87 | $7,500.00 |
| 0175 | Uncl STR excav sta ***** - (32+28.00 -L-) (8121000000-N) | LS | 1 | $32,100 | $52,036 | $51,578 | $58,500 | $54,650 | $50,000 |
| 0176 | Reinforced concrete deck slab (8147000000-E) | SF | 41,660 | $41.63 | $39.17 | $40.60 | $54.00 | $62.05 | $53.00 |
| 0177 | Grooving bridge floors (8161000000-E) | SF | 38,620 | $1.91 | $0.39 | $0.58 | $0.35 | $2.20 | $0.60 |
| 0178 | Class A concrete (bridge) (8182000000-E) | CY | 727.70 | $963.55 | $1,334.40 | $1,599.98 | $1,576.00 | $2,145.40 | $1,500.00 |
| 0179 | BRG appr slab *********** - (32+28.00 -L-) (8210000000-N) | LS | 1 | $90,000 | $92,084 | $96,540 | $90,803 | $165,091 | $90,000 |
| 0180 | Reinforcing steel (bridge) (8217000000-E) | LB | 161,923 | $1.67 | $1.36 | $1.34 | $1.73 | $1.71 | $2.00 |
| 0181 | Spiral column reinforcing steel (bridge) (8238000000-E) | LB | 41,934 | $3.65 | $2.05 | $2.00 | $2.55 | $2.62 | $2.00 |
| 0182 | Fib **" prestr conc girdr - (63") (8278000000-E) | LF | 4,851 | $502.17 | $444.57 | $469.57 | $579.00 | $577.25 | $500.00 |
| 0183 | Pile DRV equip setup ** steel piles - (HP 12 X 53) (8328200000-E) | EACH | 22 | $882.64 | $1,073.08 | $467.37 | $753.00 | $3,912.21 | $800.00 |
| 0184 | HP 12 X 53 steel piles (8364000000-E) | LF | 825 | $49.32 | $76.00 | $84.78 | $154.00 | $41.50 | $55.00 |
| 0185 | Concrete barrier rail (8503000000-E) | LF | 1,665.78 | $130.82 | $150.78 | $141.30 | $141.00 | $145.43 | $130.00 |
| 0186 | Rip rap class II (2'-0" thick) (8608000000-E) | TON | 465 | $84.55 | $0.01 | $70.92 | $111.00 | $66.70 | $0.01 |
| 0187 | Geotextile for drainage (8622000000-E) | SY | 515 | $5.08 | $8.82 | $3.48 | $15.50 | $4.93 | $5.00 |
| 0188 | Elastomeric bearings (8657000000-N) | LS | 1 | $23,125 | $74,797 | $116,453 | $128,000 | $272,631 | $25,000 |
| 0189 | Expansion joint seals (8706000000-N) | LS | 1 | $156,600 | $140,921 | $163,657 | $206,944 | $211,636 | $140,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NCDOT's tabulation for this contract. NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
Every contract let that day: NCDOT letting of November 18, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.