Low bidders on NCDOT contracts carried a median of $3,000.00 per EACH for this item, over the 24 months to 20 OCT 2026, across 12 low bids. Half of all 71 bids fell between $2,800.00 and $3,205.00.
- Owner
- North Carolina DOT
- Item
- 3389600000-N
- Unit
- EACH
- Data through
- 20 OCT 2026
NCDOT prints this item as “CBL GUIDERAIL ANCH UNIT”.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2013 | 3 | 3 | $1,540.00 | 22 | $1,590.58 |
| 2014 | 6 | 6 | $1,525.00 | 36 | $1,674.26 |
| 2015 | 5 | 5 | $1,525.00 | 36 | $1,620.00 |
| 2016 | 3 | 3 | $1,940.00 | 11 | $1,850.00 |
| 2017 | 4 | 4 | $1,625.00 | 12 | $1,667.50 |
| 2018 | 4 | 4 | $1,795.62 | 15 | $1,700.00 |
| 2019 | 3 | 3 | $1,671.86 | 18 | $1,600.00 |
| 2021 | 8 | 8 | $2,150.00 | 41 | $2,050.00 |
| 2022 | 2 | 2 | $3,050.00 | 8 | $3,325.00 |
| 2023 | 5 | 5 | $2,500.00 | 30 | $2,670.18 |
| 2024 | 3 | 3 | $2,800.00 | 16 | $3,100.00 |
| 2025 | 5 | 5 | $2,500.00 | 37 | $2,875.00 |
| 2026 | 6 | 6 | $3,155.00 | 29 | $3,000.00 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 3 | $3,200.00 |
| 2 to 3 | 3 | $3,210.00 |
| 4 to 4 | 3 | $3,000.00 |
| 4 to 46 | 3 | $2,800.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Barnhill Contracting Company | 21 | 16 (76%) |
| S T Wooten Corporation | 19 | 16 (84%) |
| Blythe Construction Inc | 16 | 12 (75%) |
| Smith-Rowe, LLC | 12 | 11 (92%) |
| FSC II LLC DBA Fred Smith Company | 8 | 8 (100%) |
| C. M. Lindsay & Sons, Inc. | 7 | 7 (100%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 15 SEP 2026 | C204349 | Wake, Durham | 2 | $3,250.00 | $3,250.00 | 4 | Blythe Construction Inc | NCDOT |
| 18 AUG 2026 | C205205 | Robeson | 4 | $3,100.00 | $3,050.00 | 2 | Bmco Construction, Inc. | NCDOT |
| 18 AUG 2026 | C205070 | Rutherford | 4 | $3,000.00 | $3,000.00 | 9 | United Infrastructure Group Inc | NCDOT |
| 16 JUN 2026 | C205186 | Rockingham | 3 | $3,210.00 | $3,000.00 | 6 | W C English Incorporated | NCDOT |
| 19 MAY 2026 | C205187 | Cumberland | 4 | $3,000.00 | $3,000.00 | 4 | Highland Paving Co LLC | NCDOT |
| 19 MAY 2026 | C204733 | Yadkin | 2 | $3,556.59 | $2,800.00 | 4 | Blythe Construction Inc | NCDOT |
| 18 NOV 2025 | C205044 | Surry, Yadkin | 4 | $2,500.00 | $2,576.12 | 6 | Smith-Rowe, LLC | NCDOT |
| 21 OCT 2025 | C205116 | Rockingham | 3 | $2,500.00 | $2,562.50 | 4 | Smith-Rowe, LLC | NCDOT |
| 21 OCT 2025 | C205093 | Davie | 2 | $2,810.00 | $2,512.63 | 10 | Branch Civil Inc | NCDOT |
| 15 JUL 2025 | C205072 | New Hanover, Pender | 46 | $2,500.00 | $3,800.00 | 7 | S T Wooten Corporation | NCDOT |
| 18 FEB 2025 | C204979 | Davie | 1 | $3,200.00 | $3,200.00 | 10 | Smith-Rowe, LLC | NCDOT |
| 19 NOV 2024 | C204949 | Moore | 6 | $2,800.00 | $2,800.00 | 5 | S T Wooten Corporation | NCDOT |
| 20 AUG 2024 | C204864 | Rockingham | 2 | $3,100.00 | $3,100.00 | 7 | Smith-Rowe, LLC | NCDOT |
| 16 APR 2024 | C204208 | Surry | 3 | $2,800.00 | $2,800.00 | 4 | Smith-Rowe, LLC | NCDOT |
| 18 JUL 2023 | C204851 | Cleveland | 28 | $3,300.00 | $2,845.18 | 4 | Ames Construction Inc | NCDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.
How these prices were read
NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the NCDOT letting of 20 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way