Cable guiderail anchor units, NCDOT 3389600000-N

Low bidders on NCDOT contracts carried a median of $3,000.00 per EACH for this item, over the 24 months to 20 OCT 2026, across 12 low bids. Half of all 71 bids fell between $2,800.00 and $3,205.00.

Owner
North Carolina DOT
Item
3389600000-N
Unit
EACH
Data through
20 OCT 2026

NCDOT prints this item as “CBL GUIDERAIL ANCH UNIT”.

$3,000.00Low bidder's median, per EACH
$3,000.00Median of all bids, per EACH
12Contracts in the window

By year of letting

Cable guiderail anchor units, NCDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
201333$1,540.0022$1,590.58
201466$1,525.0036$1,674.26
201555$1,525.0036$1,620.00
201633$1,940.0011$1,850.00
201744$1,625.0012$1,667.50
201844$1,795.6215$1,700.00
201933$1,671.8618$1,600.00
202188$2,150.0041$2,050.00
202222$3,050.008$3,325.00
202355$2,500.0030$2,670.18
202433$2,800.0016$3,100.00
202555$2,500.0037$2,875.00
202666$3,155.0029$3,000.00

Bid prices as published, not adjusted for inflation.

By quantity

Quantity (EACH)Low bidsLow-bid median
1 to 23$3,200.00
2 to 33$3,210.00
4 to 43$3,000.00
4 to 463$2,800.00
Cable guiderail anchor units, NCDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

Cable guiderail anchor units, NCDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
15 SEP 2026C204349Wake, Durham2$3,250.00$3,250.004Blythe Construction IncNCDOT
18 AUG 2026C205205Robeson4$3,100.00$3,050.002Bmco Construction, Inc.NCDOT
18 AUG 2026C205070Rutherford4$3,000.00$3,000.009United Infrastructure Group IncNCDOT
16 JUN 2026C205186Rockingham3$3,210.00$3,000.006W C English IncorporatedNCDOT
19 MAY 2026C205187Cumberland4$3,000.00$3,000.004Highland Paving Co LLCNCDOT
19 MAY 2026C204733Yadkin2$3,556.59$2,800.004Blythe Construction IncNCDOT
18 NOV 2025C205044Surry, Yadkin4$2,500.00$2,576.126Smith-Rowe, LLCNCDOT
21 OCT 2025C205116Rockingham3$2,500.00$2,562.504Smith-Rowe, LLCNCDOT
21 OCT 2025C205093Davie2$2,810.00$2,512.6310Branch Civil IncNCDOT
15 JUL 2025C205072New Hanover, Pender46$2,500.00$3,800.007S T Wooten CorporationNCDOT
18 FEB 2025C204979Davie1$3,200.00$3,200.0010Smith-Rowe, LLCNCDOT
19 NOV 2024C204949Moore6$2,800.00$2,800.005S T Wooten CorporationNCDOT
20 AUG 2024C204864Rockingham2$3,100.00$3,100.007Smith-Rowe, LLCNCDOT
16 APR 2024C204208Surry3$2,800.00$2,800.004Smith-Rowe, LLCNCDOT
18 JUL 2023C204851Cleveland28$3,300.00$2,845.184Ames Construction IncNCDOT
Latest NCDOT contracts carrying Cable guiderail anchor units

Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.

How these prices were read

NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the NCDOT letting of 20 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy