NCDOT contract C205116 bid tabulation
GRADING, DRAINAGE, PAVING, AND STRUCTURES. BRIDGE #780183 OVER US-29 BYP ON US-29 BUS. Let by North Carolina DOT on October 21, 2025, Rockingham. 4 bids received; low bid $4,612,861 by Smith-Rowe, LLC.
- Owner
- North Carolina DOT
- Letting
- 21 OCT 2025
- Pay items
- 133
- Data through
- 20 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Smith-Rowe, LLC | $4,612,861 | Low |
| 2 | W C English Incorporated | $4,880,307 | +6.0% |
| 3 | Sanford Contractors Inc | $5,162,000 | +12% |
| 4 | Haymes Brothers, Inc. | $5,352,516 | +16% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Smith-Rowe, LLC | 2. W C English Incorporated | 3. Sanford Contractors Inc | 4. Haymes Brothers, Inc. |
|---|---|---|---|---|---|---|---|
| 0001 | Mobilization (0000100000-N) | LS | 1 | $230,600 | $244,000 | $258,100 | $250,000 |
| 0002 | Construction surveying (0000400000-N) | LS | 1 | $18,500 | $81,000 | $93,000 | $60,000 |
| 0003 | Undercut excavation (0036000000-E) | CY | 650 | $0.01 | $27.00 | $19.39 | $10.00 |
| 0004 | Supplementary clearing & grubbing (0050000000-E) | ACRE | 1 | $1.00 | $0.01 | $0.01 | $450.00 |
| 0005 | Grading (0063000000-N) | LS | 1 | $654,816 | $352,000 | $620,000 | $600,000 |
| 0006 | Borrow excavation (0106000000-E) | CY | 8,000 | $0.01 | $15.00 | $0.01 | $1.00 |
| 0007 | Drainage ditch excavation (0134000000-E) | CY | 5 | $75.68 | $76.00 | $22.08 | $50.00 |
| 0008 | Select granular material (0195000000-E) | CY | 600 | $0.01 | $65.00 | $56.34 | $22.00 |
| 0009 | Geotextile for soil stabilization (0196000000-E) | SY | 600 | $3.50 | $5.00 | $2.11 | $6.00 |
| 0010 | Temporary shoring (0199000000-E) | SF | 880 | $1.00 | $82.00 | $81.40 | $1.00 |
| 0011 | Rock plating (0223000000-E) | SY | 1,140 | $68.55 | $66.00 | $111.56 | $80.00 |
| 0012 | Generic grading item (LS) - type 2 bridge approach fill, sta 20+96.07 -L- (0248000000-N) | LS | 1 | $32,975 | $20,000 | $35,000 | $62,000 |
| 0013 | Foundation conditioning material, minor structures (0318000000-E) | TON | 70 | $40.50 | $48.00 | $39.24 | $68.00 |
| 0014 | FND condit geotextile (4A) (0321000000-E) | SY | 220 | $5.35 | $6.50 | $2.11 | $5.00 |
| 0015 | 18" RC pipe culverts, class III (0372000000-E) | LF | 484 | $107.58 | $119.00 | $99.58 | $110.00 |
| 0016 | 15" RC pipe culverts, class IV (0448200000-E) | LF | 80 | $107.21 | $92.00 | $89.59 | $100.00 |
| 0017 | 18" CS pipe culverts, 0.064" thick inlet used based on county (0588000000-E) | LF | 96 | $82.54 | $132.00 | $80.08 | $100.00 |
| 0018 | **" CS elbow *****" thick - (18", 0.064") (0636000000-E) | EACH | 4 | $946.24 | $791.00 | $274.61 | $450.00 |
| 0019 | Pipe removal (0995000000-E) | LF | 37 | $26.60 | $13.50 | $30.87 | $50.00 |
| 0020 | Shallow undercut (1099500000-E) | CY | 100 | $26.54 | $29.00 | $19.18 | $9.00 |
| 0021 | Class IV subgrade stabilization (1099700000-E) | TON | 200 | $36.40 | $38.00 | $35.08 | $40.00 |
| 0022 | Geotextile for subgrade stabilization (1112000000-E) | SY | 300 | $6.00 | $4.60 | $2.73 | $5.00 |
| 0023 | Mill asp PVMT *****" DTH - (1-1/2") (1297000000-E) | SY | 8,000 | $5.69 | $13.72 | $2.95 | $3.30 |
| 0024 | Incidental milling (1330000000-E) | SY | 400 | $21.85 | $39.32 | $8.95 | $9.90 |
| 0025 | Asphalt conc base course, type B25.0C (1491000000-E) | TON | 2,020 | $123.00 | $129.15 | $123.00 | $136.00 |
| 0026 | Asphalt conc intermediate course, type I19.0C (1503000000-E) | TON | 2,040 | $123.00 | $129.15 | $123.00 | $136.00 |
| 0027 | Asphalt conc surface course, type S9.5C (1523000000-E) | TON | 1,930 | $126.00 | $132.30 | $126.00 | $140.00 |
| 0028 | Asphalt binder for plant mix (1575000000-E) | TON | 305 | $750.00 | $787.50 | $750.00 | $825.00 |
| 0029 | Asphalt plant mix, pavement repair (1693000000-E) | TON | 50 | $341.47 | $803.25 | $400.00 | $100.00 |
| 0030 | Subdrain excavation (2022000000-E) | CY | 45 | $0.01 | $19.65 | $0.01 | $38.00 |
| 0031 | Subdrain fine aggregate (2033000000-E) | CY | 34 | $0.01 | $69.60 | $0.01 | $40.00 |
| 0032 | 4" perforated subdrain pipe (2043000000-E) | LF | 200 | $0.01 | $8.27 | $0.01 | $10.00 |
| 0033 | Subdrain pipe outlet (2070000000-N) | EACH | 1 | $133.00 | $1,673.87 | $0.01 | $150.00 |
| 0034 | 4" outlet pipe (2076000000-E) | LF | 6 | $61.85 | $57.06 | $0.01 | $25.00 |
| 0035 | Masonry drainage structures (2286000000-N) | EACH | 13 | $3,202.21 | $4,482.07 | $3,701.86 | $4,250.00 |
| 0036 | Masonry drainage structures (2308000000-E) | LF | 6.50 | $821.95 | $997.38 | $400.15 | $900.00 |
| 0037 | Frame with two grates, STD 840.20 (2364200000-N) | EACH | 5 | $1,219.54 | $1,362.11 | $1,073.64 | $1,500.00 |
| 0038 | Frame with two grates, STD 840.22 (2365000000-N) | EACH | 3 | $2,782.43 | $1,418.28 | $1,073.65 | $1,500.00 |
| 0039 | Frame with cover, STD 840.54 (2396000000-N) | EACH | 4 | $1,134.27 | $1,249.76 | $871.91 | $1,500.00 |
| 0040 | Steel frame with two grates, STD 840.37 (2407000000-N) | EACH | 1 | $3,380.58 | $1,755.33 | $3,616.37 | $1,800.00 |
| 0041 | Shoulder berm gutter (2556000000-E) | LF | 260 | $42.50 | $47.20 | $102.42 | $82.00 |
| 0042 | Precast reinforced concrete barrier, single faced (2724000000-E) | LF | 100 | $133.39 | $131.00 | $236.44 | $150.00 |
| 0043 | Generic paving item (LB) - flexible repair for existing pavement cracks and joints (2762000000-E) | LB | 13,020 | $5.07 | $4.73 | $3.90 | $1.50 |
| 0044 | Impact attenuator units, type TL-3 (3001000000-N) | EACH | 2 | $21,000 | $25,000 | $17,000 | $25,000 |
| 0045 | Steel beam guardrail (3030000000-E) | LF | 2,650 | $23.00 | $24.15 | $23.00 | $25.25 |
| 0046 | Additional guardrail posts (3150000000-N) | EACH | 10 | $1.00 | $1.05 | $1.00 | $1.10 |
| 0047 | Guardrail end units, type cat-1 (3210000000-N) | EACH | 1 | $900.00 | $945.00 | $900.00 | $990.00 |
| 0048 | Guardrail end units, type TL-3 (3287000000-N) | EACH | 2 | $3,200.00 | $3,360.00 | $3,200.00 | $3,520.00 |
| 0049 | Guardrail end units, type TL-2 (3288000000-N) | EACH | 5 | $3,100.00 | $3,255.00 | $3,100.00 | $3,420.00 |
| 0050 | Guardrail anchor units, type B-77 (3317000000-N) | EACH | 7 | $2,600.00 | $2,730.00 | $2,600.00 | $2,850.00 |
| 0051 | Remove existing guardrail (3360000000-E) | LF | 2,815 | $0.90 | $2.70 | $0.90 | $1.00 |
| 0052 | Remove existing guiderail (3365000000-E) | LF | 302 | $3.00 | $2.52 | $3.00 | $3.30 |
| 0053 | Cable guiderail (3389200000-E) | LF | 220 | $14.00 | $14.70 | $14.00 | $15.50 |
| 0054 | Cable guiderail anchor units (3389600000-N) | EACH | 3 | $2,500.00 | $2,625.00 | $2,500.00 | $2,750.00 |
| 0055 | Rip rap, class B (3649000000-E) | TON | 22 | $56.33 | $68.60 | $157.52 | $72.00 |
| 0056 | Geotextile for drainage (3656000000-E) | SY | 507 | $5.15 | $4.32 | $3.75 | $5.00 |
| 0057 | Contr furn, type ***sign - (D) (4025000000-E) | SF | 20 | $18.00 | $15.75 | $15.00 | $38.00 |
| 0058 | Contr furn, type ***sign - (E) (4025000000-E) | SF | 125 | $18.00 | $12.60 | $12.00 | $33.00 |
| 0059 | Contr furn, type ***sign - (F) (4025000000-E) | SF | 80 | $18.00 | $15.75 | $15.00 | $28.00 |
| 0060 | Supports, 3-LB steel U-channel (4072000000-E) | LF | 440 | $10.00 | $8.14 | $7.75 | $12.50 |
| 0061 | Sign erection, type D (4096000000-N) | EACH | 2 | $125.00 | $131.25 | $125.00 | $110.00 |
| 0062 | Sign erection, type E (4102000000-N) | EACH | 20 | $75.00 | $78.75 | $75.00 | $94.00 |
| 0063 | Sign erection, type F (4108000000-N) | EACH | 7 | $125.00 | $131.25 | $125.00 | $82.50 |
| 0064 | Disposal of sign system, U-channel (4155000000-N) | EACH | 25 | $2.00 | $5.25 | $5.00 | $38.00 |
| 0065 | Work zone signs (stationary) (4400000000-E) | SF | 997 | $12.00 | $7.35 | $7.00 | $8.80 |
| 0066 | Work zone signs (portable) (4405000000-E) | SF | 400 | $25.47 | $14.70 | $14.00 | $16.50 |
| 0067 | Work zone signs (barricade mounted) (4410000000-E) | SF | 135 | $9.00 | $7.35 | $7.00 | $9.25 |
| 0068 | Flashing arrow board (4415000000-N) | EACH | 4 | $3,035.00 | $1,714.06 | $1,800.00 | $1,500.00 |
| 0069 | Portable changeable message sign (4420000000-N) | EACH | 4 | $9,700.00 | $2,583.46 | $5,000.00 | $2,850.00 |
| 0070 | Work zone digital speed limit signs (4423000000-N) | EACH | 10 | $1.00 | $3,150.00 | $3,000.00 | $4,400.00 |
| 0071 | Drums (4430000000-N) | EACH | 219 | $74.95 | $67.78 | $43.00 | $50.00 |
| 0072 | Sequential flashing warning lights (4434000000-N) | EACH | 26 | $255.75 | $143.45 | $125.00 | $88.00 |
| 0073 | Barricades (type III) (4445000000-E) | LF | 108 | $25.00 | $21.00 | $20.00 | $28.50 |
| 0074 | Flagger (4455000000-N) | DAY | 21 | $1,577.71 | $507.65 | $450.00 | $2,000.00 |
| 0075 | Temporary crash cushions (4465000000-N) | EACH | 4 | $1.00 | $4,725.00 | $4,500.00 | $12,000 |
| 0076 | Remove & reset temporary crash cushion (4470000000-N) | EACH | 2 | $1.00 | $1,050.00 | $1,000.00 | $7,500.00 |
| 0077 | TMA (4480000000-N) | EACH | 2 | $8,305.00 | $2,171.47 | $8,100.01 | $10,000 |
| 0078 | Portable concrete barrier (4485000000-E) | LF | 850 | $49.95 | $37.80 | $36.00 | $50.00 |
| 0079 | Remove and reset portable concrete barrier (4500000000-E) | LF | 605 | $14.05 | $7.35 | $7.00 | $35.00 |
| 0080 | Generic pavement marking item (LF) - integrated multipolymer pavement marking lines, (24", 90 mils) (4890000000-E) | LF | 80 | $18.00 | $18.90 | $40.00 | $20.00 |
| 0081 | Generic pavement marking item (LF) - integrated multipolymer pavement marking lines, (4", 90 mils) (4890000000-E) | LF | 4,449 | $2.75 | $2.89 | $2.20 | $3.00 |
| 0082 | Generic pavement marking item (LF) - integrated multipolymer pavement marking lines, (6", 90 mils) (4890000000-E) | LF | 8,322 | $3.00 | $3.15 | $2.70 | $3.30 |
| 0083 | Generic pavement marking item (LF) - integrated multipolymer pavement marking lines, (8", 90 mils) (4890000000-E) | LF | 355 | $4.50 | $4.73 | $8.50 | $4.90 |
| 0084 | Generic pavement marking item (EA) - integrated multipolymer pavement marking symbols, (90 mils) (4895000000-N) | EACH | 6 | $200.00 | $210.00 | $355.00 | $220.00 |
| 0085 | Generic pavement marking item (EA) - polycarbonate H-shaped markers (4895000000-N) | EACH | 13 | $375.00 | $393.75 | $435.00 | $415.00 |
| 0086 | Permanent raised pavement markers (4900000000-N) | EACH | 2 | $25.00 | $26.25 | $100.00 | $27.00 |
| 0087 | Temporary silt fence (6000000000-E) | LF | 6,195 | $3.00 | $3.15 | $2.90 | $4.00 |
| 0088 | Stone for erosion control, class A (6006000000-E) | TON | 180 | $0.01 | $50.91 | $51.25 | $64.00 |
| 0089 | Stone for erosion control, class B (6009000000-E) | TON | 290 | $0.01 | $57.37 | $48.25 | $50.00 |
| 0090 | Sediment control stone (6012000000-E) | TON | 305 | $0.01 | $49.65 | $37.75 | $50.00 |
| 0091 | Temporary mulching (6015000000-E) | ACRE | 4.50 | $1,700.00 | $1,785.00 | $2,000.00 | $2,600.00 |
| 0092 | Seed for temporary seeding (6018000000-E) | LB | 300 | $1.00 | $1.05 | $1.00 | $2.20 |
| 0093 | Fertilizer for temporary seeding (6021000000-E) | TON | 1.50 | $100.00 | $105.00 | $300.00 | $1,100.00 |
| 0094 | Temporary slope drains (6024000000-E) | LF | 380 | $0.01 | $15.03 | $10.70 | $24.00 |
| 0095 | Safety fence (6029000000-E) | LF | 660 | $2.25 | $2.36 | $2.00 | $3.50 |
| 0096 | Silt excavation (6030000000-E) | CY | 510 | $0.01 | $0.01 | $0.01 | $10.00 |
| 0097 | Matting for erosion control (6036000000-E) | SY | 1,200 | $2.50 | $2.63 | $1.85 | $3.00 |
| 0098 | Coir fiber mat (6037000000-E) | SY | 100 | $18.00 | $18.90 | $5.75 | $6.60 |
| 0099 | 1/4" hardware cloth (6042000000-E) | LF | 895 | $4.00 | $4.20 | $6.00 | $5.50 |
| 0100 | Flocculant (6071002000-E) | LB | 50 | $1.00 | $8.04 | $8.00 | $5.50 |
| 0101 | Seeding and mulching (6084000000-E) | ACRE | 6 | $3,000.00 | $3,150.00 | $3,000.00 | $3,250.00 |
| 0102 | Mowing (6087000000-E) | ACRE | 3 | $100.00 | $105.00 | $175.00 | $275.00 |
| 0103 | Seed for repair seeding (6090000000-E) | LB | 50 | $1.00 | $1.05 | $5.00 | $5.00 |
| 0104 | Fertilizer for repair seeding (6093000000-E) | TON | 0.25 | $1,000.00 | $1,050.00 | $500.00 | $1,550.00 |
| 0105 | Seed for supplemental seeding (6096000000-E) | LB | 125 | $1.00 | $1.05 | $5.00 | $5.00 |
| 0106 | Fertilizer topdressing (6108000000-E) | TON | 3.50 | $850.00 | $892.50 | $500.00 | $1,100.00 |
| 0107 | Specialized hand mowing (6114500000-N) | MHR | 10 | $250.00 | $262.50 | $55.00 | $192.00 |
| 0108 | Response for erosion control (6117000000-N) | EACH | 15 | $1.00 | $1.05 | $300.00 | $165.00 |
| 0109 | Concrete washout structure (6117500000-N) | EACH | 1 | $1,000.00 | $2,748.42 | $321.00 | $1,100.00 |
| 0110 | Generic erosion control item (EA) - fabric insert inlet protection cleanout (6132000000-N) | EACH | 18 | $126.95 | $339.70 | $120.00 | $305.00 |
| 0111 | Generic erosion control item (EA) - fabric insert inlet protection, type 1 (6132000000-N) | EACH | 6 | $278.15 | $339.70 | $130.00 | $324.00 |
| 0112 | Generic erosion control item (EA) - prefabricated concrete washout (6132000000-N) | EACH | 6 | $635.00 | $1,161.05 | $321.00 | $675.00 |
| 0113 | MSE retain wall no ** - (1) (8801000000-E) | SF | 1,600 | $177.61 | $160.00 | $201.00 | $165.00 |
| 0114 | MSE retain wall no ** - (2) (8801000000-E) | SF | 1,633 | $178.49 | $160.00 | $201.00 | $162.00 |
| 0115 | Remv exist STR ****** BRG (402) - (20+96.07 -L-) (8035000000-N) | LS | 1 | $215,040 | $341,000 | $220,000 | $450,000 |
| 0116 | Asbestos assessment (8065000000-N) | LS | 1 | $1,598.27 | $2,625.00 | $2,000.00 | $2,800.00 |
| 0117 | FND excav B** sta ******* - (1, 20+96.07 -L-) (8091000000-N) | LS | 1 | $20,050 | $70,000 | $34,000 | $100,000 |
| 0118 | Reinforced concrete deck slab (8147000000-E) | SF | 5,422 | $59.07 | $45.00 | $67.25 | $65.00 |
| 0119 | Grooving bridge floors (8161000000-E) | SF | 5,296 | $1.78 | $1.24 | $1.40 | $1.20 |
| 0120 | Class AA concrete (bridge) (8175000000-E) | CY | 55.60 | $672.58 | $756.00 | $1,900.00 | $1,100.00 |
| 0121 | Class A concrete (bridge) (8182000000-E) | CY | 94.90 | $1,340.34 | $1,843.00 | $1,875.00 | $1,750.00 |
| 0122 | BRG appr slab *********** - (20+96.07 -L-) (8210000000-N) | LS | 1 | $43,825 | $33,000 | $68,000 | $40,000 |
| 0123 | Reinforcing steel (bridge) (8217000000-E) | LB | 22,657 | $1.77 | $1.35 | $1.00 | $1.70 |
| 0124 | Spiral column reinforcing steel (bridge) (8238000000-E) | LB | 851 | $3.96 | $2.59 | $3.50 | $4.50 |
| 0125 | Fib **" prestr conc girdr - (36") (8278000000-E) | LF | 546.80 | $460.76 | $400.00 | $516.21 | $585.00 |
| 0126 | Pile DRV equip setup ** steel piles - (HP 12 X 53) (8328200000-E) | EACH | 24 | $1,270.21 | $1,286.00 | $3,900.00 | $1,250.00 |
| 0127 | HP 12 X 53 steel piles (8364000000-E) | LF | 960 | $50.00 | $71.00 | $0.01 | $60.00 |
| 0128 | Steel pile points (8391000000-N) | EACH | 24 | $181.00 | $154.00 | $160.50 | $150.00 |
| 0129 | Dynamic pile testing (8394000000-N) | EACH | 2 | $1.00 | $2,000.00 | $2,500.00 | $2,500.00 |
| 0130 | Concrete barrier rail (8503000000-E) | LF | 276.45 | $167.12 | $161.00 | $202.30 | $130.00 |
| 0131 | 4" slope protection (8531000000-E) | SY | 22 | $370.13 | $195.00 | $670.00 | $125.00 |
| 0132 | Elastomeric bearings (8657000000-N) | LS | 1 | $5,325.00 | $22,000 | $7,609.33 | $4,500.00 |
| 0133 | Foam joint seals (8692000000-N) | LS | 1 | $24,325 | $12,025 | $42,000 | $25,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NCDOT's tabulation for this contract. NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
Every contract let that day: NCDOT letting of October 21, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.