Vertical concrete barrier rail, NCDOT 8505000000-E
Low bidders on NCDOT contracts carried a median of $161.93 per LF for this item, over the 24 months to 20 OCT 2026, across 11 low bids. Half of all 71 bids fell between $153.39 and $203.38.
- Owner
- North Carolina DOT
- Item
- 8505000000-E
- Unit
- LF
- Data through
- 20 OCT 2026
NCDOT prints this item as “VERT CONC BARRIER RAIL”.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2013 | 37 | 37 | $82.59 | 194 | $83.87 |
| 2014 | 17 | 17 | $85.00 | 99 | $85.47 |
| 2015 | 6 | 6 | $114.50 | 42 | $119.00 |
| 2016 | 13 | 13 | $90.79 | 79 | $100.00 |
| 2017 | 12 | 12 | $101.00 | 83 | $106.00 |
| 2018 | 10 | 10 | $110.00 | 59 | $115.09 |
| 2019 | 4 | 4 | $110.50 | 24 | $120.00 |
| 2020 | 5 | 5 | $132.00 | 47 | $128.70 |
| 2021 | 19 | 19 | $135.25 | 119 | $140.00 |
| 2022 | 5 | 5 | $185.00 | 25 | $215.00 |
| 2023 | 5 | 5 | $187.45 | 23 | $200.00 |
| 2024 | 4 | 4 | $148.01 | 34 | $154.00 |
| 2025 | 4 | 4 | $155.00 | 24 | $157.70 |
| 2026 | 6 | 6 | $194.50 | 36 | $181.48 |
Bid prices as published, not adjusted for inflation.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Dane Construction, Inc. | 91 | 35 (38%) |
| Smith-Rowe, LLC | 66 | 9 (14%) |
| Apple Tuck & Associates, Inc. | 21 | 8 (38%) |
| Palmetto Infrastructure Inc | 40 | 7 (18%) |
| National Bridge Builders LLC | 12 | 7 (58%) |
| Trader Construction Co. | 12 | 6 (50%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 24 SEP 2026 | C205140 | New Hanover | 143.40 | $387.07 | $387.07 | 1 | Balfour Beatty Infrastructure Inc | NCDOT |
| 15 SEP 2026 | C205214 | Wilkes | 215 | $209.00 | $209.00 | 5 | James R Vannoy & Sons Construction Company Inc | NCDOT |
| 18 AUG 2026 | C204504 | Watauga | 170.98 | $475.50 | $356.00 | 3 | Branch Civil Inc | NCDOT |
| 18 AUG 2026 | C204877 | Rutherford | 340.75 | $180.00 | $175.00 | 8 | R.E. Burns & Sons Co., Inc. | NCDOT |
| 18 AUG 2026 | C205070 | Rutherford | 287.50 | $162.00 | $182.96 | 9 | United Infrastructure Group Inc | NCDOT |
| 19 MAY 2026 | C204773 | Gaston, Mecklenburg | 2,385.50 | $161.33 | $168.75 | 10 | Zachry Construction Corporation | NCDOT |
| 21 OCT 2025 | C204711 | Beaufort | 1,921.56 | $150.00 | $145.00 | 8 | Sanford Contractors Inc | NCDOT |
| 19 AUG 2025 | C204956 | Burke, Caldwell | 1,125 | $133.24 | $133.24 | 3 | Balfour Beatty Infrastructure Inc | NCDOT |
| 15 APR 2025 | C205059 | Stokes | 380 | $161.93 | $177.50 | 7 | Smith-Rowe, LLC | NCDOT |
| 18 FEB 2025 | C204883 | Rutherford | 317.13 | $160.00 | $215.35 | 6 | Kemp Sigmon Construction Co Inc | NCDOT |
| 17 DEC 2024 | C204969 | Anson | 600 | $153.00 | $148.00 | 11 | Sanford Contractors Inc | NCDOT |
| 15 OCT 2024 | C204348 | Iredell, Catawba | 1,268.75 | $245.00 | $150.00 | 5 | Blythe Development Co. | NCDOT |
| 19 MAR 2024 | C204876 | Rockingham | 385.43 | $142.78 | $168.00 | 9 | Smith-Rowe, LLC | NCDOT |
| 16 JAN 2024 | C204830 | Stanly | 540.76 | $143.02 | $165.00 | 9 | Smith-Rowe, LLC | NCDOT |
| 20 JUN 2023 | C204838 | Edgecombe | 265.60 | $150.00 | $147.50 | 4 | Barnhill Contracting Company | NCDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the NCDOT explorer.
How these prices were read
NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NCDOT's own: this item is compared with NCDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the NCDOT letting of 20 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.