NCDOT contract C204956 bid tabulation
DRAINAGE, GRADING, PAVING, AND STRUCTURES., GRADING, DRAINAGE, PAVING, AND STRUCTURES. BRIDGE #110010 OVER CATAWBA RIVER ON SR-1001 (CONNELLY SPRINGS RD). Let by North Carolina DOT on August 19, 2025, Burke, Caldwell. 3 bids received; low bid $30,874,733 by Balfour Beatty Infrastructure Inc.
- Owner
- North Carolina DOT
- Letting
- 19 AUG 2025
- Pay items
- 162
- Data through
- 20 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Balfour Beatty Infrastructure Inc | $30,874,733 | Low |
| 2 | Smith-Rowe, LLC | $31,044,546 | +1.0% |
| 3 | Zachry Construction Corporation | $31,764,528 | +3.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Balfour Beatty Infrastructure Inc | 2. Smith-Rowe, LLC | 3. Zachry Construction Corporation |
|---|---|---|---|---|---|---|
| 0001 | Mobilization (0000100000-N) | LS | 1 | $1,543,736 | $1,552,200 | $1,591,000 |
| 0002 | Construction surveying (0000400000-N) | LS | 1 | $745,880 | $77,200 | $500,000 |
| 0003 | Generic miscellaneous item (LS) - navigational safety plan (0000900000-N) | LS | 1 | $53,991 | $128,697 | $2,000,000 |
| 0004 | Unclassified excavation (0022000000-E) | CY | 22,500 | $12.33 | $17.96 | $17.00 |
| 0005 | Undercut excavation (0036000000-E) | CY | 450 | $14.32 | $42.35 | $19.00 |
| 0006 | Supplementary clearing & grubbing (0050000000-E) | ACRE | 1 | $14,000 | $1.00 | $1,000.00 |
| 0007 | Grading (0063000000-N) | LS | 1 | $778,470 | $696,997 | $2,000,000 |
| 0008 | Drainage ditch excavation (0134000000-E) | CY | 440 | $12.92 | $27.15 | $8.31 |
| 0009 | Select granular material (0195000000-E) | CY | 400 | $71.00 | $0.01 | $73.19 |
| 0010 | Geotextile for soil stabilization (0196000000-E) | SY | 400 | $15.52 | $5.65 | $4.91 |
| 0011 | Temporary shoring (0199000000-E) | SF | 288 | $60.00 | $95.20 | $0.00 |
| 0012 | Generic grading item (LS) - type 1 bridge approach fill, station 34+52.50 -L- (0248000000-N) | LS | 1 | $72,269 | $53,700 | $40,268 |
| 0013 | Foundation conditioning material, minor structures (0318000000-E) | TON | 130 | $68.71 | $63.25 | $53.75 |
| 0014 | FND condit geotextile (4A) (0321000000-E) | SY | 390 | $6.74 | $5.60 | $6.03 |
| 0015 | 15" drainage pipe (0335200000-E) | LF | 144 | $94.78 | $92.46 | $84.22 |
| 0016 | 18" drainage pipe (0335300000-E) | LF | 60 | $112.07 | $96.02 | $99.55 |
| 0017 | 15" RC pipe culverts, class III (0366000000-E) | LF | 272 | $114.52 | $153.08 | $110.02 |
| 0018 | 24" RC pipe culverts, class III (0378000000-E) | LF | 76 | $243.02 | $203.85 | $147.08 |
| 0019 | ***" RCP culv class IV - (12") (0448000000-E) | LF | 44 | $182.22 | $150.37 | $95.00 |
| 0020 | 15" RC pipe culverts, class IV (0448200000-E) | LF | 296 | $154.38 | $115.22 | $102.51 |
| 0021 | 18" RC pipe culverts, class IV (0448300000-E) | LF | 224 | $149.27 | $160.64 | $126.47 |
| 0022 | 24" CS pipe culverts, 0.064" thick (0594000000-E) | LF | 40 | $161.06 | $138.06 | $120.04 |
| 0023 | **" CS elbow *****" thick - (24", 0.064") (0636000000-E) | EACH | 1 | $1,559.54 | $1,475.22 | $1,317.04 |
| 0024 | Pipe removal (0995000000-E) | LF | 134 | $35.79 | $36.20 | $27.97 |
| 0025 | Shallow undercut (1099500000-E) | CY | 100 | $39.00 | $38.24 | $23.47 |
| 0026 | Class IV subgrade stabilization (1099700000-E) | TON | 200 | $51.00 | $61.25 | $43.36 |
| 0027 | Geotextile for subgrade stabilization (1112000000-E) | SY | 300 | $7.33 | $6.40 | $4.91 |
| 0028 | Aggregate base course (1121000000-E) | TON | 1,600 | $56.28 | $58.15 | $45.22 |
| 0029 | Incidental stone base (1220000000-E) | TON | 100 | $65.21 | $73.05 | $40.12 |
| 0030 | Prime coat (1275000000-E) | GAL | 330 | $30.00 | $30.00 | $10.00 |
| 0031 | Incidental milling (1330000000-E) | SY | 530 | $13.54 | $50.00 | $20.00 |
| 0032 | Asphalt conc base course, type B25.0C (1491000000-E) | TON | 1,630 | $141.43 | $141.43 | $82.00 |
| 0033 | Asphalt conc intermediate course, type I19.0C (1503000000-E) | TON | 1,490 | $140.30 | $140.30 | $84.00 |
| 0034 | Asphalt conc surface course, type S9.5B (1519000000-E) | TON | 1,700 | $139.27 | $139.27 | $90.00 |
| 0035 | Asphalt binder for plant mix (1575000000-E) | TON | 260 | $868.13 | $868.13 | $621.00 |
| 0036 | Right-of-way markers (2000000000-N) | EACH | 40 | $440.07 | $365.00 | $300.00 |
| 0037 | Subdrain excavation (2022000000-E) | CY | 44.80 | $71.69 | $44.45 | $24.04 |
| 0038 | Geotextile for subsurface drains (2026000000-E) | SY | 200 | $17.61 | $4.15 | $3.65 |
| 0039 | Subdrain coarse aggregate (2036000000-E) | CY | 33.60 | $202.87 | $99.75 | $50.08 |
| 0040 | 6" perforated subdrain pipe (2044000000-E) | LF | 200 | $27.38 | $7.80 | $24.94 |
| 0041 | Subdrain pipe outlet (2070000000-N) | EACH | 1 | $571.03 | $533.00 | $303.22 |
| 0042 | 6" outlet pipe (2077000000-E) | LF | 6 | $545.45 | $61.85 | $44.14 |
| 0043 | Pipe plugs (2264000000-E) | CY | 0.36 | $3,077.43 | $1.00 | $2,591.05 |
| 0044 | Flowable fill (2275000000-E) | CY | 15 | $482.86 | $503.61 | $338.45 |
| 0045 | Masonry drainage structures (2286000000-N) | EACH | 17 | $3,574.65 | $4,148.24 | $4,310.85 |
| 0046 | Masonry drainage structures (2308000000-E) | LF | 2.60 | $288.91 | $731.34 | $688.24 |
| 0047 | Frame with two grates, STD 840.16 (2364000000-N) | EACH | 1 | $1,079.28 | $2,972.79 | $1,140.45 |
| 0048 | Frame with two grates, STD 840.22 (2365000000-N) | EACH | 3 | $985.85 | $2,884.75 | $1,010.07 |
| 0049 | Frame with two grates, STD 840.29 (2367000000-N) | EACH | 6 | $985.85 | $1,274.14 | $1,063.67 |
| 0050 | Frame-GRT-HD 840.03 ** - (E) (2374000000-N) | EACH | 1 | $1,244.09 | $1,491.65 | $1,191.62 |
| 0051 | Frame-GRT-HD 840.03 ** - (F) (2374000000-N) | EACH | 2 | $1,244.09 | $1,491.65 | $1,263.68 |
| 0052 | Frame-GRT-HD 840.03 ** - (G) (2374000000-N) | EACH | 2 | $1,244.09 | $1,491.65 | $1,263.68 |
| 0053 | Frame with cover, STD 840.54 (2396000000-N) | EACH | 1 | $789.41 | $1,160.21 | $909.92 |
| 0054 | Generic drainage item (EA) 840 - frame with cover, STD 840.55 (2472000000-N) | EACH | 1 | $717.76 | $1,160.21 | $909.99 |
| 0055 | **"X**" concrete curb - (8" X 12") (2535000000-E) | LF | 60 | $13.42 | $55.00 | $60.53 |
| 0056 | 1'-6" concrete curb & gutter (2542000000-E) | LF | 140 | $15.92 | $80.00 | $34.08 |
| 0057 | 2'-6" concrete curb & gutter (2549000000-E) | LF | 930 | $24.45 | $50.00 | $41.92 |
| 0058 | Shoulder berm gutter (2556000000-E) | LF | 20 | $26.38 | $105.00 | $91.97 |
| 0059 | Generic paving item 848 (SY) - 6" concrete sidewalk (2761000000-E) | SY | 150 | $69.47 | $98.02 | $107.59 |
| 0060 | Steel beam guardrail (3030000000-E) | LF | 2,025 | $23.00 | $23.00 | $25.76 |
| 0061 | Steel beam guardrail, shop curved (3045000000-E) | LF | 50 | $24.00 | $24.00 | $26.88 |
| 0062 | Additional guardrail posts (3150000000-N) | EACH | 10 | $11.00 | $0.01 | $12.32 |
| 0063 | Guardrail end units, type at-1 (3195000000-N) | EACH | 1 | $800.00 | $800.00 | $896.12 |
| 0064 | Guardrail anchor units, type III (3215000000-N) | EACH | 4 | $2,250.00 | $2,250.00 | $2,665.95 |
| 0065 | Guardrail end units, type TL-3 (3287000000-N) | EACH | 4 | $3,200.00 | $3,200.00 | $3,584.47 |
| 0066 | Remove existing guardrail (3360000000-E) | LF | 1,000 | $1.00 | $1.00 | $1.12 |
| 0067 | Rip rap, class I (3628000000-E) | TON | 15 | $222.53 | $87.57 | $71.06 |
| 0068 | Rip rap, class B (3649000000-E) | TON | 443 | $83.72 | $81.60 | $67.20 |
| 0069 | Geotextile for drainage (3656000000-E) | SY | 4,365 | $3.10 | $2.25 | $4.24 |
| 0070 | Supports, 3-LB steel U-channel (4072000000-E) | LF | 255 | $12.00 | $12.00 | $7.84 |
| 0071 | Sign erection, type D (4096000000-N) | EACH | 4 | $150.00 | $150.00 | $207.23 |
| 0072 | Sign erection, type E (4102000000-N) | EACH | 8 | $100.00 | $100.00 | $168.02 |
| 0073 | Sign erect, reloc ** GRD MTD - (D) (4116100000-N) | EACH | 3 | $150.00 | $150.00 | $207.23 |
| 0074 | Disposal of sign system, U-channel (4155000000-N) | EACH | 10 | $2.00 | $2.00 | $22.40 |
| 0075 | Disposal of support, U-channel (4192000000-N) | EACH | 4 | $2.00 | $2.00 | $22.40 |
| 0076 | Disposal of sign, D, E or F (4238000000-N) | EACH | 1 | $2.00 | $2.00 | $22.40 |
| 0077 | Work zone signs (stationary) (4400000000-E) | SF | 138 | $7.25 | $14.00 | $7.56 |
| 0078 | Work zone signs (portable) (4405000000-E) | SF | 316 | $30.12 | $25.51 | $9.52 |
| 0079 | Work zone signs (barricade mounted) (4410000000-E) | SF | 72 | $7.25 | $8.00 | $8.12 |
| 0080 | Portable changeable message sign (short term) (4422000000-N) | DAY | 28 | $20.00 | $336.90 | $84.01 |
| 0081 | Temporary portable traffic signal system (4424500000-N) | EACH | 1 | $17,959 | $32,779 | $15,122 |
| 0082 | Drums (4430000000-N) | EACH | 92 | $68.71 | $86.05 | $53.77 |
| 0083 | Cones (4435000000-N) | EACH | 33 | $31.15 | $1.00 | $26.88 |
| 0084 | Barricades (type III) (4445000000-E) | LF | 168 | $34.36 | $30.00 | $29.12 |
| 0085 | Flagger (4455000000-N) | DAY | 66 | $501.79 | $1,130.00 | $345.93 |
| 0086 | Temporary crash cushions (4465000000-N) | EACH | 4 | $6,500.00 | $8,205.25 | $7,281.08 |
| 0087 | Remove & reset temporary crash cushion (4470000000-N) | EACH | 1 | $2,500.00 | $2,450.00 | $2,800.41 |
| 0088 | Portable concrete barrier (4485000000-E) | LF | 819 | $38.00 | $49.00 | $42.57 |
| 0089 | Remove and reset portable concrete barrier (4500000000-E) | LF | 320 | $12.00 | $13.05 | $13.44 |
| 0090 | Law enforcement (4510000000-N) | HR | 4 | $90.00 | $188.63 | $123.20 |
| 0091 | Generic traffic control item (EA) - temporary river traffic warning signs (4600000000-N) | EACH | 6 | $750.00 | $1,500.00 | $193.20 |
| 0092 | 4" cold appl plstic lines type ** - (IV) (4770000000-E) | LF | 9,000 | $5.04 | $5.00 | $5.60 |
| 0093 | 24" cold appl plstic line type ** - (IV) (4795000000-E) | LF | 40 | $161.32 | $160.00 | $179.20 |
| 0094 | Paint pavement marking lines (4") (4810000000-E) | LF | 34,202 | $0.25 | $0.25 | $0.28 |
| 0095 | Paint pavement marking lines (8") (4820000000-E) | LF | 110 | $1.01 | $1.00 | $1.12 |
| 0096 | Polyurea lines (**", *** mils) - (4", 20 mils) (4846000000-E) | LF | 12,057 | $2.27 | $2.25 | $2.52 |
| 0097 | Removal of pavement marking lines (4") (4850000000-E) | LF | 994 | $1.01 | $1.00 | $1.12 |
| 0098 | Removal of pavement marking lines (8") (4860000000-E) | LF | 110 | $4.54 | $4.50 | $5.04 |
| 0099 | Removal of pavement marking lines (24") (4870000000-E) | LF | 40 | $12.10 | $12.00 | $13.44 |
| 0100 | Generic pavement marking item (EA) - inlaid cradle markers (4895000000-N) | EACH | 47 | $131.08 | $130.00 | $145.60 |
| 0101 | Portable lighting (5255000000-N) | LS | 1 | $102,112 | $35,400 | $40,066 |
| 0102 | Temporary silt fence (6000000000-E) | LF | 4,160 | $2.90 | $4.00 | $4.48 |
| 0103 | Stone for erosion control, class A (6006000000-E) | TON | 225 | $82.15 | $87.80 | $66.83 |
| 0104 | Stone for erosion control, class B (6009000000-E) | TON | 670 | $83.72 | $84.35 | $66.83 |
| 0105 | Sediment control stone (6012000000-E) | TON | 1,245 | $71.35 | $0.01 | $52.86 |
| 0106 | Temporary mulching (6015000000-E) | ACRE | 13 | $1,600.00 | $100.00 | $1,232.00 |
| 0107 | Seed for temporary seeding (6018000000-E) | LB | 900 | $2.00 | $1.00 | $1.12 |
| 0108 | Fertilizer for temporary seeding (6021000000-E) | TON | 5 | $900.00 | $950.00 | $1,060.06 |
| 0109 | Temporary slope drains (6024000000-E) | LF | 200 | $17.34 | $22.40 | $28.03 |
| 0110 | Safety fence (6029000000-E) | LF | 460 | $3.00 | $5.00 | $3.35 |
| 0111 | Silt excavation (6030000000-E) | CY | 1,920 | $4.00 | $0.01 | $14.44 |
| 0112 | Matting for erosion control (6036000000-E) | SY | 7,000 | $1.60 | $2.50 | $2.23 |
| 0113 | Coir fiber mat (6037000000-E) | SY | 100 | $6.00 | $30.00 | $22.32 |
| 0114 | 1/4" hardware cloth (6042000000-E) | LF | 570 | $5.00 | $3.50 | $3.91 |
| 0115 | Low permeability geotextile (6043000000-E) | SY | 100 | $6.00 | $6.30 | $22.32 |
| 0116 | Special stilling basins (6070000000-N) | EACH | 42 | $329.27 | $695.00 | $1,098.63 |
| 0117 | Flocculant (6071002000-E) | LB | 60 | $5.00 | $1.00 | $1.12 |
| 0118 | Wattle (6071010000-E) | LF | 90 | $8.00 | $20.00 | $22.32 |
| 0119 | Wattle barrier (6071013000-E) | LF | 2,015 | $12.00 | $8.00 | $8.93 |
| 0120 | Coir fiber baffle (6071030000-E) | LF | 265 | $9.00 | $9.00 | $10.04 |
| 0121 | **" skimmer - (1-1/2") (6071050000-E) | EACH | 1 | $985.74 | $1,405.97 | $1,744.62 |
| 0122 | **" skimmer - (2") (6071050000-E) | EACH | 1 | $1,207.72 | $1,550.00 | $1,908.75 |
| 0123 | Seeding and mulching (6084000000-E) | ACRE | 12 | $2,700.00 | $2,800.00 | $3,124.39 |
| 0124 | Mowing (6087000000-E) | ACRE | 9 | $250.00 | $200.00 | $223.17 |
| 0125 | Seed for repair seeding (6090000000-E) | LB | 150 | $4.50 | $5.00 | $5.58 |
| 0126 | Fertilizer for repair seeding (6093000000-E) | TON | 0.25 | $1,400.00 | $800.00 | $888.86 |
| 0127 | Seed for supplemental seeding (6096000000-E) | LB | 275 | $4.50 | $1.00 | $1.11 |
| 0128 | Fertilizer topdressing (6108000000-E) | TON | 8 | $925.00 | $800.00 | $888.86 |
| 0129 | Specialized hand mowing (6114500000-N) | MHR | 10 | $175.00 | $250.00 | $277.77 |
| 0130 | Response for erosion control (6117000000-N) | EACH | 25 | $250.00 | $25.00 | $27.78 |
| 0131 | Concrete washout structure (6117500000-N) | EACH | 1 | $3,237.11 | $2,980.25 | $979.42 |
| 0132 | Reforestation (6123000000-E) | ACRE | 0.22 | $12,000 | $4,500.00 | $4,999.82 |
| 0133 | Generic erosion control item (EA) - prefabricated concrete washout (6132000000-N) | EACH | 6 | $1,400.86 | $1,635.00 | $871.79 |
| 0134 | CM&R temp access *********** - (34+52.50 -L-) (8017000000-N) | LS | 1 | $8,037,852 | $7,143,438 | $7,000,000 |
| 0135 | Remv exist STR ****** BRG (402) - (34+52.50 -L-) (8035000000-N) | LS | 1 | $1,658,920 | $3,200,000 | $3,900,000 |
| 0136 | Asbestos assessment (8065000000-N) | LS | 1 | $1,200.00 | $1,500.00 | $1,444.09 |
| 0137 | **'-**" dia drilld piers - (6'-0") (8108000000-E) | LF | 1,462.60 | $3,416.49 | $3,504.00 | $2,380.85 |
| 0138 | Perm STL casing for ** pier - (6'-0") (8111000000-E) | LF | 1,119.60 | $920.00 | $1,226.00 | $1,047.89 |
| 0139 | Sid inspections (8113000000-N) | EACH | 21 | $1,000.00 | $1,720.00 | $2,707.24 |
| 0140 | CSL testing (8115000000-N) | EACH | 21 | $1,900.00 | $2,732.00 | $1,907.30 |
| 0141 | Uncl STR excav sta ***** - (34+52.50 -L-) (8121000000-N) | LS | 1 | $191,612 | $191,292 | $101,423 |
| 0142 | Reinforced concrete deck slab (8147000000-E) | SF | 57,591 | $42.80 | $47.03 | $37.73 |
| 0143 | Grooving bridge floors (8161000000-E) | SF | 49,446 | $0.63 | $0.86 | $0.37 |
| 0144 | Class A concrete (bridge) (8182000000-E) | CY | 900.40 | $1,416.45 | $1,124.22 | $1,217.92 |
| 0145 | BRG appr slab *********** - (34+52.50 -L-) (8210000000-N) | LS | 1 | $111,548 | $92,130 | $78,268 |
| 0146 | Reinforcing steel (bridge) (8217000000-E) | LB | 401,365 | $1.50 | $1.55 | $1.28 |
| 0147 | Spiral column reinforcing steel (bridge) (8238000000-E) | LB | 75,172 | $3.01 | $3.53 | $2.52 |
| 0148 | Pile DRV equip setup ** steel piles - (HP 14 X 73) (8328200000-E) | EACH | 26 | $3,774.93 | $1,335.11 | $5,000.00 |
| 0149 | HP 14 X 73 steel piles (8384000000-E) | LF | 1,235 | $81.98 | $66.58 | $87.55 |
| 0150 | Steel pile points (8391000000-N) | EACH | 13 | $253.29 | $216.85 | $187.35 |
| 0151 | Dynamic pile testing (8394000000-N) | EACH | 1 | $5,020.17 | $1.00 | $2,332.75 |
| 0152 | Two bar metal rail (8475000000-E) | LF | 2,134.17 | $195.91 | $162.03 | $167.99 |
| 0153 | *****"galv STL pipe rail - (44") (8496000000-E) | LF | 33.50 | $369.86 | $453.83 | $298.27 |
| 0154 | Vertical concrete barrier rail (8505000000-E) | LF | 1,125 | $133.24 | $124.35 | $155.40 |
| 0155 | 1'-**"X*****"conc parapet - (1'-2" X 2'-6") (8517000000-E) | LF | 2,165 | $117.01 | $212.67 | $123.34 |
| 0156 | Rip rap class II (2'-0" thick) (8608000000-E) | TON | 517 | $101.44 | $83.93 | $0.01 |
| 0157 | Geotextile for drainage (8622000000-E) | SY | 571 | $4.52 | $4.35 | $5.28 |
| 0158 | Elastomeric bearings (8657000000-N) | LS | 1 | $51,159 | $24,925 | $117,543 |
| 0159 | Generic structure item (LS) - strip seal expansion joints (8860000000-N) | LS | 1 | $231,061 | $173,100 | $128,518 |
| 0160 | Generic structure item (LF) - modified 74" prestressed concrete girders (8867000000-E) | LF | 6,432.02 | $459.10 | $402.03 | $343.43 |
| 0161 | Generic structure item (LF) - vertical concrete barrier rail with moment slab (8867000000-E) | LF | 68 | $439.21 | $1,050.42 | $452.11 |
| 0162 | Generic structure item (EA) - thermal integrity profiler (8897000000-N) | EACH | 21 | $3,967.14 | $2,395.00 | $3,382.47 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NCDOT's tabulation for this contract. NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
Every contract let that day: NCDOT letting of August 19, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.