NCDOT contract C204883 bid tabulation
GRADING, DRAINAGE, PAVING, AND STRUCTURES. BRIDGE #800040 OVER NORTH FORK FIRST BROAD CREEK ON NC-226. Let by North Carolina DOT on February 18, 2025, Rutherford. 6 bids received; low bid $5,593,808 by Kemp Sigmon Construction Co Inc.
- Owner
- North Carolina DOT
- Letting
- 18 FEB 2025
- Pay items
- 133
- Data through
- 20 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Kemp Sigmon Construction Co Inc | $5,593,808 | Low |
| 2 | NHM Constructors, LLC | $6,688,028 | +20% |
| 3 | Ipc Paving LLC DBA Ipc Structures LLC | $7,358,244 | +32% |
| 4 | Reeves Construction Company | $7,618,294 | +36% |
| 5 | Caton Construction Group Inc | $7,793,804 | +39% |
| 6 | Mastec Civil, LLC | $7,950,111 | +42% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Kemp Sigmon Construction Co Inc | 2. NHM Constructors, LLC | 3. Ipc Paving LLC DBA Ipc Structures LLC | 4. Reeves Construction Company | 5. Caton Construction Group Inc | 6. Mastec Civil, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Mobilization (0000100000-N) | LS | 1 | $275,000 | $621,412 | $365,000 | $380,000 | $389,690 | $395,000 |
| 0002 | Construction surveying (0000400000-N) | LS | 1 | $53,000 | $109,080 | $150,000 | $55,000 | $24,850 | $135,000 |
| 0003 | Supplementary clearing & grubbing (0050000000-E) | ACRE | 1 | $100.00 | $3,712.00 | $2,250.00 | $1.00 | $7,000.00 | $19,000 |
| 0004 | Undercut excavation (0057000000-E) | CY | 450 | $25.00 | $55.10 | $20.00 | $34.00 | $65.00 | $81.00 |
| 0005 | Grading (0063000000-N) | LS | 1 | $450,000 | $839,165 | $950,000 | $710,000 | $792,000 | $250,000 |
| 0006 | Borrow excavation (0106000000-E) | CY | 24,900 | $24.00 | $25.10 | $33.00 | $29.50 | $45.00 | $40.00 |
| 0007 | Drainage ditch excavation (0134000000-E) | CY | 1,080 | $15.00 | $25.50 | $17.00 | $55.00 | $25.00 | $39.10 |
| 0008 | Select granular material (0195000000-E) | CY | 400 | $20.00 | $83.00 | $38.00 | $36.50 | $80.00 | $67.00 |
| 0009 | Geotextile for soil stabilization (0196000000-E) | SY | 1,300 | $4.00 | $5.70 | $5.00 | $14.00 | $5.00 | $9.25 |
| 0010 | Temporary shoring (0199000000-E) | SF | 861 | $150.00 | $165.68 | $25.00 | $185.00 | $85.00 | $179.35 |
| 0011 | Generic grading item (LS) - type 1 bridge approach fill, station 18+28.00 -L- (0248000000-N) | LS | 1 | $300,000 | $53,537 | $150,000 | $53,000 | $63,900 | $25,000 |
| 0012 | Foundation conditioning material, minor structures (0318000000-E) | TON | 70 | $1.00 | $55.80 | $65.00 | $194.00 | $80.00 | $92.00 |
| 0013 | FND condit geotextile (4A) (0321000000-E) | SY | 210 | $1.00 | $9.30 | $12.00 | $18.50 | $5.00 | $8.50 |
| 0014 | 15" drainage pipe (0335200000-E) | LF | 68 | $100.00 | $79.50 | $92.00 | $166.50 | $85.00 | $95.00 |
| 0015 | 15" RC pipe culverts, class III (0366000000-E) | LF | 100 | $100.00 | $98.50 | $148.00 | $140.00 | $100.00 | $150.00 |
| 0016 | 18" RC pipe culverts, class III (0372000000-E) | LF | 96 | $110.00 | $111.10 | $160.00 | $153.00 | $115.00 | $178.00 |
| 0017 | 15" CS pipe culverts, 0.064" thick (0582000000-E) | LF | 152 | $100.00 | $94.10 | $98.00 | $144.50 | $105.00 | $270.00 |
| 0018 | 24" CS pipe culverts, 0.064" thick (0594000000-E) | LF | 188 | $130.00 | $116.70 | $112.00 | $156.00 | $120.00 | $175.00 |
| 0019 | **" CS elbow *****" thick - (15", 0.064") (0636000000-E) | EACH | 8 | $1,000.00 | $1,221.70 | $843.00 | $1,200.00 | $1,500.00 | $1,300.00 |
| 0020 | **" CS elbow *****" thick - (24", 0.064") (0636000000-E) | EACH | 4 | $1,250.00 | $1,491.90 | $889.00 | $2,400.00 | $1,800.00 | $1,300.00 |
| 0021 | Pipe removal (0995000000-E) | LF | 287 | $25.00 | $32.10 | $38.00 | $92.00 | $60.00 | $67.00 |
| 0022 | Shallow undercut (1099500000-E) | CY | 100 | $10.00 | $25.10 | $28.00 | $70.00 | $68.00 | $75.00 |
| 0023 | Class IV subgrade stabilization (1099700000-E) | TON | 200 | $30.00 | $44.70 | $55.00 | $94.00 | $65.00 | $55.00 |
| 0024 | Aggregate base course (1121000000-E) | TON | 1,286 | $50.00 | $44.70 | $56.50 | $73.50 | $60.00 | $52.00 |
| 0025 | Incidental stone base (1220000000-E) | TON | 150 | $50.00 | $46.70 | $66.50 | $61.50 | $80.00 | $76.00 |
| 0026 | Prime coat (1275000000-E) | GAL | 1,250 | $7.25 | $10.91 | $10.00 | $15.00 | $10.31 | $51.00 |
| 0027 | Incidental milling (1330000000-E) | SY | 935 | $55.00 | $16.36 | $15.00 | $13.76 | $15.46 | $6.00 |
| 0028 | Asphalt conc base course, type B25.0C (1491000000-E) | TON | 950 | $107.00 | $163.62 | $150.00 | $162.00 | $154.64 | $165.00 |
| 0029 | Asphalt conc intermediate course, type I19.0C (1503000000-E) | TON | 770 | $110.00 | $163.62 | $150.00 | $162.00 | $154.64 | $165.00 |
| 0030 | Asphalt conc surface course, type S9.5B (1519000000-E) | TON | 1,220 | $120.00 | $163.62 | $150.00 | $167.00 | $154.64 | $170.00 |
| 0031 | Asphalt binder for plant mix (1575000000-E) | TON | 160 | $600.00 | $709.02 | $650.00 | $700.00 | $670.10 | $708.00 |
| 0032 | Asphalt plant mix, pavement repair (1693000000-E) | TON | 50 | $250.00 | $381.78 | $694.00 | $91.00 | $300.00 | $253.00 |
| 0033 | Subdrain excavation (2022000000-E) | CY | 212.80 | $1.00 | $25.10 | $45.00 | $132.50 | $77.00 | $35.00 |
| 0034 | Geotextile for subsurface drains (2026000000-E) | SY | 200 | $1.00 | $7.50 | $15.00 | $32.50 | $8.00 | $6.00 |
| 0035 | Subdrain fine aggregate (2033000000-E) | CY | 126 | $1.00 | $80.70 | $93.10 | $63.50 | $115.00 | $35.00 |
| 0036 | Subdrain coarse aggregate (2036000000-E) | CY | 33.60 | $1.00 | $84.60 | $70.50 | $99.00 | $125.00 | $50.00 |
| 0037 | 6" perforated subdrain pipe (2044000000-E) | LF | 950 | $1.00 | $23.80 | $22.00 | $41.50 | $35.00 | $35.00 |
| 0038 | Subdrain pipe outlet (2070000000-N) | EACH | 3 | $1.00 | $1,093.30 | $575.00 | $669.00 | $3,000.00 | $1,000.00 |
| 0039 | 6" outlet pipe (2077000000-E) | LF | 18 | $1.00 | $27.50 | $50.00 | $40.00 | $80.00 | $50.00 |
| 0040 | Endwalls (2209000000-E) | CY | 1.50 | $1,500.00 | $3,219.00 | $4,500.00 | $3,400.00 | $4,500.00 | $1,000.00 |
| 0041 | Masonry drainage structures (2286000000-N) | EACH | 7 | $4,000.00 | $3,334.70 | $5,700.00 | $2,800.00 | $8,000.00 | $2,500.00 |
| 0042 | Masonry drainage structures (2308000000-E) | LF | 0.30 | $750.00 | $800.00 | $840.00 | $27.00 | $550.00 | $1,500.00 |
| 0043 | Frame with two grates, STD 840.16 (2364000000-N) | EACH | 1 | $1,500.00 | $1,039.50 | $1,295.00 | $2,100.00 | $1,600.00 | $1,200.00 |
| 0044 | Frame with two grates, STD 840.20 (2364200000-N) | EACH | 4 | $1,500.00 | $913.40 | $1,100.00 | $894.50 | $1,500.00 | $1,200.00 |
| 0045 | Frame with two grates, STD 840.22 (2365000000-N) | EACH | 2 | $1,500.00 | $898.60 | $998.00 | $1,260.00 | $1,500.00 | $1,200.00 |
| 0046 | Shoulder berm gutter (2556000000-E) | LF | 150 | $100.00 | $171.10 | $100.00 | $100.00 | $100.00 | $118.00 |
| 0047 | Steel beam guardrail (3030000000-E) | LF | 1,112.50 | $23.00 | $24.00 | $23.00 | $22.00 | $22.00 | $24.00 |
| 0048 | Steel beam guardrail, shop curved (3045000000-E) | LF | 75 | $23.50 | $32.73 | $23.50 | $30.00 | $30.00 | $32.00 |
| 0049 | Additional guardrail posts (3150000000-N) | EACH | 10 | $11.00 | $44.73 | $11.00 | $41.00 | $41.00 | $43.50 |
| 0050 | Guardrail end units, type at-1 (3195000000-N) | EACH | 1 | $900.00 | $1,036.26 | $900.00 | $950.00 | $950.00 | $1,006.25 |
| 0051 | Guardrail anchor units, type III (3215000000-N) | EACH | 4 | $2,350.00 | $2,508.84 | $2,350.00 | $2,300.00 | $2,300.00 | $2,445.00 |
| 0052 | Guardrail end units, type TL-3 (3287000000-N) | EACH | 3 | $3,400.00 | $3,599.64 | $3,400.00 | $3,300.00 | $3,300.00 | $3,500.00 |
| 0053 | Remove existing guardrail (3360000000-E) | LF | 1,368.75 | $1.00 | $3.28 | $1.00 | $3.00 | $3.00 | $5.00 |
| 0054 | Temporary steel beam guardrail (3380000000-E) | LF | 1,150 | $7.00 | $12.34 | $7.00 | $11.31 | $11.31 | $11.98 |
| 0055 | Temporary steel beam guardrail, shop curved (3382000000-E) | LF | 62.50 | $10.00 | $20.73 | $10.00 | $19.00 | $19.00 | $20.15 |
| 0056 | Temp GDRL anch units ****** - (III) (3387000000-N) | EACH | 4 | $800.00 | $1,636.20 | $800.00 | $1,500.00 | $1,500.00 | $1,600.00 |
| 0057 | Temp GDRL end units ***** - (at-1) (3389150000-N) | EACH | 1 | $400.00 | $654.48 | $400.00 | $600.00 | $600.00 | $700.00 |
| 0058 | Temp GDRL end units ***** - (TL-2) (3389150000-N) | EACH | 3 | $1,850.00 | $2,399.76 | $1,850.00 | $2,200.00 | $2,200.00 | $2,335.00 |
| 0059 | Temporary additional guardrail posts (3389160000-N) | EACH | 10 | $11.00 | $21.82 | $11.00 | $20.00 | $20.00 | $22.00 |
| 0060 | Rip rap, class I (3628000000-E) | TON | 500 | $70.00 | $77.40 | $93.50 | $68.00 | $80.00 | $83.00 |
| 0061 | Rip rap, class II (3635000000-E) | TON | 130 | $90.00 | $77.40 | $88.50 | $93.00 | $80.00 | $94.25 |
| 0062 | Rip rap, class B (3649000000-E) | TON | 345 | $70.00 | $63.50 | $81.50 | $75.00 | $80.00 | $82.00 |
| 0063 | Geotextile for drainage (3656000000-E) | SY | 2,760 | $5.00 | $5.00 | $12.00 | $9.50 | $5.00 | $7.00 |
| 0064 | Supports, 3-LB steel U-channel (4072000000-E) | LF | 90 | $7.15 | $9.82 | $9.00 | $8.00 | $10.00 | $8.00 |
| 0065 | Sign erection, type E (4102000000-N) | EACH | 4 | $285.00 | $114.53 | $105.00 | $75.00 | $300.00 | $317.00 |
| 0066 | Sign erect, reloc ** GRD MTD - (D) (4116100000-N) | EACH | 2 | $175.00 | $136.35 | $125.00 | $245.00 | $250.00 | $195.00 |
| 0067 | Disposal of sign system, U-channel (4155000000-N) | EACH | 4 | $10.00 | $21.82 | $20.00 | $10.00 | $2.00 | $11.10 |
| 0068 | Disposal of support, U-channel (4192000000-N) | EACH | 2 | $10.00 | $21.82 | $20.00 | $10.00 | $2.00 | $11.10 |
| 0069 | Stockpile sign, D, E or F (4237000000-N) | EACH | 2 | $10.00 | $54.54 | $50.00 | $245.00 | $2.00 | $11.10 |
| 0070 | Work zone signs (stationary) (4400000000-E) | SF | 192 | $8.50 | $8.18 | $7.50 | $12.00 | $15.00 | $9.45 |
| 0071 | Work zone signs (barricade mounted) (4410000000-E) | SF | 36 | $9.85 | $8.45 | $7.75 | $12.00 | $9.00 | $11.00 |
| 0072 | Drums (4430000000-N) | EACH | 71 | $100.00 | $54.54 | $55.00 | $60.00 | $65.00 | $54.64 |
| 0073 | Barricades (type III) (4445000000-E) | LF | 32 | $26.00 | $32.72 | $35.00 | $35.00 | $25.00 | $29.00 |
| 0074 | Flagger (4455000000-N) | DAY | 10 | $500.00 | $574.20 | $700.00 | $500.00 | $1,100.00 | $1,364.04 |
| 0075 | Thermoplastic pavement marking lines (4", 90 mils) (4685000000-E) | LF | 3,850 | $2.00 | $2.18 | $1.50 | $2.00 | $2.00 | $2.00 |
| 0076 | Paint pavement marking lines (4") (4810000000-E) | LF | 6,310 | $0.50 | $0.55 | $0.50 | $1.00 | $0.50 | $0.70 |
| 0077 | Generic pavement marking item (EA) - inlaid raised pavement markers (4895000000-N) | EACH | 16 | $55.00 | $59.99 | $436.85 | $25.00 | $55.00 | $575.00 |
| 0078 | Temporary silt fence (6000000000-E) | LF | 3,510 | $2.50 | $2.67 | $3.25 | $3.15 | $2.45 | $2.45 |
| 0079 | Stone for erosion control, class A (6006000000-E) | TON | 135 | $10.00 | $63.20 | $86.50 | $85.00 | $80.00 | $113.45 |
| 0080 | Stone for erosion control, class B (6009000000-E) | TON | 1,785 | $10.00 | $63.50 | $55.00 | $82.00 | $80.00 | $114.50 |
| 0081 | Sediment control stone (6012000000-E) | TON | 835 | $10.00 | $52.70 | $55.00 | $92.00 | $75.00 | $56.00 |
| 0082 | Temporary mulching (6015000000-E) | ACRE | 8.50 | $1,200.00 | $1,363.50 | $1,500.00 | $2,100.00 | $1,250.00 | $1,250.00 |
| 0083 | Seed for temporary seeding (6018000000-E) | LB | 600 | $5.00 | $1.09 | $4.00 | $1.00 | $1.00 | $1.00 |
| 0084 | Fertilizer for temporary seeding (6021000000-E) | TON | 4 | $1,200.00 | $1,090.80 | $1,400.00 | $450.00 | $1,000.00 | $1,000.00 |
| 0085 | Temporary slope drains (6024000000-E) | LF | 270 | $10.00 | $41.00 | $32.00 | $76.00 | $45.00 | $42.00 |
| 0086 | Safety fence (6029000000-E) | LF | 320 | $1.85 | $2.35 | $3.15 | $2.00 | $2.15 | $3.00 |
| 0087 | Silt excavation (6030000000-E) | CY | 4,400 | $5.00 | $25.10 | $5.00 | $26.00 | $50.00 | $10.70 |
| 0088 | Matting for erosion control (6036000000-E) | SY | 18,650 | $1.75 | $2.02 | $1.75 | $1.90 | $1.85 | $1.85 |
| 0089 | Coir fiber mat (6037000000-E) | SY | 5,580 | $5.00 | $6.54 | $6.00 | $6.75 | $6.00 | $6.00 |
| 0090 | 1/4" hardware cloth (6042000000-E) | LF | 190 | $10.00 | $4.36 | $14.60 | $6.00 | $10.00 | $4.00 |
| 0091 | Low permeability geotextile (6043000000-E) | SY | 600 | $10.00 | $6.20 | $5.50 | $2.40 | $8.00 | $6.15 |
| 0092 | **" temporary pipe - (18") (6045000000-E) | LF | 130 | $75.00 | $63.00 | $92.20 | $271.00 | $120.00 | $55.00 |
| 0093 | Special stilling basins (6070000000-N) | EACH | 12 | $1,000.00 | $1,263.90 | $1,588.00 | $1,300.00 | $2,400.00 | $1,410.00 |
| 0094 | Flocculant (6071002000-E) | LB | 360 | $10.00 | $5.45 | $5.50 | $8.00 | $1.00 | $1.00 |
| 0095 | Coir fiber wattle (6071012000-E) | LF | 470 | $8.00 | $10.91 | $15.25 | $13.00 | $10.00 | $10.00 |
| 0096 | Coir fiber wattle barrier (6071014000-E) | LF | 293 | $10.00 | $10.91 | $15.15 | $13.00 | $10.00 | $10.00 |
| 0097 | Coir fiber baffle (6071030000-E) | LF | 420 | $6.00 | $10.36 | $7.20 | $6.50 | $9.50 | $9.50 |
| 0098 | **" skimmer - (1-1/2") (6071050000-E) | EACH | 2 | $2,500.00 | $1,359.50 | $4,000.00 | $1,200.00 | $3,500.00 | $2,000.00 |
| 0099 | **" skimmer - (2-1/2") (6071050000-E) | EACH | 1 | $3,000.00 | $1,937.90 | $5,000.00 | $1,200.00 | $3,900.00 | $2,500.00 |
| 0100 | Seeding and mulching (6084000000-E) | ACRE | 12 | $2,000.00 | $2,999.70 | $2,800.00 | $3,000.00 | $2,750.00 | $2,750.00 |
| 0101 | Mowing (6087000000-E) | ACRE | 9 | $150.00 | $218.16 | $100.00 | $175.00 | $200.00 | $200.00 |
| 0102 | Seed for repair seeding (6090000000-E) | LB | 100 | $6.00 | $5.45 | $10.00 | $5.00 | $5.00 | $5.00 |
| 0103 | Fertilizer for repair seeding (6093000000-E) | TON | 0.25 | $1,750.00 | $872.64 | $2,000.00 | $700.00 | $800.00 | $800.00 |
| 0104 | Seed for supplemental seeding (6096000000-E) | LB | 250 | $6.00 | $3.27 | $12.00 | $5.00 | $3.00 | $3.00 |
| 0105 | Fertilizer topdressing (6108000000-E) | TON | 7.50 | $1,300.00 | $1,036.26 | $1,200.00 | $700.00 | $950.00 | $950.00 |
| 0106 | Impervious dike (6111000000-E) | LF | 160 | $75.00 | $242.90 | $100.00 | $100.00 | $222.00 | $245.00 |
| 0107 | Specialized hand mowing (6114500000-N) | MHR | 10 | $75.00 | $109.08 | $80.00 | $45.00 | $100.00 | $100.00 |
| 0108 | Manual litter removal (6114800000-N) | MHR | 5 | $65.00 | $255.20 | $60.00 | $45.00 | $175.00 | $73.00 |
| 0109 | Litter disposal (6114900000-E) | TON | 1 | $500.00 | $1,020.80 | $430.00 | $300.00 | $250.00 | $1,265.00 |
| 0110 | Response for erosion control (6117000000-N) | EACH | 25 | $100.00 | $163.62 | $250.00 | $450.00 | $150.00 | $150.00 |
| 0111 | Concrete washout structure (6117500000-N) | EACH | 2 | $1,500.00 | $985.43 | $1,000.00 | $1,000.00 | $5,400.00 | $2,000.00 |
| 0112 | Reforestation (6123000000-E) | ACRE | 0.10 | $6,000.00 | $4,908.60 | $10,000 | $8,500.00 | $4,500.00 | $4,500.00 |
| 0113 | CM&R temp STR *********** - (18+28.00 -L-) (8007000000-N) | LS | 1 | $950,000 | $783,535 | $800,000 | $1,325,000 | $1,339,000 | $2,000,000 |
| 0114 | Remv exist STR ****** BRG (402) - (18+28.00 -L-) (8035000000-N) | LS | 1 | $175,000 | $186,445 | $270,000 | $300,000 | $121,400 | $143,845 |
| 0115 | Asbestos assessment (8065000000-N) | LS | 1 | $10,001 | $849.73 | $3,000.00 | $1,700.00 | $1,300.00 | $1,700.00 |
| 0116 | 3'-0" dia drilled piers in soil (8105520000-E) | LF | 54.30 | $1,200.00 | $1,350.82 | $1,725.00 | $1,300.00 | $2,160.00 | $1,405.00 |
| 0117 | 3'-0" dia drilled piers not in soil (8105620000-E) | LF | 36 | $1,200.00 | $1,539.58 | $2,300.00 | $1,300.00 | $1,070.00 | $4,525.00 |
| 0118 | Permanent steel casing for 3'-0" dia drilled pier (8111200000-E) | LF | 36 | $10.00 | $10.91 | $10.00 | $375.00 | $124.00 | $203.00 |
| 0119 | CSL testing (8115000000-N) | EACH | 1 | $2,500.00 | $2,727.00 | $2,500.00 | $1,000.00 | $25,000 | $3,100.00 |
| 0120 | Uncl STR excav sta ***** - (18+28.00 -L-) (8121000000-N) | LS | 1 | $20,000 | $59,889 | $125,000 | $95,736 | $25,000 | $30,000 |
| 0121 | Reinforced concrete deck slab (8147000000-E) | SF | 6,699 | $80.00 | $73.21 | $100.00 | $80.00 | $100.00 | $77.00 |
| 0122 | Grooving bridge floors (8161000000-E) | SF | 7,005 | $1.00 | $2.66 | $0.87 | $2.50 | $1.11 | $1.50 |
| 0123 | Class A concrete (bridge) (8182000000-E) | CY | 97.40 | $1,700.00 | $2,198.26 | $2,500.00 | $3,200.00 | $1,995.00 | $2,900.00 |
| 0124 | BRG appr slab *********** - (18+28.00 -L-) (8210000000-N) | LS | 1 | $65,000 | $69,756 | $125,000 | $75,000 | $50,000 | $80,000 |
| 0125 | Reinforcing steel (bridge) (8217000000-E) | LB | 22,623 | $2.00 | $0.80 | $2.45 | $2.50 | $1.75 | $3.00 |
| 0126 | Spiral column reinforcing steel (bridge) (8238000000-E) | LB | 2,621 | $4.00 | $2.19 | $5.63 | $5.00 | $3.50 | $5.00 |
| 0127 | 45" prestressed concrete girders (8262000000-E) | LF | 626.96 | $475.00 | $564.30 | $700.00 | $675.00 | $580.00 | $585.00 |
| 0128 | Pile DRV equip setup ** steel piles - (HP 12 X 53) (8328200000-E) | EACH | 16 | $1,200.00 | $1,692.83 | $7,000.00 | $2,200.00 | $1,170.00 | $1,600.00 |
| 0129 | HP 12 X 53 steel piles (8364000000-E) | LF | 320 | $50.00 | $70.82 | $65.00 | $50.00 | $290.00 | $150.00 |
| 0130 | Vertical concrete barrier rail (8505000000-E) | LF | 317.13 | $160.00 | $212.04 | $218.67 | $250.00 | $170.00 | $240.00 |
| 0131 | Rip rap class II (2'-0" thick) (8608000000-E) | TON | 1,047 | $90.00 | $83.72 | $64.85 | $73.00 | $100.00 | $92.00 |
| 0132 | Geotextile for drainage (8622000000-E) | SY | 1,164 | $4.00 | $5.45 | $3.75 | $12.50 | $15.00 | $9.75 |
| 0133 | Elastomeric bearings (8657000000-N) | LS | 1 | $16,000 | $8,782.20 | $75,000 | $30,000 | $28,000 | $12,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NCDOT's tabulation for this contract. NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.
Every contract let that day: NCDOT letting of February 18, 2025. Compiled by Mirage Metrics.