NCDOT letting results, February 18, 2025
19 contracts let by North Carolina DOT on February 18, 2025, $155,623,976 in low bids, a median of 3 bidders per contract.
- Owner
- North Carolina DOT
- Contracts
- 19
- Low bids, total
- $155,623,976
- Data through
- 20 OCT 2026
Contracts let that day
| Contract | Project | County | Bids | Low bidder | Low bid | Second bid | Gap | Source |
|---|---|---|---|---|---|---|---|---|
| C204994 | DRAINAGE, PAVEMENT REHABILITATION AND BRIDGE REHABILITATION. US-74 (FUTURE I-74) FROM 0.11 MILES EAST OF US-701 BUSINESS TO 0.17 MILES WEST OF NC-214 | Columbus | 3 | S T Wooten Corporation | $22,950,356 | $25,803,248 | +12% | NCDOT |
| C204980 | GRADING, DRAINAGE, PAVING, AND WALLS. GREAT WAGON ROAD FROM SR-1001 (SHALLOWFORD ROAD) TO SR-1308 (LEWISVILLE-VIENNA ROAD) | Forsyth | 7 | Branch Civil Inc | $19,785,000 | $21,177,562 | +7.0% | NCDOT |
| C205062 | ROCK EMBANKMENTS, PAVING, AND GUARDRAIL. NC-80 FROM MM 11.77 TO MM 12.16 (SITES 45, 46, 47, AND 48) | Mcdowell | 3 | Watson Contracting Inc | $14,798,700 | $15,573,718 | +5.0% | NCDOT |
| C205054 | MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 1 SECTION OF US-601, 1 SECTION OF NC-150, 5 SECTIONS OF NC-801, AND 12 SECTIONS OF SECONDARY ROADS | Rowan, Davie | 3 | NJR Group Inc | $11,502,013 | $11,785,661 | +2.0% | NCDOT |
| C204940 | GRADING, DRAINAGE, PAVING, AND BRIDGE PRESERVATION. US-74 (FUTURE I-74) AT INTERCHANGE WITH US-1 (EXIT 311) | Richmond | 3 | Barnhill Contracting Company | $8,453,440 | $8,685,000 | +3.0% | NCDOT |
| C204989 | PAVEMENT REHABILITATION. I-77 FROM MILEMARKER 52.6 TO MILEMARKER 56.77 | Iredell | 1 | Maymead, Inc. | $7,563,219 | NCDOT | ||
| C205026 | ROADWAY AND BRIDGE CONSTRUCTION (EXPRESS DESIGN BUILD). BRG #100428 ON SR-2429, BRG #100203 ON SR-2416, BRG #100307 ON SR-2426, AND BRG #100424 ON SR-2786 | Buncombe | 3 | NHM Constructors, LLC | $7,561,270 | $8,395,060 | +11% | NCDOT |
| C205027 | ROADWAY AND BRIDGE CONSTRUCTION (EXPRESS DESIGN BUILD). BRG #100200 AND BRG #100175 BOTH ON NC-197, BRG #100147 ON SR-2173, AND BRG #100139 ON SR-2171 | Buncombe | 2 | Lee Construction Co of the Carolinas, In | $7,477,000 | $8,629,560 | +15% | NCDOT |
| C205049 | DRAINAGE, PAVING, AND PAVING., DRAINAGE, PAVING, AND SIGNALS. US-19/US-23 BUS (HAYWOOD RD) FROM US-19/US-23/US-74 (PATTON AVE) TO RIDGELAWN RD | Buncombe | 2 | Watson Contracting Inc | $6,985,219 | $8,313,031 | +19% | NCDOT |
| C204978 | GRADING, DRAINAGE, PAVING, AND STRUCTURE. BRIDGE #840082 OVER THE DAN RIVER ON SR-1674 (SHEPPARD MILL ROAD) | Stokes | 8 | Smith-Rowe, LLC | $6,592,206 | $7,674,174 | +16% | NCDOT |
| C205053 | MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 1 SECTION OF US-70, AND 31 SECTIONS OF SECONDARY ROADS | Iredell | 2 | Maymead, Inc. | $6,273,018 | $9,441,879 | +51% | NCDOT |
| C205029 | ROADWAY AND BRIDGE CONSTRUCTION (EXPRESS DESIGN BUILD). BRIDGE #560042 OVER IVY CREEK ON SR-1576 (BEND OF IVY RD) AND BRIDGE #560304 OVER SR-1183 (UPPER SHUTIN | Madison | 2 | Kemp Sigmon Construction Co Inc | $5,900,000 | $6,920,000 | +17% | NCDOT |
| C204883 | GRADING, DRAINAGE, PAVING, AND STRUCTURES. BRIDGE #800040 OVER NORTH FORK FIRST BROAD CREEK ON NC-226 | Rutherford | 6 | Kemp Sigmon Construction Co Inc | $5,593,808 | $6,688,028 | +20% | NCDOT |
| C205028 | ROADWAY AND BRIDGE CONSTRUCTION (EXPRESS DESIGN BUILD). BRG #100135 ON SR-2153, AND BRG #100132 ON SR-2150 BOTH OVER IVY CREEK | Buncombe | 1 | Reeves Construction Company | $5,515,353 | NCDOT | ||
| C205048 | MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 1 SECTION OF NC-10, AND 53 SECTIONS OF SECONDARY ROADS | Catawba | 2 | Maymead, Inc. | $4,777,967 | $5,574,878 | +17% | NCDOT |
| C204979 | GRADING, DRAINAGE, PAVING, AND STRUCTURE. BRIDGE #290076 OVER I-40 ON SR-1436 (PINEBROOK SCHOOL RD) | Davie | 10 | Smith-Rowe, LLC | $4,230,585 | $4,462,485 | +5.0% | NCDOT |
| C205052 | MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 6 SECTIONS OF SECONDARY ROADS | Wake | 4 | FSC II LLC DBA Fred Smith Company | $4,159,627 | $4,380,097 | +5.0% | NCDOT |
| C205055 | MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 1 SECTION OF US-1, 1 SECTION OF NC-177, AND 6 SECTIONS OF SECONDARY ROADS | Richmond | 2 | FSC II LLC DBA Fred Smith Company | $3,362,164 | $3,437,109 | +2.0% | NCDOT |
| C205051 | MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 1 SECTION OF NC-109, 1 SECTION OF NC-134, AND 3 SECTIONS OF SECONDARY ROADS | Montgomery | 4 | FSC II LLC DBA Fred Smith Company | $2,143,032 | $2,144,070 | 0.0% | NCDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than NCDOT received, the others did not match their published totals and are left out. Each contract number opens its full bid tabulation.